DESIGN AND CONSTRUCTION OF THE THIRD SET of LOCKS

DESIGN AND CONSTRUCTION OF THE THIRD SET of LOCKS
PANAMA CANAL EXPANSION PROGRAMM
Coordination Manager : Jan Kop
Panama, April 11, 2014
The Construction of te Third set of Locks Foresees..
Is…
the most important of all parts of the project which include:
•
Access channel in the Pacific Ocean side (dredging contract)
•
Access channel in the Atlantic Ocean side (dredging contract)
•
Connection channel between the pacific locks and the existing channel (PAC 0, Pac 1
1 through PAC 4)
•
Enlargement and deepening of the existing channel.
Assures..
to have the operation of the new installations in the year 2015 accomplishing 101 years of
the start of the operations of the Panama Canal.
Jan De Nul Panama Projects
Jan Kop
5
JAN DE NUL PANAMA PROJECTS
Panama - Panama Canal : Widening and Deepening of the Atlantic Entrance & North Approach
Channel to the Third Set of Locks
6
JAN DE NUL PANAMA PROJECTS
Panama - PAC-4 Dredging of a Trench for Cellular Cofferdam Installation
7
JAN DE NUL PROJECTS IN PANAMA
Panama - Pacific Muck Removal
8
JAN DE NUL PANAMA PROJECTS
Panama - New Pacific Entrance North Access Channel for the New Third Set of Locks Complex
9
Pacific Locks Rendering
Atlantic Upper Chamber - Rendering
GUPC Standard Lockage Scenarios
Down Lockage (Lake  Ocean)
Pacific 
 Gatun Lake
G1
G2
Lock Head 1
G3
G4
Lock Head 2
G5
G6
Lock Head 3
G7
G8
Lock Head 4
Scale - E & M
• 16 gates varying in weight, value some 500 MUS
• 152 valves, value some 225 MUS
• 76 units of HPU and electrical installation
• 60,000m2 of buildings spread out over 45 buildings
• 800km Electrical cables
• 300km Fiber optic
• 25km Piping
ATLANTIC SITE – BEFORE START IN 2009
ATLANTIC SITE - 2010
ATLANTIC SITE - 2010
ATLANTIC – CURRENT – WATER SAVING BASINS & CHAMBERS
PACIFIC SITE – BEFORE START IN 2009
PACIFIC SITE – APRIL 2010
PACIFIC SITE – APRIL 2010
PACIFIC – CURRENT – WATER SAVING BASINS & CHAMBERS
On both Pacific and Atlantic project:
Two exclusive sets of Aggregates Crushing and Cooling Plants
Two Concrete Batching Plants have been deployed; one for the
Atlantic Side and other to the Pacific Side;
The Basalt for the Aggregates to be used in the Atlantic Side are
primarily crushed in the Pacific Side and transported by trucks to the
Cartagena temporary docks, from which the material is shipped to the
Atlantic Side by the means of two 8,000 ton capacity barges,
navigating through the existing Canal.
The installation of infrastructure consisting basically of:
. Power generation and distribution systems;
. Lighting systems;
. Industrial water and compressed air generation and
distribution systems;
. Internal and temporary roads.
Supporting infrastructure :
. Main and detached offices;
. Labor Camp in the Atlantic Side;
. Mechanical and Electrical repair and assistance shops;
. Warehouses and store yards;
. Reinforcing steel cutting and bending yards.
CARTAGENA NORTH BASALT LOADING FACILITY
Industrial Plants
Capacity
Atlantic
Pacific
Primary Crushing Plant
3.300 ton/hr
-
1
Sec., Ter. y Qua. Crushing Plants
1.300 ton/hr
1
1
Concrete Batching Plants
540 m3/hr
1
1
Cement & Pozolane storage & handling Plants
9.000 m3
1
1
Barges for the Aggregates shipment
8.000 ton/day
2
-
Cartagena Aggregates transhipment docks
15.000 ton/day
-
1
30 ton
-
23
400 ton/day
1
1
Trucks for the Aggregates transport
Reinf. Steel Cutting and Bending Yards
Concrete Transport and Placement
Capacity
Atlantic
Pacific
Baby Tower Belts Rotec
120 m3/hr
4
4
Tele Belts Putzmeister TB 130
130 m3/hr
6
5
Tele Belts Putzmeister TB 200
200 m3/hr
-
1
Creter Crane Rotec 24 x 200
150 m3/hr
1
1
Concrete Pumps Putzmeister BSF 58
60 m3/hr
-
3
Concrete Pumps Schwing BSF 58
60 m3/hr
3
-
Concrete Trucks Maxon y Gicalla
8 m3
38
38
Steel Reinforcement Fabrication
GENERACIÓN DE ENERGÍA ELÉCTRICA (PACÍFICO – 14 MW / ATLÁNTICO – 10 MW
ATLÁNTIC SITE – MINDI WORKERS CAMP
GRUPO UNIDOS POR EL CANAL
ATAGUÍA - PACÍFICO
–
MOVIMIENTO DE TIERRA
ESTADO ANTES DEL INICIO EN 2010 – LADO OCÉANO
GRUPO UNIDOS POR EL CANAL
–
MOVIMIENTO DE TIERRA
ATAGUÍA - PACÍFICO
ESTADO CON ATAGUÍA TERMINADA, ANTES DEL ACHICAMIENTO
GRUPO UNIDOS POR EL CANAL
–
MOVIMIENTO DE TIERRA
ATAGUÍA - PACÍFICO
ATAGUÍA DESPUÉS DEL ACHICAMIENTO PRINCIPAL
In March 13 2014 the drilling and blasting #1250 has been carried out
without incidents
. Volume of Basalt excavated - 9,800,000 m3;
. Total drilling for explosives - 1,240 km - 141,000 drilled holes ;
. Total quantity of explosives - 5,190,000 kg
Rock blasting without incidents and with rigorous vibration control
due to the proximity of the Miraflores Locks
The Design and Build of the Third Set of Locks has to take into
consideration several fundamental elements :
• The complexity of the geology in the Pacific side;
• The active faults on the Pacific side and the consequent high seismicity expected
in this area;
• The fact that only in the Pacific side suitable rock for the concrete production is
available;
• The presence of recent sedimentary and unstable deposits in the Atlantic side
and in part of the Pacific side;
• The very strict requirements for the locks maneuvers and operation (availibility
99.6%)
• The negative effect of the rainy season on the production during construction
phase;
• The short schedule time available for the huge foreseen quantities;
- Concrete Production
. Republic of Panama
118,000 m3 / month Total
. Works in the Atlantic and Pacific Sites
100,000 m3 / month each
Total 200,000 m3 / month
- Reinforcing Steel Cutting and Bending
. Republic of Panama
3,500 ton / month Total
. Works in the Atlantic and Pacific Sites
4,500 ton / month each
Total 9,000 ton / month
- Aggregates Production
. Republic of Panama
180,000 ton / month Total
. Primary Crushing in the Pacific Site
600,000 ton / month Total
.Coarse and Fine Aggregates in the Pacific
and Atlantic Sites
300,000 ton / month each
Total 600,000 ton / month
GRUPO UNIDOS POR EL CANAL
–
CONCRETO
Quantities of CONCRETE in Third Set of Locks Project compared with known
stuctures:
Pirámide Keops:
2,200,000 m3
Edificio 20 pisos:
10,000 m3
Esclusas Pacífico -
2,550,000 m3
= 1.2 Pirámides Keops
= 255 Edificios de 20 pisos
Esclusas Atlántico -
2,270,000 m3
= 1 Pirámide Keops
= 227 Edificios de 20 pisos
GRUPO UNIDOS POR EL CANAL
–
CONCRETO
Quantities of STEEL in Third Set of Locks Project, compared with
known structures:
Torre Eiffel:
10,000 toneladas
Esclusa Pacífico
102,000 toneladas = 10.2 Torres Eiffel
Esclusa Atlántico
90,000 toneladas
=
9.0 Torres Eiffel
19 Torres Eiffel
The dimensions of a Lock Gate are approximately
equivalent to the Treasury Building in Panama City.
GRUPO UNIDOS POR EL CANAL
1
–
CALIDAD, SALUD, SEGURIDAD Y AMBIENTE
RESCATE DE VIDA SILVESTRE
RESCATE DE VIDA SILVESTRE – CANTIDADES HASTA
ABRIL 2011
( En distintos tipos y tamaños)
2
1. RESCATE DE BOA CONSTRICTOR
2. RESCATE DE COCODRILO
Mamíferos
un
1,030
Reptiles
un
1,036
Amfibios
un
81
Cocodrilos
un
282
Culebras
un
312
Personnel on Site - Status as of MARCH 2014
Work Areas
Expatriate
Staff
Panamanian
Staff
Labor
Totals
Main Office
41
142
0
183
Atlantic Work Site
96
531
1,435
2,062
Pacific Work Site
131
530
1,627
2,288
Sub Total GUPC's employees
268
1,203
3,062
4,533
6%
27%
68%
100%
Subcontractors and Services
314
179
1,332
1,825
Total General
582
1,382
4,394
6,358
9%
22%
69%
100%
THANK YOU!