The 2013 – 2019 Winona Bridge project is MnDOT’s first Contract Manager/General Contractor (CMGC) project BENEFITS OF THE CMGC PROCUREMENT METHODOLOGY The importance of starting construction work on the project in Sepotember of 2014 cannot be understated. To accomplish this goal, the use of the CMGC procurement methodology was the key critical element to success. CMGC allowed accelerated design plan review and approvals and very compressed bid package advertisement timelines. This allowed work packages 1-3 to all stay on schedule. The overarching goal of placing Trunk Highway 43 traffic on the new bridge by fall 2016 is currently on target. The Winona Bridge project management team feels there is less than a 5% chance this same goal would have been met with traditional design-bid-build (DBB) contracting, while at the same time DBB would have led to increased costs. To meet the aggressive schedule, the project team has jointly developed numerous submittals under the Professional/ Technical contract utilized during the CMGC design phase. Long lead time items such as the cofferdam designs, vibration and settlement monitoring plan, project schedule, environmental management plan and storm water prevention plan, and the scour mitigation plan were all done well in advance of when they would have been in DBB. This fact alone would have delayed any new construction on the project until the spring of 2015 using the DBB process. SAVING TIME CAS E S TU DY CMGC PROCUREMENT METHODOLOGY S AV E S M O N E Y Delaying the start of permanent construction into 2015 under DBB would have added approximately $1 million to the project costs due to wage increases, inflationary costs, and wintertime construction. In addition, the DBB approach would have put the project schedule at the mercy of spring 2015 Mississippi River flooding. Any river flooding, such as in 2014, could have led to significant project delays causing flooding risks (costs) of around $750,000. With DBB, the placement of traffic on the new bridge likely would have been in the fall of 2017, with a conservative cost increase of $1.75 million (not including the increased costs of maintaining the existing bridge, or factoring the increased risk of a bridge closure). $1.75 million ESTIMATED CMGC COST SAVINGS FOR MORE INFORMATION ON THE WINONA BRIDGE PROJECT AMES CONSTRUCTION IS THE WINONA BRIDGE CMGC CONTRACTOR TERRY WARD, PE, MSISE, PMP, PROJECT MANAGER (507) 286-7688 • [email protected] The Burnsville, Minnesota, company is also the GENERAL CONTRACTOR on the nearby DRESBACH BRIDGE PROJECT (shown). Or visit WWW.MNDOT.GOV/WINONABRIDGE and WWW.FACEBOOK.COM/WINONABRIDGE A history of quality bridge projects, on-time delivery and professionalism. Case Study 7
© Copyright 2024 ExpyDoc