Download PDF Document (1831Kb)

ESOF Energy Storage
Workshop
LCNI 2014
21st October 2014
Introduction
• Welcome
• Energy Storage Operators’ Forum session
• Significant amounts of energy storage connected:
– LCNF Conference 2013: 5.1MW, 6.4MWh commissioned
– LCNI Conference 2014: 12.4MW, 20.1MWh commissioned
• Learning being shared from full project lifecycle
• “State of Charge of GB” paper
Introduction: ‘State of Charge’ in
October 2013
Key
Commissioned
Under construction
Planned
Decommissioned
Darlington 2.5 MW 5 MWh
100 kW 200 kWh
50 kW 100 kWh
Willenhall 2 MW 375 kWh
Shetland 1 MW 6 MWh
Shetland 1 MW 3 MWh
Orkney 2 MW 500 kWh
Nairn 100 kW / 150 kWh
Wooler 100 kW 200 kWh
50 kW 100 kWh
Maltby 50 kW 100 kWh
Milton Keynes 150 kW 450 kWh
Chalvey 25 kW 25 kWh
Hemsby 200 kW 200 kWh
Bristol 90 kW up to 321 kWh
6 kW 14.4 kWh
Leighton Buzzard 6 MW 10 MWh
Introduction: ‘State of Charge’ in
October 2014
Shetland 1 MW / 3 MWh
Shetland 1 MW / 6 MWh
Key
Commissioned
Under construction
Planned
Decommissioned
Orkney 2 MW / 500 kWh
Nairn 100 kW / 150 kWh
Darlington 2.5 MW / 5 MWh
100 kW / 200 kWh
50 kW / 100 kWh
Wooler 100 kW / 200 kWh
50 kW / 100 kWh
Maltby 50 kW / 100 kWh
Willenhall 2 MW / 1 MWh
Chalvey 75 kW / 75 kWh
Milton Keynes 250kW / 500kWh
(3 units)
Bristol 90kW / 216 kWh
Hemsby 200 kW / 200 kWh
(25 domestic, 5 commercial units)
Thames Valley 972 kW / 513 kWh
(25 units)
Leighton Buzzard 6MW / 10MWh
Outline of Workshop
• Introduction (Stewart Reid, SSE Power Distribution)
• Developing the Business Case for Energy Storage (John Hayling,
UK Power Networks)
• Maximising the Benefits of Energy Storage (Nathan Coote, SSE
Power Distribution)
• Integrating Storage into Business as Usual (Dave Miller, Northern
Powergrid)
• Conclusion
• Discussion Session
Developing the Business
Case for Energy Storage
John Hayling
UK Power Networks
What drives the business case for
distribution storage?
Business case for distribution connected storage
Avoided
Reinforcement
Value within DNO
Business
Additional
Revenue
Value outside conventional
DNO business e.g. from
ancillary / wholesale market
Business
case
Case Study: SNS Project business
case benefits
Conventional
Once Proven
Smarter
Network Storage
Successful
£m
16.0
12.0
3.0
8.0
2.0
11.5
2.5
4.0
5.1
4.0
0.0
Conventional
Reinforcement
Installed
Cost
Tech
Cost
Reduction /
Ahead of Need
Future
Income
Streams
System
Cost
Savings
Future Net
Method Cost
Source: UKPN analysis, Poyry Analysis.
Includes Civil, Elec, Labour, Opex estimates. All values in 2013 prices. Discount factor 7.2%
What distribution storage
business models are there?
Model
Key points
DNO merchant
Full merchant risk,
exposed to power
price and balancing
services
Comments
► DNO builds, owns and operates the asset.
► DNO exposed to construction and operational
risks
DNO exposed to
incentive scheme
► Prior to construction, long term contracts (e.g. 10
years) for the commercial control of the asset
outside of specified windows are agreed
DNO
contracted
DNO has full
operational control
► Possible barriers: Are long term contracts
feasible (risk appetite, credit risk)?
Contracted
services
Low Commercial
Risk for a DNO
DSO
Charging
incentives
No guarantee of
asset being built
► DNO offers a long term contract (e.g. 10 years)
for services at a specific location with commercial
control in certain periods
► Third party responsible for building, owning and
operating the asset, and monetising additional
revenue streams
What legal and regulatory barriers
exist for storage?
Key messages:
• Default treatment of storage as a subset of generation creates
uncertainty and raises potential issues
• But generation licence exemption route does provide flexibility
to progress distribution connected storage projects of
appropriate size in a manner consistent with unbundling
requirements
• De minimis business restrictions do place a loose limit on
deployment by DNOs, if storage continues to be classed as
generation
• Possible application and operation of assets is affected
though by the need to ensure that competition in generation
and supply is not distorted
• Tax treatment for storage could lead to double counting of
CCL and FiTs levee
In Conclusion
Three points to take away:
• With suitable site selection, by incorporating the right
additional revenue and system cost savings distribution
grid scale storage will deliver a competitive business
case
• DNO Contracted and Contracted Services are the two
operating business models most likely to deliver success
• Providing the legal and regulatory issues identified can
be resolved
Maximising the Network
Benefits of Energy Storage
Nathan Coote
Scottish and Southern Energy
Power Distribution
Scope
•
•
•
•
•
Smarter Network Storage
FALCON
1MW Battery, Shetland
Conclusions
Further Information
Benefits of energy storage
•
•
•
•
•
•
•
Peak shaving
Frequency response
Reactive power and voltage support
Reserve services
Back up power or black start
Avoided or deferral of cost
Generation optimisation
Smarter Network Storage
• 6MW/10MWh Li-ion
• 3 x 2MW PCS
• Commissioning stage
Smarter Network Storage:
Design Considerations
Realising Value:
Operations and Maintenance
SAFETY
Specification
Development and
Procurement
Installation and
Commissioning
SAFETY
Identify
Requirement for
EES, Develop
Business Case and
Commercial Model
Realising Value:
Operations and
Maintenance
End of Life
Disposal
SAFETY
FALCON
Milton Keynes
• 100 kWh sodium metal halide
• 50 (100) kW inverter
• Site controller
• DC switchgear
FALCON: Peak shaving
FALCON: Frequency response
1MW Battery, Shetland
• 1MW / 3MWh VRLA battery
• 1.25MVA PCS
• 11kV connection
• ANM and SCADA control
1MW Battery, Shetland
Time [hh:mm]
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
9:00
8:00
7:00
6:00
5:00
4:00
3:00
2:00
1:00
0:00
Demand [MW]
1MW Battery, Shetland
28.00
Shetland Demand
26.00
24.00
22.00
29-Sep
20.00
30-Sep
01-Oct
02-Oct
18.00
03-Oct
16.00
14.00
1MW Battery, Shetland
4.00
Shetland Wind
3.50
3.00
28-Sep
29-Sep
2.00
30-Sep
01-Oct
1.50
02-Oct
03-Oct
04-Oct
1.00
0.50
Time [hh:mm]
23:00
22:00
21:00
20:00
19:00
18:00
17:00
16:00
15:00
14:00
13:00
12:00
11:00
10:00
9:00
8:00
7:00
6:00
5:00
4:00
3:00
2:00
1:00
0.00
0:00
Wind [MW]
2.50
1MW Battery, Shetland
49.9 Hz
47.8 Hz
t = 2.90s
t = 546ms
t = 1.83 s
44.8 Hz
088
094
080
024
021
022
025
023
007
1L5
2L5
3L5
Conclusions
• The benefits of energy storage are wide ranging
• Maximising the benefit from energy storage is a complex task
• Quantifying the total value is challenging as not all benefits are
captured within markets
• O+M phase of the project provides opportunities to realise value
while evaluating against actual losses more accurately
• Pursuing a commercial model which stacks multiple benefits and
technologies can make the business case work
More information
– https://www.ukpowernetworks.co.uk/internet/en
/community/smarter-network-storage/
– http://www.westernpowerinnovation.co.uk/Falc
on.aspx
– https://www.ofgem.gov.uk/ofgempublications/89496/sset10011mwbatteryshetla
nd-closedownreport20141.1.pdf
Integrating Storage into
Business as Usual
Dave Miller FIET
Northern Powergrid
Integrating Storage
People and Process
– Storage is different to conventional solutions
– Like any business process change, introducing storage
needs careful management, and every individual is
different
– From a planning and control perspective, storage and
demand response are similar
– If you own your storage, the ESOF GPG captures what
we’ve learnt about the practical on-site issues
Integrating Storage
Control for Thermal Constraints
Integrating Storage
Control for Voltage Constraints
Integrating Storage
Optimising for Commercial Benefit
Session Conclusions
• Three key areas shared today
• LCN Fund projects have developed the State-of-the-
Art throughout the whole project life cycle.
• Lessons learnt being shared – including
consolidating into a Good Practice Guide on EES
(published in December)
• Some areas still to develop
PANEL DISCUSSION
Stewart Reid, SSE Power Distribution (Chair)
Geraldine Bryson, Electricity North West
Dave Miller, Northern Powergrid
Nathan Coote, SSE Power Distribution
Alan Collinson, SP Energy Networks
John Hayling, UK Power Networks
Philip Bale, Western Power Distribution