HNTB Field Office 680 Rhode Island Ave, NE Second Floor, Unit N Washington, DC 20002 Phone: (202) 733-1970 Fax: (202) 627-2395 Construction of Pedestrian/Bicycle Bridge Along the Metropolitan Branch Trail Over CSX Tracks at the Rhode Island Avenue Metro Station D.C. Contract No.: DCKA-2013-C-0005 Federal Aid Project No. CM-8888 (392) CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT 09/20/2014 – 09/26/2014 Project Website: http://rhodeislandavepedbridge.com Rhode Island Avenue Pedestrian Bridge Construction – Truss Bridge Assembly at the Trail Side – 09/26/2014 CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT WEEK OF 09/20/2014 PAGE 2 of 11 1. EXECUTIVE SUMMARY Project Description: Work under this project consists of the construction of a new Pedestrian/Bicycle Bridge and associated ramps and stairs along the Metropolitan Branch Trail over CSX Tracks at the Rhode Island Avenue WMATA Metro Station, NE. Proposed work will include but not be limited to: Construction of a new bridge to include a steel truss composed of hollow structural steel sections. Light weight reinforced concrete deck, 1” acrylic bridge barrier and steel wire mesh netting. Construction of ramp structures consisting of light weight precast ramp sections integrally supported with cast-in-place concrete pier columns and footings, installation of combination of bridge railing panel barriers on ramps. Construction of pier foundation on reinforced concrete shafts. Construction of stairs, landings and connecting pathways to proposed Metropolitan Branch Trail and the WMATA Rhode Island Metro Station. PEPCO fed light pole system. Landscape work including sodding and drainage. Coordination of the project to Stakeholders, CSX and WMATA. The bridge design includes wheelchair and bicycle accessible ramps to enhance safety for all users and lighting features to allow for greater visibility. As part of the design a stairway will be placed on the west side of the bridge to provide direct access to the Rhode Island Avenue Metro Station. The total value of the contract at award to Corman Construction Company was $8,475,253.50. Corman received the notice to proceed with the contract work on August 19, 2013 with total project duration of 505 days. CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT WEEK OF 09/20/2014 PAGE 3 of 11 2. STATUS OF CONSTRUCTION / PROGRESS SUMMARY Progress Summary: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. Continued assembling, splicing sections and bolting the truss bridge per the approved shop drawings. Continued welding the angles and the SIP truss Bridge deck pan support at the Trail side. Skidmore test done on the TCB A325 and A325 Hexagonal bolts at the Trail side. The wrench check on torqued bolts was done on the splice joint bolts at 110R and 105L at the Trail side. Began to install CSX hand rail clamps for the CSX protection shield. Installed a waterproofing membrane at Retaining Wall area and finish backfilling the Trail abutment with number 57 stone. Tested granular base layer for density which was compacted by Corman at the Trail Abutment approach. Continued reviewing Work Zone Safety and Erosion and Sedimentation (E&S) control on the project. Continued Constructability Review of Plans and site conditions to assist Corman Construction in any potential future conflict resolution issues. Continued to maintain and manage the SharePoint and update the project website regularly. Maintained project filing and document management systems (hard copy and electronics). Updated and maintained sets of drawings, specifications, and logs. Updated/reviewed of resident concerns about the project (No other outstanding issues or complaints). 3. ISSUES / ACTION ITEMS - Ongoing Issues / Items: No new items. New Issues / Items: No new items. Action Items: o Wired Lighting Change Order. 4. MEETINGS / PROJECT COORDINATION - Weekly progress meeting was held on Thursday 09/25/2014 at the field office. See Meeting Minutes for more details. 5. DAILY WORK PERFORMED Field construction activities performed during this period: Saturday 09/20/14 1. The general contractor Corman Construction arrived on site to continue assembly of the truss bridge per the approved shop drawings according to Rev. 3. The contractor worked on splicing sections A103, A104 and A106. All bolts have not been installed to snug-fit position at this time as the contractor has been adjusting the grade of the bridge continuously by rigging the bridge at particular locations in order for members to align and connect. Corman continued to use a pneumatic jack and come-along to maneuver truss members into alignment. Once all sections of the bridge were connected the contractor shot grades for the bridge and attempted to get the bridge as close to grade as possible. 2. CSX Flagger Danny Meyer was on site on this date. 3. WMATA Flagger Stephon Paige was on site on this date. CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT WEEK OF 09/20/2014 PAGE 4 of 11 Monday 09/22/14 1. The general contractor Corman Construction arrived on site to begin backfilling the Trail Abutment retaining wall. The contractor removed steel forms from the wall facing and plugged all Shea bolt holes. Corman then proceeded to install a waterproofing membrane on all construction joint per DDOT Standard Drawing 703. Corman backfilled the wall with approximately 9 inches of fill material on the inside face and then placed stone atop. Corman test pitted to find the infiltration trench drain located along the east fence of the trail work area; once located Corman started to tap into the drain and connect the 10” PVC pipe. 2. The general contractor Corman Construction had the Skidmore test done on the TCB A325 and A325 Hexagonal bolts. Skidmore test results for TCB 7/8inch diameter were 42000Ibf (2#) and 5100Ibf as against the minimum of 39000Ibf, and they were 58000Ibf (2#) and 6200Ibf as against the minimum of 39000Ibf for the A325 Hexagonal bolt. Corman did the final check on the camber and started torqueing the bolts in place. 3. CSX Flagger Danny Meyer was on site on this date. 4. WMATA Flagger Stephon Paige was on site on this date. Tuesday 09/23/14 1. The general contractor Corman Construction arrived on site to continue backfilling the trail abutment with #57 stone between approximate Station markers 47+00 and 47+50. The contract plans showed compact fill to be placed at this location but according to the approved change order the contractor submitted to place #57 stone in lieu of compact fill. Corman placed the stone in small lifts and employed compactive effort by means of a jumping jack along the edges and a remotely controlled sheep foot vibratory roller. Corman placed and compacted fill material for the 2’–0” bench shown on the outside face of the retaining wall per the approved plans. 2. The general contractor Corman Construction, second crew had the Skidmore test done on the TCB A325 and A325 Hexagonal bolts. Skidmore test results for TCB 7/8inch diameter were 39000Ibf (2#) and 51000Ibf as against the minimum of 39000Ibf for the lot number 16426 (7/8” dia.x2 ¼” TC Bolt) and 46000Ibf (2#) and 49000ibf for the lot number 17460 (7/8” dia.x2 ½” TC Bolt). The wrench check on torqued bolts was done on the splice joint bolts at 110R and 105L (topmost eight) because of the limited spaces to accommodate the calibrated torqueing wrench. Torqueing values recorded were 660,640, 700(2#), for the joint number 110R and 620(3#) and 600 for the joint number 105L compared to the reference torque value of 580 determined with the Skidmore test calibration. Corman was also on the job site installing the angle (1.5inchx2inch) support at 12inch centers for the SIP form installation. 3. CSX Flagger Danny Meyer was on site on this date. 4. WMATA Flagger Stephon Paige was on site on this date. Wednesday 09/24/14 1. The general contractor Corman Construction arrived on site to finish backfilling the trail abutment with #57 stone between approximate Station markers 47+00 and 47+50. The contractor rolled the material with a sheep foot remotely controlled compactor and a sled tamper. The structure which was standing at approximate Sta. 47+00 was demolished by Corman to allow for the surveyors to shoot the proper line and grade. The contractor accepted a delivery of CR-6 stone to place atop the 57 stone at the trail abutment approach. Corman placed 6 inches of material at the approach per the approved plans. The material was compacted with the same aforementioned equipment. DDOT Technician was on site to CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT WEEK OF 09/20/2014 PAGE 5 of 11 conduct density test. The first compaction test failed due to a low moisture reading; Corman wet the material, re-rolled it and a passing compaction test was conducted. See DDOT’s Technician report for soil compaction dated 9/24/14. 2. The general contractor Corman Construction, second crew and the sub-contractor TNT welders were on the jobsite welding the 1.5”x2.0” angles for the SIP truss deck pan support and the 7.5”x10”-10GA angle for the curb line (0.125” weld, 1.5inch length at 12inch center to center). The 2” flat 10 GA strap cut to length was also welded at 18” center to center on the curb line angle. 3. CSX Flagger Danny Meyer wasn’t on site on this date. 4. WMATA Flagger Stephon Paige was on site on this date. Thursday 09/25/14 1. The general contractor Corman Construction arrived on site and left shortly thereafter due to inclement weather. The field inspectors utilized the day to review the truss bridge erection plan as the contractor plans to erect the truss next week Tuesday night, September 30, 2014. 2. CSX Flagger Danny Meyer wasn’t on site on this date. 3. WMATA Flagger Stephon Paige was on site on this date. Friday 09/26/14 1. The general contractor Corman Construction and the subcontractor, TNT welders, were on the jobsite and continued welding the 1.5”x2.0” angles for the SIP truss deck pan support., the 7.5”x10”-10GA angle for the curb line (0.125” weld, 1.5inch length at 12inch center to center) per submittal #69 on the west. The 2” flat 10 GA strap cut to length was also welded at 18” center to center on the curb line angle and stringer member of the curb section as per submittal # 61 on the east side. Also installations to anchor the temporary safety fence around the structure were being installed on the vertical tubes of the bridge structure. 2. The general contractor Corman Construction arrived on site to begin installing CSX hand rail clamps for the CSX protection shield. The contractor used a soft geotextile product to place between the steel truss member and the clamp to protect the bridge paint from scratches, chips, etc. Corman began to cover the black painted section of truss members at all field connections in preparation for bridge paint. One field splice connection was primed in the bottom chord at the connection of members a106 to a107 (work in progress). 3. The sub-contractor Best Fence was on site to remove sections of the CSX fencing adjacent the trail side easement lot. The contractor stated all sections of fence will be replaced once bridge is erected. The crane location on page 9 of the CSX submittal 10 shows the crane swing radius to be obstructed by the CSXT fence and DDOT black ornamental fence.. 4. CSX Flagger Danny Meyer was on site on this date. 5. WMATA Flagger Stephon Paige was on site on this date. 6. INSPECTION & MATERIAL TESTS PERFORMED - Truss Bridge at Trail Side; Skidmore test for TCB A325 and A325 Hexagonal bolts. Skidmore test results for TCB 7/8inch diameter were 42000Ibf (2#) and 5100Ibf as against the minimum of 39000Ibf, and they were 58000Ibf (2#) and 6200Ibf as against the minimum of 39000Ibf for the A325 Hexagonal bolt. Tests were performed on Tuesday 09/23/2014. CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT WEEK OF 09/20/2014 PAGE 6 of 11 - Wrench check on torqued bolts was done on the splice joint bolts at 110R and 105L at the Trail side on Wednesday 09/24/2014. - Testing material for density at the Trail Abutment approach compacted by Corman was conducted on Wednesday 09/24/2014. 7. RFI’s / SUBMITTALS - Requests For Information: o - No RFI Executed at this time. Submittals: o CSX Submittal No.12 As Built seat bridge elevations. CSX forwarded to Corman on 09/22/14 for use as noted. o Submittal No.80 CPM Schedule - Update 11 For July & August 2014. DDOT/HNTB forwarded to Corman on 09/25/14 for use as noted. o Submittal No.81 Truss Bridge SS Netting. Corman forwarded to DDOT/HNTB on 09/25/14 for review & approval. DDOT/HNTB forwarded to DDOT-QA/QC division on 09/25/14 for review & comment. 8. CHANGE ORDERS/TASK ORDERS - - - Proposed Change Orders: o PCO No.2 for Replacement of Solar Powered Lighting. o PCO No.3 for Pier 6 site Conditions. o PCO No 4 for Item 1: Furnish and install a new retaining wall. Item 2: Furnish and install temporary access road 12’ x 22’. Change Order: o Change Order No. 1 for unsuitable soil disposal is executed. o Change Order No. 2 for acceleration to demobilize from the staging area is executed. o Change Order No. 3 for the Trail Abutment Retaining Wall is in progress. o Change Order No. 4 for PCO No. 2 (Bridge light design change), PCO No.3 (Pier 6 Site Conditions) and PCO No. 4 (WMATA access) are in progress. Task Orders: No new Task Orders. 9. DBE PARTICIPATION SUMMARIES - - HNTB DBE Activity: o CKI & Associates, Inc. Review and Analysis of the CPM Schedule. Project Public out Reach. Field inspections. o HRV, Inc. Truss Bridge Fabrication Inspections at the Manufacturer’s Site Corman Construction, Inc. DBE Activity: o Prince Construction. Reinforcing steel for the Metro side piers & wall. 10. ACCIDENTS / INCIDENTS - There were no reported personnel or safety accidents in the project limits during this reporting period. CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT WEEK OF 09/20/2014 PAGE 7 of 11 11. PHOTOS OF WORK PERFORMED THIS PERIOD Corman connecting and Splicing members of the last section of the Truss Bridge – 09/20/2014 Corman adjusting grade of Bridge at Ttruss end – 09/20/2014 CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT WEEK OF 09/20/2014 PAGE 8 of 11 Waterproofing membrane and 10” PVC connection installation at Trail Abutment retaining wall – 09/22/2014 Torqueing the TCB A325 Bolts at the splice joint 107R and Skidmore Testing of the A325 Bolts on the job site 09/22/2014 CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT WEEK OF 09/20/2014 PAGE 9 of 11 Placing and rolling #57 stone to compact at the Trail Abutment Retaining Wall – 09/23/2014 Calibrated Wrench Check on torqued A325 bolts and Welding the 1.5inch x 2.0inch support for SIP on the stringers at the Trail side – 09/23/2014 CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT WEEK OF 09/20/2014 PAGE 10 of 11 Installation of 1.5” x 2” angle support and SIP truss bridge deck forms at the Trail Side – 09/24/2014 DDOT technician testing material for density and Corman compacting material at Trail Abutment approach – 09/24/2014 CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT WEEK OF 09/20/2014 PAGE 11 of 11 Best Fence removing sections of fencing and replace with temporary fencing – 09/26/2014 Corman installing steel plate for CSX overhead protection and protecting black bridge paint before priming field splice connections – 09/26/2014
© Copyright 2024 ExpyDoc