Congestion Management Process
Update & Status of the System Report
Project Statement
Update the Congestion Management Process (CMP) to be
MAP-21 compliant & support ongoing CMP implementation &
maintenance
Anchorage Bowl & ChugiakChugiak-Eagle River
Define and implement a Project Public Involvement Plan to
engage regional agency stakeholders in the CMP update
presented to
AMATS Technical Advisory Committee
Update the Status of the System Report to represent 2014
conditions & develop a web-based dashboard to display
multimodal system results
presented by
Teresa Brewer
Vivian Underwood
Develop Data Management Plan
October 9, 2014
2
FHWA’
FHWA’s 88-Step Congestion Management
Process
Develop Congestion Management Objectives
Integrate with MTP, TIP, other efforts
Develop Multimodal Performance Measures
Monitor system performance
Analyze Congestion Problems & Needs
Identify, Evaluate & Assess CMP Strategies
Program & Implement CMP Strategies
Apply at scale of region, corridor, or activity area
Define CMP Network
Project Deliverables
CMP Update
Step
Step 1. Develop •
Regional Objectives
for Congestion
•
Management
Step 2. Define the •
CMP Area and
Network
•
Evaluate Strategy Effectiveness
3
Provide input on network characteristics through
participation in an online survey
Review the CMP network to ensure it is consistent with
the MTP and verify that transit routes, bicycle and
pedestrian systems, and planned improvements to these
systems are adequately represented. Ensure areas
experiencing significant growth are incorporated into the
network.
Outreach
Component
Online survey #1
(Oct. 7-13, 2014)
TAC Meeting
(December 2014)
Online survey #1
(Oct. 7-13, 2014)
TAC Meeting
(December 2014)
4
Project Deliverables (cont.)
CMP Update
Step
Step 3. Develop
Multimodal
Performance
Measures
TAC Input Needed
Provide input on CMP objectives through participation in
an online survey
Review objectives to ensure they are realistic, specific to
the Anchorage region, achievable over different periods of
time, and are linked to the MTP update currently
underway
Project Deliverables (cont.)
TAC Input Needed
Outreach
Component
Review performance measures to ensure they are
TAC Meeting
supported by available data and models, provide a
(December 2014)
recognizable measure and comparison of congestion, and
are consistent with the MTP and MAP-21
CMP Update
Step
Step 6. Identify,
•
Evaluate and Select
Strategies
•
Step 4. Monitor •
System
Performance/ Data
Management Plan
Provide information on potential data sources for the
CMP Update and ensure agreement on monitoring
standards and protocols for the adopted data and
supporting measures
Step 7. Program
Selected
Strategies/CMP
Implementation
Plan
•
Provide input on implementing and programming CMP
strategies, as well as the flow charts defining steps for
integrating CMP projects into various MOA/AMATS
planning processes
TAC Meeting
(February 12, 2015)
Step 5. Analyze
Congestion
Problems and
Needs
Provide input on critical regional bottlenecks and
Online survey #1
congestion issues through participation in an online survey (Oct. 7-13, 2014)
Provide input on preliminary congestion analysis and
TAC Meeting
ensure congestion problems and bottlenecks are
(December 2014)
represented
Step 8. Evaluate
Strategy
Effectiveness
•
Review CMP strategy effectiveness results and proposed
process for conducting periodic assessments of project
effectiveness and viability for congestion mitigation
TAC Meeting
(February 12, 2015)
5
•
•
•
TAC Meeting
(December 2014)
6
TAC Input Needed
Provide input on multimodal project strategies to mitigate
congestion through participation in an online survey
Provide input on multimodal project strategies to mitigate
congestion, as well as strategy effectiveness
Outreach
Component
Online survey #2
(Late October)
TAC Meeting
(February 12, 2015)
Project Schedule
7
WrapWrap-Up/Questions