Biogas Support Program (PoA)

Terms of Reference (ToR) for Verification of CPAs of Nepal
Biogas Support Program (PoA)
1.
Introduction
Alternative Energy Promotion Centre (AEPC) was established in 1996 with the objective of developing
and promoting renewable energy technologies with focus in rural areas of Nepal. Since then, AEPC has
been successfully implementing/executing several renewable energy programme/activities in Nepal. From
July 16, 2012 AEPC is executing a five years National Rural and Renewable Energy Programme
G\fRREP) which has a single programme modality. It is envisaged that no other programmes or projects
will be supported or executed outside the NRREP's
to updating knowledge on Climate Change
committed
framework. The AEPC/\IRREP is further
well
a
diversified portfolio of RETs projects using
mitigation and adaptation options; further development
different instruments and establishing high quality performance assurance and monitoring systems.
related to renewable energy promotion in Nepal
The Climate and Carbon Unit (CCU) under NRREP is catalyzing the renewable energy programmes in
order to better address climate change issues. The CCU also supports government to formulate climate
change sensitive RE policies/plans and supports District Development Committees to prepare climate and
gender sensitive energy plans. CCU is working on development & management of RETs carbon projects
feasible in the country. Under regulated carbon market, AEPC has succeeded in registering 6 Clean
Development Mechanism (CDM) Projects: 4 biogas projects consisting of about 60 thousands biogas
plants, one Micro hydro project with total 450 mini/micro hydro projects and one Biogas PoA with each
CPA comprising of maximum 20,000 digesters. Two CDM PoAs have been requested for registration
with the LTNFCCC. The details of these projects are available at http://www.aepc.gov.np/.
2.
Background
Nepal Biogas Support Program-PoA was registered with the UNFCCC CDM Executive Board (EB) on
3l January 2013 (Registration Ref. No. 9572). AEPC is the coordinating and managing entity of this
PoA. The start date of this PoA is 22''d June 2007, with a length of 28 years. The technologies used in this
PoA are household biogas digesters with different sizes of 2,4,6, 8 and 10 m3. The programmes uses
only one design i.e. GGC 2047 model As of now three CPAs are being validated by DOE for inclusion in
the PoA and the inclusion of the same are expected by April 2014. Since the Biogas PoA (including CPA1:20,000 digesters) was registered on 31 Jan2013 and three other CPAs are expected to be included in
the PoA soon, AEPC intends to procure seruices from the LINFCCC accredited DOEs for the verification
of the PoA (a CPAs). The details of the biogas CPAs proposed for verification are presented in the table
below:
able
S.N
1
2
3
4
3.
l: CPAs
lbr verillcation
Title
CDM Prosramme olActiv v (CPA) -l
CDM Prosramme of Activ v (CPA) -2
CDM Programme of Activ tv (CPA) -3
CDM Prosramme of Activitv (CPA) -4
Duration/Exnected Duration of verification
3l
30
30
30
Jan 2013-30 June2014
Aoril 2014-30 June 2014
April 2014-30 June 2014
Aoril 2014-30 June 2014
Objectives
The general objective of the task"is verification of four CDM programme Activities (CPAs) of Nepal
Biogas Support Program-PoA (Registration Ref no 9572).
4.
Scope of
Work
The scope of the work includes but is not limited to:
T.r-t
of Reference (ToR) for Verification of CPAs of Nepal
Biogas Support Program (PoA)
a
An independent and objective review of the Monitoring Reports (lvIR) and supporting documentation.
Prepare verification findings as per the guidance provided by CDM Executive Board
a
Prepare verifi cation rePorts
o
Submit to UNFCCC CDM Executive Board issuance request based on the final verification outcome.
5.
Working Approach
a
The DoE shall elaborate their working approach indicating the timelines to achieve the milestones
shall also be
consistent with timeline indicated in the ToR. The methodology for carrying out the study
activity.
each
to
complete
required
time
discussed concisely, preferable diagrammatic indicating
6.
Inputs from AEPC/NRREP
o
o
NRREp budget and relevant documents/materials and information, in particular:
Input from relevant AEPC and NRREP officers
7.
Time and budget
7.1 Timing
agreement'
The DOE is expected to complete this activity within three months from the date of contract
7.2 Budget
Contract will be
Budget should be prepared in free form indicating the activities, man-days involved, rate etc.
in
excess of the
cost
done with the DOE on lump sum basis and is not entitled to receive any additional
costs for the
contract amount. The DoE is subject to bear itself, the transportation and accommodation
local travel assotiated with the assignment. The contract amount will be in Nepalese
intemational and
Rupees.
8.
Taxes
and the tax
The DOE is subject to pay 28o/otaxof the contract amount as per the applicable tax laws-ofNepal
will be deducted from'the DOE's receivables while making the payments after the delivery of milestones'
The payment schedule is given in annex I.
9.
Deliverables(output)
Reporting of the work shall be done as per following:
.
.
o
Initial review of MR and submission of draft protocol through email
Submission of the Verification Reports for the CPAs of the PoA under consideration
Communicate AEPC during each stage of the verification assignment
10. Qualification of DoE and auditors
scopes and sectors is sought'
of CDM rules and procedure.
A competent team with relevant knowledge and experience in the specific
The team shall compose of
verifiers/auditors as per the requirement
Terms of Reference (ToR) for Verification of CPAs of Nepal
Biogas Support Program (PoA)
1L. Documents to be submitted by the DOE
The DOE should submit the technical and financial proposals in separate sealed envelopes and the both
should be sealed in an outer envelope. The documents submitted by the bidder should include:
Technical Proposal
a. Authorized certification of DOE
b. Signed CV of proposed auditors/verifier
c. Working Approach
d. List of similar experiences
e"
Time frame indicating the specific activities.
f.
Any other relevant documents
Financial Proposal
g.
h.
Budget sheet in separate sealed envelope indicating details, for example, the activities, man-days
involved, rate etc.
Budget may be proposed in Nepalese Rupees. The cost of services, if indicated otherwise than
Nepalese Rupees, will be convefied to the Nepalese Rupees as per the exchange rate for the final
day of the proposal submission deadline'
12. Selection Procedure
The consultant selection method is the Ouality and Cost based method as stipulated in sub-rule 4(a)
of rule 71 of the Public Procurement Rules of Nepal. Detail criteria for the selection of DOE are given
in annex II. An illustration of selection procedure with Quality and Cost based method is given in annex
Il1.
f..-t
of Refeience (ToR) for Verification of CPAs of Nepal
Biogas Support Program (PoA)
Annex I
-
Payment Schedule
lnstallments
I
st installment (advance)
Percent
20o/o
2nd installment
3rd installment
40% of Contract Amount
Expected OutPut
Contract signed followed
of Contract Amount
40% of Contract Amount
Total
Amount NRs
bY
Invoice
Submission of verifi cation
findines after initial review
Submission of final
verification reoort
l00o/"
uld be understood as the total contract amount
indicating the Tax and not as the total receivable amount'
(ToR) for Verification of CPAs of NePal
Biogas SuPPort Program (PoA)
ffie
Annex
II - Selection /Evaluation Criteria
Thefollowingwillbethemarkingofthetechnicalandfinancialproposals.
ProPosal
B. Financial ProPosal
A. Technical
10%
30%
70
A. Technical ProPosal
5
OverallExperience of the DOE in verification
i. e*p..i.*e of DOE in verification of similar projects/programs
region
:. g*p.ri.n.e of DOE in working in South Asia
project verification
cDM
in
4. overal experi"n"e. of veriReistAuditors
projects/programs
similar
of
in verification
5. Experienc. of V.tntt'AuJl'o"
6. Clarity on working aPProach
7. Work schedule with manning
1.
10
10
10
15
5
15
30
B. Financial ProPosal
B.
Financial Proposal
proposals will be
DOEs securing toP scores in the technical
The financial ProPosals of the toP three
opened for further assessment'
C.
Selection
uP and the DOE
t7 nical and financial ProPosals will be summed
The marks obtained by the DOE in the
warded with the task.
securing the highest marks in total will [e
P
rocu rement
as
pects checked ; "z'ft'
t',--d
P6curen
Approved
Recommended bY:
ffiokharel
Sr. International Technical Adviser
AEPCAIRREP
D^r",U7.0q.
i?
Executive Director
AEPC
Date
:
Terms of Reference (ToR) for Verification of CPAs of Nepal
Biogas Support Program (PoA)
Annex
III - Illustration
of DOE selection approach with the Quality and Cost Based Method
Under quality and cost based method the technical proposal is evaluated first and the top three
DOEs will be selected. After that the financial proposals of the top ranking DOEs will be opened
quote will receive full
and the scores will be assigned based on the leist quote such that the least
quotes higher than
score. Based on relative 1rlightug. of quotes, scores will be assigned to the
given by adding
be
will
the least quotes. Once financial scores are given, the cumulative scores
the
technical and financial scores. The DOE securing highest cumulative score will be awarded
task.
is
For example 4 DOEs (A, B, C, and D) have applied for the assignment. Their technical proposal
opened and they receive the technical marks as follows:
Rank
DOEs
Technical Score (out of70)
A
B
62
C
65
1t'
63
2"d
J
61
D
the
hnical
luati
.ad
-N.
the followi
DOEs will be considered for further evaluation:
DOEs
Technical Score (out of70)
C
65
1t'
D
63
2'd
A
62
J
Rank
quotes are as
Now, the financial proposals of the above three DOEs (A, C and D) are opened the financial
follows:
DOEs
Financial Ouote (NPR)
C
300,000.00
2s0.000.00
250.000.00
D
A
Now, the financial scores will be calculated as follows:
Financial Score: (Lowest Quote X 30) / Proposed Quote
DOEs
Financial Score
:(2s0000 x 30y300000:25
:(2s0000 x 30y250000:30
:(2soooo x 3oy25oo0o:30
300,000.00
250,000.00
250,000.00
C
A
D
ncial scores as follows
technlca landfi nanclal
be assigned by adding the techni
Rank
Score (out of 100)
Total
Technical Score Financial Score (out of30)
Final scores
DOEs
will
be as follows:
f inancial Ouote (NPR)
Hence. the financial scores of the DOEs
will
(out of70)
C
65
D
63
A
62
Hence, the DOE
25
30
30
"D" will
90
^rd
J
93
92
2'd
be awarded with the task after the completion of evaluation.