Dealing with rapidly changing weather The Furioso

6
®
Routes
COLETANCHE
NEWS
March 2012 / n°6
Events
This coming spring, we will be attending:
Geo-Congress 2012 organized by the American Society of
Civil Engineer:
March 25-29, 2012
Oakland, CA, USA
Booth 205
The 2012 RPIC Federal Contaminated Sites National
Workshop, April 30 to May 3, 2012 in Toronto, ON, Canada.
Geo-Americas 2012, May 1st- 4th / Lima Peru / Booth 48.
We will be presenting 4 papers.
COLETANCHE® is a bituminous
geomembrane manufactured by
bitumen
impregnation
of
a
non-woven geotextile produced by the
US firm Johns-Manville.
Dealing with rapidly
changing weather
Sand cover
Bitumen
Non-woven
polyester
Glass fleece
Anti-root
film
The Furioso Mine project
in Chilean Patagonia
Coletanche; the difference
Installation of geomembranes in regions of the world characterized by rapidly changing weather
conditions, high and/or low temperatures, and very high wind conditions always poses problems.
The solution is simple:
1.
Use a heavy geomembrane,
2.
Line a small area whenever weather conditions allow, and
3.
Place the cover soil (ballast) as quickly as possible.
COLETANCHE® allows the implementation of this simple solution because:
• it is heavier than any of the other geomembranes. Therefore COLETANCHE® will not be uplifted in
wind speeds up to 50 mph (80 kmh).
• it can be installed by a general local contractor (or the operator/owner’s own forces) and does not
requires a specialty subcontractor. This allows full schedule flexibility and eliminates concerns of
stand-by cost associated with weather delays.
Why did they choose Coletanche ?
Closure of the wasterock facility at the Furioso Mine in Chilean Patagonia presented the challenges
highlighted above. The owner and his consultant evaluated different geosynthetics options and selected COLETANCHE® because it was the only geomembrane that can be installed in strong wind and
even snowy weather.
Geographic Location
The mine is approximately 46 miles (75 km) southwest of
Chile Chico at an elevation of about 4,600 ft. (1,400m)
above sea level at latitude 46°33'S and longitude
071°42'W. The mine is essentially non-accessible during
the winter months (between mid-March through December) due to the high snowfall and poor road conditions.
Daytime temperatures in the winter can be as low as
-13°F (-25°C) with wind speed in excess of 50 mph (80
km/h).
◄Conditions on 11 January 2012, the day we were supposed to start.
A typical mid-summer day in Patagonia!
Naches, WA - 2006
The wasterock facility was designed to contain
approximately 223,000 cubic yards (170,000 cubic
meters) of waste rock material. Approximately 16 acres
(6.5 ha) of Coletanche were installed.
◄ A couple of days later, the facility is ready for Coletanche
Note the nature and size of particules in support soil.
Installation
Note that COLETANCHE® is flat on the ground
support with no wrinkles, waves, or kinks due to
its low thermal expansion and therefore the cover
soil can be pushed over the Coletanche without
problems.
Wasterock facility during lining ►
The installation team consisted of Patagonian workers
hired by the mine and trained by Coletanche staff.
They placed and welded all the panels of COLETANCHE®.
COLETANCHE® toughness and strength allows the
contractor to use regular equipment near and on the
geomembrane thereby facilitating construction and reducing the schedule.
COLETANCHE® will be connected to the rock outcrop in
the background.
Summary
The benefits from using a Coletanche
based solution rather than using
another flexible geomembrane were:
Financial
In 45 days we placed:
• 700, 000 ft2 (65, 000 m2) of Coletanche
• 39, 000 ft (12, 000 m) of seaming
• 8 inches (20 cm) of cover soil instead of 3ft (1m)
over 16 acres (6,5 ha).
• Erosion/biotic barrier consisting of 20 inches (50cm) minus rock.
• Performed all CQA activities.
• Local work force was used rather than a specialty contractor
• The ability to work whenever weather allowed.
+
• A final cover system less expensive than one built with any other geomembrane.
Convenience
Protection of
Environment
and Sustainability
• No speciality geosynthetics sub-contractor meant full control of schedule.
• Use of available large mining equipment.
• The final cover protects the waste rock from precipitation that causes acid generation for years to come.
• Reduction of cover thickness led to reduced CO2 emission through reduction of truck traffic
For more technical information or to organize a brown bag
please contact Axter Coletanche Inc.
2000 rue Peel - suite 670 - Montreal, QC, H3A 2W5 - Canada
Phone: (1) 514 903 1912 - Email: [email protected]
www.coletanche.com