package 4 addendum 4 - National Highway Authority

o
NATIONAL HIGHWAY AUTHORITY
Procurement & Contract Administration Section
i,
28 Mauve Area, G-9/I, Islamabad I
051-9032722, E 0S1-9260419
No. 2(447)/ cM(P&cA)/ NHA/ 20 14/ I g )-
March l?
,2or4
To,
All Prospective Bidders
Subject:
MINUTES OF' 2"d PRE-BID MEETING AND ADDENDUM NO. O4:
& Protection Works
River I
Chachran Sharif with Kot Mithan.
Reference: 2ndPre-Bid Meeting held on 24-02-2014 for the subject works.
Minutes of 2'd Pre-Bid Meeting and Addendum No. 04 for the
subject works are enclosed herewith, please.
(PARr{ASHI
Director (P&CA)
Enclosure: (if
(iil
Minutes of 2nd Pre-Bid Meeting (O2 pagesf.
Addendum No. 04 {.1,2Pagesf.
Cc:
Member (Planning), NHA, Islamabad.
General Manager (P&CA), NHA, Islamabad.
trr'
"f
,
,
-t
MTNUTESop z'd pnn-ntr mnEtlNG Hnlu oN zarHrnBRUARy. 2o1a
of River Traini
Works (Consis
Banks. Gunda Bunds and Cunette) of ShaheedBenazir Bhutto Bridse over River
Indus Connectins Chachran Sharif with Kot Mithag
01.
2n0Pre-Bid Meeting was held in NHA Auditorium, HQ, Islamabadat 1400 hours
on 24thFebruary 2014 to discussthe revised drawings and BOQ and to clarify the points, if any,
raisedby the Bidder. The following attendedthe meeting:
.
National Highway Authority
i.
Mr. ParvezIqbal Sulehri
ii.
Mr. Asim Amin
iii,
Mr. Parkash
v.
Mr. Nand Kumar Soofi
vi.
Mr. Asad Rahat
General Manager (P&CA)
General Manager (Design)
Director (P&CA)
Director (QS)
Deputy Director (P&CA)
Design Consultant (M/s EA Consulting)
l.
ll.
Mr. HarisAqil
Mr. SiddiqSulemani
Bidders
i.
Mr. NaeemA. Khan
ii.
Mr. NaseerA Shafai
ii.
Mr. Parvaiz Gori
iv.
Engr. Nadeem Khan
v.
Mr. QaiserMehmood
vi.
Mr. Ghulam Hasan
vii.
Mr. NK
viii.
Lt. Col. Atif
General Manager (Technical)
Head of Highways
M/s FWO - M/s Sachal(JV)
M/s FWO - M/s Sachal(JV)
M/s ZKB
M/s Chaudhry EngineersAssociates
M/s Matracon Pakistan
M/s Habib ConstructionServices
M/s SalmanEnterprises
M/s FWO
02.
The said meeting was started with the welcomed to all participants by General
(P&CA)
Manager
and General Manager (Design). All the participants were asked to give
introduction about himself. All the participantsthen introduced themselvesalongwith the name of
their firms.
03.
General Manager (Design) explained the revised drawings and BOQ of the subject
works that the changesare in stone quantities and apron width. The bidders were askedto collect
revised drawings and BOQ which will be later issuedformally through Addendum No. 04.
04.
Afterwards, the bidders were askedto come forward with their questions/
and the bidders raised certain questions / queries regarding subject works. Questions /
ies / answersof the sameare as
followins details:
Sr.
Questions/ Queries
No.
Ouestionsof M/s ZKB:
Replies/ Answer
Mobilization
Advance may
increased15% insteadof IjYo.
11
be Agreed to be put up for consideration of higher
authorities. In case of approval, the same will be
informed later throush Addendum
In C-Factor, weightages of HSD and Weigh,tages are as per PEC Standard Price
Labour may be increased.
Adiustmentprocedure.
Ouestionof M/s RMC
1ll
Provision of SecureAdvance may be
includedin Biddine Documents.
ri i -.- l JI 5 \
w--
Page I of2
ti*'3f
\!'ri. , t
\.r-.'t='
.,.1.
t+'
)
Queritions of M/s FWO:
Partially taking over certificate may
be considered for Cunette / Gunda
Bund, River Training Works.
Provision of Coffer dam may be
inc,luded in BOQ as a separateitem
(as PD-FWO informed that the river
is changing its direction and may flow
through under construction bridge in
the comins monsoonseason).
lV.
05.
Not agreed.
Not agreed,However, General Manager (Design)
informed that if it happenedthen the samecan be
made later on in contractas separateitem.
The meeting concludedwith a vote of thanks to all the participants.
---ooOoo---
Page 2 of 2
ADDENDUM NO. 04
Package'4: Construction of River Training & Protection Works
(Consisting of Guide Banks, Gunda Bunds and Cunette) of ShaheedBenazir
Bhutto Bridge over River Indus Connectine Chachran Sharif with Kot Mithan
The following amendmentshave been made in the Bid Document under this Addendum, which
shall be read and construedas an integral part of Bid Document and shall take precedencein case
of any conflict / ambiguities in the Bidding Document and other provisions of the Bidding
Document.
1. Biddine Data:
Refer page-35of Bidding DocumentITB Clauses20.1(a) and23.l, Para-Sof AddendumNo.
01, Para-l of Addendum No. 02 & 03 for the subiect works, the dates be changedas
27thMarchzllfi.
2 . Appendix-D to Bid" Bill of Ouantity (BOQ):
Refer page-49of Appendix-D to Bid, Bill of Quantity of Bidding Document be replacedwith
the amendedAppendix-D to Bid, Bill of Quantity attachedat Annexure-I.
a
J.
Special Provllions (SP):
Refer pages from 105 to 111 (07 Nos.) of Special Provisions of Bidding Document be
replacedwith the amended07 pagesattachedat Annexure-Il.
4 . Tender Drawings. Volume-III:
Following pages of Tender Drawings Volume-III be replaced with the amended pages
attachedat Annexure-Ill:
(D
Page-5of DrawingNo. EA-684-SB-H-1001.
(ii)
Page-7of DrawingNo. EA-684-SB-H-2001.
(iii)
Page-8of Drawing No. EA-684-SB-H-2002.
5 . Other terms and conditions shall remain same.
i,,
i'
tj
Package- : Consfruction of River Training & Protection Works (Consisting of Guide Banks, Gunda Bunds and Cunette)
of ShaheedBenazir Bhutto Bridge over River Indus Connecting Chachran Sharif with Kot Mithan.
Bill of Quantify
Pay Item
No.
Item Description
Unit Quantities
l0l
Clearing and grubbing
SM
73,000
t04
Compaction of Natural Ground
SM
73,000
l06c
ExcavateSurplusCommonMaterialin dry/wetarea
CM
203,500
CM
500,000
Rate
in figures
in words
Amount
(Rs.)
Formation of Embankmentfrom Roadway Excavation in
l08a common Material (in drylwet area) for Apron, Guide Banks,
Cunetteetc.
201
GranularSubbase
CM
7,700
509b
RiprapClassB
CM
12,600
6 1 3 a Sprigging
SM
37,000
6l3b
SM
37,000
SM
37,000
sP-2.1Filter Layer(Medium)
CM
17,500
sP-2.2 Riprapon Slopes,ClassDl (W50: 80 - 100kg)
CM
79,s00
sP-2.3 Riprapon Apron,ClassD2 (W50 = 100- 120kg)
CM
360,000
6l3c
Sodding
Top Soil
TOTAL
P
*\
'Iotal
Amount rn FrgureRupees:
r
Name oI UontractoranclStamp
z5
An"n-fi "'/
u
Q
co'struction
of shaheed
tsenazir
Bhutto
Bridge r$#*,
Connecting
Chachran
Sharif"""r
with Kot Mithan
I
t
Contract
4: Riverfrainffi
SI}-2 RIVER TRAINING WORK AND PROTtrCTION WORI(
2"1
Description
River trainingand protectionwork shall includeconstruction
of guidebanks,guide
walls, gunda bund, cunette,bank protection,flooring
and appioach embalkment
protectionas requiredfor ensuringsafetyof the bridge
structureand its approaches
againstdalnageby flood/flowing water. Construction
of various comporilnts shall
conformto drawingsandthesespecificationsor as directed
by therngin;er"
2.2
GuideBank
2'2'1 This work shallconsistof construction
of ernbankment
of guidebankandprovisionof
pitching/revetm.ent
on slopes,apronetc. as indicatedon th" drawingin accordance
with thesespecifications
or asapprovedby theEngineer.
2'2'2 The alignmentand layoutof guidebanks
shall be as indicatedon the drawingor as
approvedby the Engineer. The constructionof embanlcnent
ro. tuiJe bank shali
conformto provisions
of items100,105,106
& 108of NliA Genera'l
Specifications.
Riprap/Pitching,filter undemeathpitching and ap.on
etc., shall be as per these
specifications'
\[4tereever,clearing& grubling uni
or naturatlround is
requiredthe sameshouldconformto provisionsof "o*pu"iion
items i00, 10trand 104 of NF{,{
GeneralSpecifications.
For sub-baseprovidedas shownin drawingsshoulJconform
to provisionsof items200 and20r of NHA Generar
specifications.
2'2"3 Guidebanksshallgeneraliybe macleo1'locally
availablematerialsfrom the river bed
preferablycohesionless materials.Trial piis
shall Le taken in borrow holes to
examinesuitabilityof soil firr constructionand
also to decidethe types of eart6
tnovingmachinery.tobe aranged.The boruowpits
shouldbe sufficienui u*uy rro*
tlre locationof the launchingup.ou.No borow pitr
rrt*ra
be dug on the ri'er side of
. theguidebanks.
" constructionof guidebanksshallbe
talienin handalongwith the constructionof the
bridge'Every effort shall be madeto complete
the work of the guide bank in o'e
working season.,
where thereis any,doubt;bou;
within one wotking season,suitatle measures";;piJtion ortne who,leguide bank
rh;ii;* plannedand executedfor
protectionof completedwork. The construction
of,guide bank shall be staftedfi"orn
abutmenttowardsupstream.
2"2.4
S:::::':rl,:
:t.^:r::,?nd
pitchingof the guidebankssharrgeneraily
conformro
#;j;i'Jd *:ru;il:
;lX,l::,3i
iio"3":!.,".!!.!::,
fry:tliati,ns.
.3uffi.i,nrl.,gtr,
in
on
e
t"
ty"
y:^:yl_
*"
rh
y*
;
;;
;;;il:#
#
:; #'k-,ffiffifl:
:lj;* i I
b:"oyq1..i.J
;fi1,1"80
il";;'"ft;;illlii:!1il,;,ff"i
f#,;l::.::'i:,"::*ilT'1
un
i,^.
u
l
uur
'
;;#"il?ji'l,lllfl
ffi fi:
3*11t"
m:":1,::
*l:s"
l:sh
"y
:J*';;il
our
d*beIeft;"u
b;"ilfi
;;,r#,#J
H:,T ;.l],1
H"jli":
:f l*^9119:
tt\
"
lH,iltiJl,i#llllil;
il
;"'-J.ff:fff'-iJ
il,;'T:L,:tn{ll:[TJ
ffif#Hj
n::::::"d
11##'s'
appropriate
earth
moving rnachinery and trained staff
be deployed in
ec
cf.^",'.
^,^
/.1^,
construction.
J,
\,'
Constructionof ShaheedBenazirBhutto Bridge over ltiver Indus
ConnectingChachranSharifrvith Kot Mithan
t
t
Contlact4: Rivert.uinffi
2"2"5 The Contractorshall furnish his planningand methodologyfor
approvalof the
Engineerregardingtranspotlof stonesfromthe quarriesto the siteof work
takinginto
accountthe quantitiesof stonerequiredto be transportedevery day,
truck, etc.,
deployed,availableferry or boatsandlabouravailablefor loadingand
unloaoingand
for laying within the time frame for constructionof guide bank.io*quut,
.eserveof
stonesshould be maintainedfor major works as decidedby the Engineer.
Reserve
stonesshallbe stackedfar awayfrorn the mainchannelof the river.
2'2'6 Wherethe alignmentof guide bank or the approachembankment
crossesbranch
channelof the river,the branchchannelmay be"eitherdiverted.to
the mainchannelof
the river rvith.thehelp of spurs,etc..orclosld by a properlydesigned
closingdyke or
closurebu'd (gundabund)beforetaking,p ,onit u"tion ofguide
bank.
2"3
APRON
2.3,1 General
This work shall consistof furnishingand placinga protective
coveringof erosion
resistantmaterialas riprap. This work shail conJistof laying
boulders/rockpieces
directlyon the bedof riversfor protectionagainstscour"The
work shallbe camiedout
strictly in acoordance
with the specificatio-ns
and in confonnity with lines, grades,
thicknessetc shownon drawings.
2"3.2 LayingBoulderApron
To ensureregularand orderlydispositicnof the flull intended
quantityof stonein the
apron,the surfaceon which the apronis t6 be laid shall
be leveleduno [.*p*r"o ro,
the lengthandwidth as shovri1on.ih, dru*ings"In case
the surfaceon *hirh apronis
to be la.idis belowthe low waterlevel,the giund t.olt
,rruybe raiseJupio to* *ut*,
ievel by dumpingearthand the apronlaid ihereon.The quantity
of stonerequiredi*
apronshallbe rervottedout by takingthetoe oipiifhing
at higherlevei"
rlie rock/stonefbr apronshallbe placerlby-equipment
on the surfa{leandto the depth
indicatedon drawings"Tlte rock/itonestrattue placec
to the f'ull coursethicknessin
one operationand in such manneras to avoid displacement
of urrderlyingmaterial.
The rock/stoneshall be placed in a nrannerthat
will ensurethat the rock/stoneis
reasonablyhonrogenouswith the large pieces
uniformly distributedand firmly
interlockedrryiththe smallerpieces.unirputt,
nrlinl irre voids betweenlarge
I pieees.
somehandplacingrnaybe requiredto provide
ilffi;
uniformsurface.
2.4
PITCHING / REVETMENT ON SLOPES
2.4"1 Description
This work sl,all consistof coveringof the slopes
of guide banks,r;rainilgworkqand
road embankments
with erosionrisistantrnaierial;-iron",boulders,
over a layer of
granularmaterialcalledfilter as shownon
the drawings" while river sideslopesare
given this protectionagainstriver action,
the rearrropJr, not subjectedto direct attack
of theriver, may be protectedagainst-ordinary
wave splashingby ().3-0.drnetrethick
cover of riprap, glavey or silty earth and
turfed. The rnaterialsshall be testedin
accordance
with theseSpecifications
andshallmeetthe prescribedcriteria.
constructionof shaheedBenazirBhuttoBridgeoverRiverIndus
Con
ChachranSharifwith Kot Mithan
t
Contract
4; RiverTraininganOprote"tioffiiffi
I
The work shall conformto theseSpecifications
and shall be in conformitywith the
lines,grades,thicknessshownon tlie drawingsandshallmeetall prescribed
standards
ofacceptance.
2"4.2 Fitching/Filtermedia
2.4"2.IPitclring/riprap
The pitchingshall be providedas indicatedin the drawings.The thickness
and the
shapeof the stonepitchingshallbe asshownon the drawing"
The stonesshall compriseroughlydressedand shaped,set on their edges
with their
longestdimensionat right anglesto theflow of watei.
The bed upon which riprap shall be laid, shall be firm, oompacted
and of specified
thicknessof duly approvedgranularrnaterial.
Stones/Rock
piecesshallbe laid with close,brokenjoints andshaltrbe firmly bedded
into the slopeand againstthe adjoiningrocVston"u.rn. stone/rockpieces
shall be
laid perpendicular
to the slopewith endsin contact.The riprap shall be thoroughly
compactedas_construction
progresses
and the finishedsurfate,hull pr"r.nt an even,
tight surface.Interstices
betweenrock/stone
piecesshallbe chinkedwittr spattsfirmly
rammedin.
stones/rockpiecesshallbe placedin layersto its futl thicknessin
a singleoperation
and after placing shall be reworkedto fonn a dense,well-knit,
interlockedand
unifofinly gradedlayer.It shall be pkncedso that rock pieces jifferent
of
sizesare
evenly distributed, wittrout cluster of smalleuoiL/rton*
pieces. Excessiye
displacement
of the underlyinglayershallbe avoided.
I
Stones/rock
piecesshallbe placeddirect,afterthe underlyingfilter layer(rnedia)has
been finishedto the final srope,gradeand rines as shown
on the ,lru*ing, o, u,
. directedby the Engineer.
2.4.2.2Material Requirementfor Apron & Riprap/pitching
The size/'rn''eight
of stoneshouldbe as indicatedon drawing.The stonesused
shallbe;
field stoneor rough ulhewn quaruystone,sound,hard,
durabledense,resistantto the
actionof air & water,fairly regularin shapeof rectangie
and suitablein all respectfor
the purposeirltended' Eachplecesof stone/rocksha'il
be fiee from cracks,fissures,
planesof weakness,subjectto markeddeterioration
by water or weat6erand/orotlier
flaws which could lead to breakageshall not u" ur"i.
eny pi*"" showingsignsof
significantedge and colner *.u, o, of severerounding
oi detoriationshall not be
accepted'Materialfor apronshallbe obtainedfrom quarfr
proposedby thecontractor
and approvedby the Engineer.
stones
are
preferable
Quarry
to round bouldersas the
latter roll off easily. Angular stones fit into each
other better uno rruu. gooa
interlocking characieristics]
Rock/Stonepieces shall be obtainedfrom a quarry
proposed by the contractor and approviq of
the Engineer"with regard to the
consistencyof stone/rockpieces
and the overallipfrurun.,, of the works the
"oiour
useof stone/rockpiecesfrom more
thanone sourceand/oicornprisingmorethan ons
rcck type
shall'ot be permitted,exceptwhereupprou"au, ilunou*eer.
Theuseof
',' i:
:.:.;
ii
!/
l)
t
I
Construciion
of Shaheed
BenazirBhuttoBridgeoverRiver Indus
ConnectingChachrarrSharifwith,Kot Mithan
Contract4: River TrainingandprotectionWorks
agglomerates
or Alluvial cobbleswill not be permitted.Roundbouldersshall not be
allowed. Sarnplesof the stone/rockpiecesto be used shall be submittedto and
approvedby theEngineerbeforeanypieceis usedin thepennanent
work.
The sizeof stone_shall
be as largeas possible.In no caseany fragmentshall weigh
lessthan 60 kg. The specificgravityof stonesshallbe as high as p6ssibleand it
shall
not be lessthan2'60.The sizesof spallsshallbe a minirnumof is ** and shall
be
suitableto fill the voidsin thepitching
Abrasionafter 1,000revolutionsin a Los Angelesmachinein accordance
with ASTM
C 535 shallnot exceeda lossin weightof 40%.The soundness
shallbe measuredin
sodiumsulphatesolutionin accordance
with ASTM C88,and the weight lossafter 5
cycles shall not exceed5%. The absorptionmeasuredin accordan*riittt AST14
C
97 shallnot exceed2o%.
Rock piecesshallnot containimpuritiesor foreignmattersin suchquantity
as would
be damagingto the environmentor the integrity ortn. works"
The averagedensityof the stones/rocli
piecesshall not be lessthan 2,600kg/cu m,
u'ifh not morethan l0% of the stones/roCk
piecesby weightcomprisingpieceshaving
a densitylesstlran 2,550kg/cu rn. Not more tltan5Taof tit" rlon"rlro"k pieces
by
weight shall comprisepieceswhosemaximumdirnensionis greaterthan
tluee times
their minirnumdimension,wherethe minimumdimensionis Jefinedas
the minimum
distancebetweentwo parallelstraightlinesthroughwhichthe piece
"unluripurr.
The "Wx" of_the stones/rock
piecesis definedas the weight, which exceedsthe
weight of xYoby weight of the rock grieces.
The medianstoneweight (Wuo)of,the
stones/rock
piecesshall not be lessthan the value definedon the firawinis
for the
particulartype of pitcltinglriprap/apron.
The ratio of Ws5to Wrs shallnot be lessthan
" threenor greaterthan ten, andiro pieceof rock shall weigh more than five tirnesthe
requiredvalueof W5e'The valueof w3o shallnot be lessthan
haif of mininrumvalue
., of Wso.
Not morethan2o/oof the stones/rock
piecesshallcomprisepiecesweighinglessthan
onethirtiethof requiredvalueof W5s.
2.4.2.3Filterlayer (media)
'fhe
materialfor the filter shall consistof sand,glavel, stone
or coarsesa.nd.To
preventescapeof the embankment
malerialthroughthe voidsof the stone/rockpieces
as well as to allow free movementof water witliout creating
any uplift head on the
pitching/ripraP.,
o1e nrorelayersof gradedmaterials,commonlyknown as
a filter
91
layer(rnediu'r),shalr
beprovidedundeineaththepitching/riprap.
The gradationof the filter rnaterialshaltsatisfythe following
requirements:
Provisionof a suitabtydesignedfilter is o""*rrury under
the slopepitching/riprapto
prevent tbe escape.of underlying etnbankment
material throujh the voids of
stone/rockpieceswhensubjectedto tho attackof flowing
waterand wave aetion,etc.
In orderto achievethis requirernent,the filter may be
frovided i6l..gneor more layers
satisfying
thefoltowingcriteria:
i,.:'iiffir,-
o
a
Construction
of Shaheed
BenazirBhuttoBridgeoverRiver Indus
ConnectingChachranSharifwith Kot Mithan
Contract4: River Training andprotectionWoii<s
D 15(Filteg
<5
D 85 (Base)
D 15(Filte$
4<
<20
D 15 (Base)
D 50 (Filter)
<25
D 50 (Base)
Filter desigllmay not be requiredif ernbankment
consistsof CH soilswith liquid lirnit
greaterthan50 resistantto surfaceerosion.In this case,if a layerof materialis used
as beddingfor pitching,it shallbe well gradedandits D 85 sizeshallbe at leasttwice
the maximurnvoid sizein pitching
In the foregoing,D 15lneansthe sizeof thatsievewhichailows l5 per centby weight
of the filter materialto passthroughit andsirnilaris the meaningof D 30 andD g5.
If more than one filter layer is required,the samerequirementas above
shall be
lbllowed for each layer. Tlie finei filter shall be consideredas basematerial
for
selectionof coarserfilter.
The filter shall be compactedto a firm condition"The thicknessof filter generally
is
of the orderof 200 mrn to 300 mm. Wherefilter is providedin fwo layers,
thickness
of eachlayershallbe 150mm"
2.4.3 Construction0perations
Reforelayingrhe pitching/riprap,the side of banksshallbe
trirnrnedto the required
' slopeandpro_files
put up by meansof line andpegsat intervalsof 3 metresto
ensure
regularstraightwork and a uniform slopethrougliout.Depressions
shall be filled and
thoroughlycompacted.
The filter granular material shall be laid over the prepared
base and suitably
compacted
to the thicknessspecifiedon the drawings.
The lowest courseof pitching/riprapshall be startld from the
top of apron and built
up in coursesupwards.
The stonepitching/riprapshall colnlnencein a trench
below the toe of the slope.
stoneshallbe placedby derick or by handto the required
length,thicknessanddepth
cotiformingto the drawings.stoneslrockpiecesshail
be setnonnal to the slope,and
placedso that the largestdimensionis perpendicuru,
to the face of the slope,unless
suchdimensioris g..ut", trra' the specifiedthickness
of pitching.
The largeststonesshall be placedi, the bottomcourses
and for use as headersfor
subsequent
courses.
t$r
Fr-+y'
l ,i"li
"',..1/
of Shaheed
Construction
BenazirBhuttoBridgeoverRiver Indus
ConnectingChachranSharif with Kot Mithan
Contract4: River Training and ProtectionWorks
o
f
In handplacedpitchingiriprap,the stoneof flat stratifiednatureshouldbe placedwith
the principalbeddingplanenormalto the slope.The patternof laying shall be such
that thejoints are brokenand voids are minimumby packingwith spalls,wherever
necessary,
andthe top surfaceis as smoothaspossible.
Whenfull depthof pitching/riprap
can be fonnedwith a singlestone,the stonesshall
be laid breakingjoints and all intersticesbetweenadjacentstonesshall be filled.in
with spallsof thepropersizeandwedgedin with hammersto ensuretight packing.
When fwo or more layersof stonesmust be laid to obtainthe designthicknessof
pitching, dry rnasonryshall be used and stonesshall be well bonded"To ellsure
regular and orderly dispositionof the full intendedquantity of stone as shown,
templatecrosswalls in dry masonryshall be built abouta metrewide and to the full
height of the specifiedthicknessat suitable intervalsand all along the length and
width of thepitching.Within thesewalls the stonesshallbe handpacftedasspecified.
2"5
MEASUREMENTS and PAYMENT
2.5.1 Measurement
The differentitemsof work involvedshallbe measured
asprovidedbelow:
a. clearing& Grubbingreferitem 101.3of NHA Generalspecifications
b' Compactionof NaturalGroundreferitem 104.3of NHA GeneralSpeeifications
a. RoadwayandBorrowExcavationreferitem 105.4of NHA GeneralSpecifications
d' Excavationof Unsuitableor Surplusmaterialrefer item 106.3of NHA General
Specifications
" e. Formationof Embankment
referitem 108.4of NFIA GeneralSpecifications
' f. GranularSubbase
referitem 201.4of NHA Generalspecifications
g' Springging, Sodding and Top Soil refer item 613.4
of NHA
Specifications
h.
General
Filter layer (Medium):The quantitiesto be measuredfor payrnentshall be the
numberof cubicmetersof completedandacceptedwork ptacedto the designated
thicknesson slopesasshownon Drawings.
i . RipRapClassB referitem 509.4NHA GeneralSpecifications
j.
StonePitching/RipRap
ClassDl (Wso: g0-100kg) andD2 (Wso: 100_l50kg):
The quantitiesto be measuredfor pavementshall be the number
of cubic rnetJis
of completedand acceptedwork placedto the designated
thicknessof slopesas
shownon Drawings.Slopepreparitionshallnot be rieasuredfor payment
but will
be considered
subsidiaryto the iternof .,stonepitching/riprapandToifilter layer,,
The computationof tlre quantitiesof abovementionediterns
will be basedon the
volutnswithin thetheoreticallimiting dimcnsionsdesienated-on-the
Drawinss.
'..q."Drawings,
ffiz
l,' ''
?^y-rt r^-
. I
r
l l
l /
|
.
Constructionof ShaheedBenazirBhutto Bridge over River Indus
ConnectingChachranSharif with Kot Mithan
Contract4: River Training and protection Works
I
'.l
2"5.2 Payment
The acceptedquantitiesmeasuredas providedaboveshallbe paid for at the contract
unit price for the Pay Item listed below and shownin the giil of
euantities,wirich
price and paymentshall constitutefull compensation
for furnishingall materials,
hauling,placing,watering,rolling, labour,equipment,
toolsand incidJntalsnecessary
to completethe item.
Pay ltem
No.
Description
101
Clearing& Grubbing
SM
104
Cornpactionof Natural Ground
SM
I 06c
ExcavateSurplusCommonMaterial in dry/wetarea
CM
l0Ba
Fonnationof Ernbankmentfi.om
RoadwayExcavationin commonmaterial
(in drylwet area)for Apron, GuideBanks,
Cunetteetc
CN4
201
GranularSubbase
ch4
509b
RipRapClassB
CfuT
673a
Sprigging
SN4
613b
Sodding
sxd
613c
Top Soil
SM
sP-2.1
Filter Layer(Mediurn)
CIVI
5P.2,2
Rip Rapon Slopes,
ClassDl (Wso:80-100kg)
CM
sP-2.3
Riprapin Apron,ClassD2 (Wso: 100-120
kg)
C\4
Unit of
1\{easurement
103
-?*-1t--q
'I
t
o
J
r>@
r
P@
a@
ll-
v@
/el@
,rl
I
APPROACH ROAD
AHIR
-v
7
@
*]
@
KoMqqQ{--
PIR
l"*o"o".o
"*,oou
NOTES:
N
D
IJ
R.
S
E
R.
t
&Fd/q
-</
@
=l
ql
trl
1)
STATED.
OTHERWISE
AREIN METERS
UNLESS
ALLDIMENSIONS
2I
SIDE.
THAN6OKGSHALL
BEUSEDON RIVER
WEIGHING
LESS
NO STONE
3)
WHICH
BIGVOIDS
NOTHAVTNG
THROUGH
BETAKENtN PLAC|NG
STONES
CARESHOULD
ON SLOPES,
BEATTHEBOTTOM
AND
STONES
SHOULD
SMALLER
COMPARATIVELY
SWIRLING.
WATERWILLCORSE
ONEATTHETOP,
LARGER
4)
THAN50,
OF"CH"SOtLWITHLIQUIDLIMITGREATER
CONSTSTS
OFGUIDEBANKS
tF EMEANKMENT
LAYER
MAYNOTBEREQUIRED.
FILTER
5)
T FM O N S O O N ,
BELOW
H F LB E F O RTEH EO N S EO
N O P O R T I OO
N FG U I D EB A N KS H O U I -BDEL E F T
6 ) THE RIVERS
7\
ANYTEMPORARY
WORKS
IN DRYCORIDITIONS.
THEGUIDE BANKSSHOULDBECONSTRUCTED
SHALLNOTBEPArDSEPARATELY
DRYCONDTTTONS
(E.G.COFFERDAMETC)REQUTRED
TO ACHTEVE
PAYITEMS.
INCIDENTAL
TOOTHER
ANDSHALLBECONSIDERED
'--l'
:r'\/t\/,\-r
D
q
tA
?,
"(,
\s
k%o
ISSUEDFORTENDER:
t\
s@
Y,/
C L I E N T- :
REVISEDTENDERDRAWING
1
0
F E B - 1 / REVISEDTENDERDRAWING
\PR-,1
: D . N C DATE
TENDERDRAWINGS
DESCRIPTION
ISLAMIC REPUBLIC OF PAKISTAN
NATIONAL HIGHWAY AUTHORITY
ISLAMABAD
HAS
ATIF
HAS
ATIF M . S . S CONSULTANTi
HAS
BY
tvt.D.D
CKD
M,S,S
TAN
-
^'t
-O
o
PROJIC
RIVER INDUS CONNECTING CHACHARAN SHARIF
WITH KOT MITTHAN
GACKAGE 4: RIVER TRAINING & PROTECTION WORKS)
DRAWN BY
EA Consulting ( Pvt.) Limited
BY
DESIGNED
(Formerly Engineering Associates)
ECONOMISTS
& PLANNING
EXPERTS
ARCHITECTS,
ENGINEERS,
CONSULTING
S,IMRAN
HASAN
M.SIDDIQ
APPROVED
B)
TANVEER
JTLE
LAYOUTPLANOF GUIDEBANKS
\CArE:
'1;5ooo
' ..-.
.t rIDWL.NO.
I rn oa+ sa-tr .rboy'
'aXz-tc
fly
' ::'
-oven
LAYER(MEDIA)'
o.zov TH. FILTER
D T T A I LA
3_3
SECTION
(sHnrr)
ISSUEDFOR TENDER:
S E C T I O N4-- 4
(oowrl sTREAM
NosE)
CLiENT-
NOTE:STATED.
OTHERWISE
UNLESS
AREIN METERS
1- ALL DIMENSIONS
ffi
#F.
-
s,'rD
-
'ROJECT:
ISLAMIC REPUBLIC OF PAKISTAN
NATiONAL HIGHWAY AUTHORITY
ISLAMABAD
EA Consulting ( Pvt.) Limited
(FormerlyEngineering Associates.)
EXPERTS
&PLANNING
EcoNoMlsrs
ARcHlrEcrs,
ENGINEERS,
coNsuLTtNG
dirNirnucuoN
oF sHAHEEDBENAzIRBlrurro BRIDGEovER
RIVER INDUS CONNECTINC CHACHARAN SHARtr
WITHKOTMITTHAN
(PACKAGE 4: RIVER TRAII'{ING & PROTECflON WORKS)