Water Security Advisory Group - Minutes No. 03

OurWaterSecurity
Minutes of the Water Security Advisory Group
Date
27 May 2014
Location
Civic Reception Room
Start Time
5:30pm
Finish Time
9:15pm
Chair
GROUP MEMBERS
Stakeholder Groups
☒
Paul Gregory
Primary Member
Present
Cairns Regional Council
Cairns Regional Council
Cairns Regional Council
Cairns Regional Council
CRC Water and Waste
Mareeba Shire Council
DNRM
Cr Bob Manning
Cr Richie Bates
Cr Steve Brain
Peter Tabulo
Paul Utting
Cr Tom Gilmore
Shannon Dempster
☐
☒
☒
☒
☒
☒
☐
DEWS
Kirsten Shelley
☐
WTMA / DEHP
MDWSS LAMC
Advance Cairns
UDIA Cairns
CAFNEC
MRACRP
Cairns River Improvement Trust
Andrew MacLean
Joe Moro
Trent Twomey
Adam Gowlett
Angelika Ziehrl
Bruce Corcoran
Rob Lait
Yuriko Nakachi-Monaei
(arrived 5:50pm)
Mani Sunai-Norris
(arrived 5:50pm)
Steve Purcell
Allan Dale
(departed 7:00pm)
Suzanne Gibson
Jeff Pezzuti
☒
☒
☐
☒
☒
☒
☒
Cairns YEA!
Cairns YEA!
RAPA
General Community
Alternate
Member
Neil Quinn
Present
☒
Jon Turner
☐
Darren
Thompson
Bruce Jennison
Scott Dixon
Mark Matthews
☒
☐
☐
☒
☒
☒
☒
☒
General Community
☒
General Community
☒
ASSOCIATE MEMBERS
Group
Member
Present
Queensland Health
Andrew D’Addona
☐
Mulgrave Central Mill
Peter Flanders
☒
Stanwell – Barron Hydro
Michael Sinclair
☐
GBRMPA
Phil Laycock
☐
Sunwater
Charlie Martens
☐
Canegrowers
Richard Hesp
☐
PROJECT TEAM
CAIRNS REGIONAL COUNCIL
CONSULTANTS
Jon Turner
Manager Infrastructure
Erin Holton
Gilbert & Sutherland
☒
Executive Engineer –
Neil
Ben Millar
Gilbert & Sutherland
☒
Planning
Sutherland
Coordinator Regulatory
Mark Wuth
Phil Matthew
Gilbert & Sutherland
☒
& Systems Support
Strategic Programs
Erik Zesers
Pat Nixon
Jacobs SKM
☐
Coordinator
Personal Assistant – GM
Carol Mills
Paul Dennis
Jacobs SKM
☐
Water and Waste
Owen Droop
OD Hydrology
☒
☒
☒
☒
☒
☒
OurWaterSecurity
Meeting No. 3 – 27 May 2014
Minutes of the Water Security Advisory
Group
Item
1
2
3
4
What
Declare Meeting Open

Welcome to Country conducted by Chair.

Apologies from Shannon Dempster (DNRM).

Alternates attending noted.
Previous Meeting Minutes
 Minutes of Meeting No. 2 carried with amendment that
Jon Turner was the alternate for Paul Utting and not
Paul Gregory.
 Chair directed members’ attention to new handout
material provided by Project Team:
o
Checklist for Issued Documentation
o
Meeting No 3 Reference Paper
o
Project Team “pen portraits”
 Neil Sutherland explained meeting agenda in context
of overall meeting process and introduced presenters
from Project Team.
Levels of Service (continuation)
 OD presented further information on Levels of Service
(LOS), as outlined in attached slides.
 OD emphasised the supply shortfall risk and
importance to define it when considering and
developing LOS.
 Responding to Cr. Gilmore query, OD clarified the
interpretation and use of “duration” criteria with
subsequent discussion amongst group. Examples of
other water supply schemes indicate “duration” criteria
or targets are not commonly defined or adopted.
 Responding to Cr. Brain query, OD clarified
contingency response plans are considered to be the
physical works required, including implementation
timeframes, rather than the funding reserve or ability
to finance.
 In relation to comparison of Cairns LOS performance
with other water supply schemes, OD referred to
benchmarking work currently being carried out by
DEWS and additional information will be available at
future meeting(s).
Normalised Multiple Objective Analysis – Finalisation
of Objectives and Indicators
 EH presented Step 4 goals, and the process and
outcomes of the compatibility review.
 EH, PM, and NS facilitated discussion with and
among members to review the refined list of
objectives.
 Adam Gowlett queried if an objective should be
defined for aesthetic values or qualities, for example,
in relation to beautification of parks and gardens or
enjoyment of lakes/dams/rivers. OD clarified it is
typically incorporated into LOS criteria recognising
landscape irrigation as a user type, or minimum water
level as criteria.
Who
Noted / Action
Chair
Chair
Moved by Adam Gowlett,
seconded by Angelika
Ziehrl.
Chair
Neil S
Owen D
Agreed aesthetic values
or qualities of parks and
gardens, for example,
may be incorporated into
LOS.
Erin H,
Phil M,
Neil S
Project Team to define
minimum
irrigation
requirements for this user
type when considering
LOS.
All members agreed by
Doc # 4328109v6
OurWaterSecurity
Meeting No. 3 – 27 May 2014
Minutes of the Water Security Advisory
Group
Item
What
Refined list with notes from discussion attached
(Table 1).
 Final list of agreed objectives, by consensus, is
attached (Table 2).
Potable Demand Reduction
 Due to time constraints, this agenda item was
rescheduled to be presented and discussed at
Meeting No 4.
General business
 Next meeting scheduled for Tuesday 24 June 2014.
 Agreed new meeting start time is 5:00pm.
 Chair noted that a Register of Correspondence will be
maintained and presented at each meeting.
 Homework for next meeting:
o Each
member
is
to
assign
weights,
independently, to the final agreed list of objectives
and indicators.
 Next meeting topics
o Findings of market research
o NMOA Step 4 Stage 2 - Group weighting of
objectives
o Adopt initial Levels of Service
o Demand management
o Finalise demand forecasts
Meeting close
 Meeting closed at 9:15pm
Who

5
6
7
Doc # 4328109v6
Pat N
Noted / Action
consensus that list is final.
Noted.
All to note new meeting
start time is 5:00pm.
Chair
Project Team to maintain
Register of
Correspondence.
Project
Team
will
distribute instructions and
forms for members to
assign
weights
to
objectives.
Chair
OurWaterSecurity
Minutes of the Water Security Advisory Group
Table 1: Normalised Multiple Objective Analysis – Refined Objectives As Discussed with Notes of Discussion
ID
Objective
Indicator
Compliance
Objective
Notes from
Discussion
Environmental Objectives
En1
Meet all licence conditions
Compliance with Licence conditions
✔
OK
En2
Meet all Environmental Flow Objectives and Water
Allocation Security Objectives under the relevant Water
Resource Plans e.g. The Wet Tropics WRP, Barron
WRP and Walsh WRP
Compliance with EFO's and WASO's under relevant
WRP's.
✔
OK, but recategorise part for
WASO’s to
Economic
Objectives.
En3
Minimise extent of disturbance to World Heritage Areas
Ha
En#
Minimise extent of disturbance to Zone A and B of the
Wet Tropics World Heritage Area
En4
Minimise carbon emissions
Greenhouse gas emissions [t CO2-eq/y]
Re-order to below
En7
En5
Minimise extent of other native forest flooded or
disturbed
Ha
OK
En6
Minimise extent of other land flooded or disturbed
Ha
OK
En7
Maintain extent of wetlands
Ha
OK
En8
Minimise disturbance to populations of threatened,
endangered, endemic species and/or migratory
species.
No. of species affected. Assessed through desktop
assessment of available mapping.
OK
En9
Maintain or enhance groundwater resources
Abstraction-recharge is greater than or equal to 0
OK
En#
Provide additional flow for environmental benefit above
the WRP requirements
ML
New objective
OK
✔
New compliance
objective
OurWaterSecurity
Meeting No. 3 – 27 May 2014
Minutes of the Water Security Advisory Group
ID
Objective
Indicator
Compliance
Objective
Notes from
Discussion
Technical Objectives
T1
Ensure compliance with defined Levels of Service
criteria (to be defined by WSAG)
Compliance with defined LoS
OK with agreement
to be Compliance
Objective
T2
Ensure losses within the system are minimised
Losses (ML/a) captured as part of the water balance
Re-word Objective
“…are minimised to
an optimal level”.
Re-word Indicator
“…balance, with
benchmarking
comparisons”.
T#
Alternative water sources are identified
ML
New objective
Social Objectives
S1
Ensure the serviced community has adequate access
to water
Proportion of service connections with unrestricted
access
OK
S2
Support community aspirations for sustainability
ML recycled water, no. water efficient devices etc.
OK
S3
Protect culturally significant sites (Indigenous and
historical)
Compliance with existing ILUA, Native Title
✔
OK
S#
Consult with relevant parties with respect to Cultural
Heritage
Agreement established (Yes/No)
✔
New Compliance
Objective
Doc # 4328109v6
OurWaterSecurity
Meeting No. 3 – 27 May 2014
Minutes of the Water Security Advisory Group
ID
Objective
Indicator
Compliance
Objective
Notes from
Discussion
Economic Objective
E1
Minimise life cycle costs
Cost
Delete, adopt as a
principle when
developing the
strategy
E2
Minimise cost to consumer
$ per year per household
Delete, adopt as a
principle when
developing the
strategy
E3
Ensure availability of water is not a constraint for new
developments
ML for new development
Amend wording –
replace
“development(s)”
with
“opportunity(ies)”
E4
Aim to achieve cost recovery for water services
Indicator - $/ML vs revenue
OK
E5
Ensure the strategy delivers regional benefit wherever
possible.
ML supply
OK
E#
Meet all Water Allocation Security Objectives under the
relevant Water Resource Plans e.g. The Wet Tropics
WRP, Barron WRP and Walsh WRP
Compliance with WASO's under relevant WRP's.
✔
Part of objective recategorised from
Environmental
Objectives.
Compliance with ADWG biological and chemical
standards
✔
OK
Human Health Objective
H1
Ensure water supplied is fit for purpose and poses no
risks to human health
Doc # 4328109v6
OurWaterSecurity
Meeting No. 3 – 27 May 2014
Minutes of the Water Security Advisory Group
ID
Objective
Indicator
H2
Preserve absolute minimum availability of water for
hygiene and sanitary purposes
Minimum L/p/d has 100% availability
✔
OK
H3
Minimise risk associated with infrastructure
Adherence with Dam Safety Regulations
✔
OK
Doc # 4328109v6
Compliance
Objective
Notes from
Discussion
OurWaterSecurity
Meeting No. 3 – 27 May 2014
Minutes of the Water Security Advisory Group
Table 2: Normalised Multiple Objective Analysis – Final Objectives and Indicators
ID
Objective
Indicator
Compliance
Objective
Environmental Objectives
En1
Meet all licence conditions
Compliance with Licence conditions
✔
En2
Meet all Environmental Flow Objectives under the relevant Water
Resource Plans
Compliance with WASO's under relevant WRP's.
✔
En3
Minimise extent of disturbance to World Heritage Areas
Ha
En4
Minimise extent of disturbance to Zone A and B of the Wet Tropics
World Heritage Area
Ha
En5
Minimise extent of other native forest flooded or disturbed
Ha
En6
Minimise extent of other land flooded or disturbed
Ha
En7
Maintain extent of wetlands
Ha
En8
Minimise carbon emissions
Greenhouse gas emissions [t CO2-eq/y]
En9
Minimise disturbance to populations of threatened, endangered,
endemic species and/or migratory species.
No. of species affected. Assessed through desktop
assessment of available mapping.
En10
Maintain or enhance groundwater resources
Net recharge (recharge-abstraction) is greater than or equal to
zero
En11
Provide additional flow for environmental benefit above the WRP
requirements
ML
Doc # 4328109v6
✔
OurWaterSecurity
Meeting No. 3 – 27 May 2014
Minutes of the Water Security Advisory Group
ID
Objective
Indicator
Compliance
Objective
Technical Objectives
T1
Ensure compliance with defined Levels of Service criteria (to be
defined by WSAG)
Compliance with defined LoS
T2
Ensure losses within the system are minimised to an optimal level
Losses (ML/a) captured as part of the water balance, with
benchmarking comparisons
T3
Alternative water sources are identified
ML
✔
Social Objectives
S1
Ensure the serviced community has adequate access to water
Proportion of service connections with unrestricted access
S2
Support community aspirations for sustainability
ML recycled water, no. water efficient devices etc.
S3
Protect culturally significant sites (Indigenous and historical)
Compliance with existing ILUA, Native Title
✔
S4
Consult with relevant parties with respect to Cultural Heritage
Agreement established (Yes/No)
✔
Economic Objective
E1
Ensure availability of water is not a constraint for new opportunities
ML for new opportunity
E2
Aim to achieve cost recovery for water services
Indicator - $/ML vs revenue
E3
Ensure the strategy delivers regional benefit wherever possible.
ML supply
E4
Meet all Water Allocation Security Objectives under the relevant
Water Resource Plans
Compliance with WASO's under relevant WRP's.
Doc # 4328109v6
✔
OurWaterSecurity
Meeting No. 3 – 27 May 2014
Minutes of the Water Security Advisory Group
ID
Objective
Indicator
Compliance
Objective
Human Health Objective
H1
Ensure water supplied is fit for purpose and poses no risks to human
health
Compliance with ADWG biological and chemical standards
✔
H2
Preserve absolute minimum availability of water for hygiene and
sanitary purposes
Minimum L/p/d has 100% availability
✔
H3
Minimise risk associated with infrastructure
Adherence with Dam Safety Regulations
✔
Doc # 4328109v6