for the Month of Feb,2014

Monthly Progress Report of Arun-3 HEP (900 MW) for the Month of Feb,201
Sr.
No
Description
1 MOU
Hydrological
Data
2
Status as on 28.02.14
The MOU was signed between GON and SJVN on 02.03.2008.
Gauge and Discharge sites are operational w.e.f 03.11.08. Data is being recorde
lab made operational w.e.f. 03.11.08 and Silt analysis being done regularly. H
House discharge site is not working w.e.f. 25/06/2012 due to flash flood. The Gh
re- establishment of G&D site at power house has been completed.The me
discharge and silt data for PH site has been taken w.e.f 25.01.14.
First round of PDA meeting held between17th to 19th, June13 and second round
Signing of
on 27/28th, June13. Third round of PDA meeting held between 19/20th J
Project
Template of PDA is being revised/modified.
3 Development
Agreement (PDA)
Generation
Licence
Preparation of
5
DPR
EIA / EMP study
6
4
13-03-14
Generation license applied on 14.07.2013 is under process.
Final DPR submitted to CEA on 31.03.11. 13 chapters of DPR cleared so f
progress.
The report has been submitted to IBN, GoN on 30th June, 2013. GoN raised
for improving the draft EIAEMP report on 23.08.2013 and report is under
report has been submitted to Competent Authoriety for approval.
RSS comp/d:/official/MPR/MPR-Arun III for Feb 14.xlsx
1 of 4
Construction
material survey
7
13-03-14
Work Completed. The material is suitable for non-wearing surfaces only. CSM
observations, for use of aggregate for wearing surface. To reply the observatio
award for testing samples from DP-15 of Power House area for wearing surf
was made on 24.01.2014. The samples from the site has been collected on 2
sent to CSMRS Deptt on 02.03.14.
RSS comp/d:/official/MPR/MPR-Arun III for Feb 14.xlsx
2 of 4
Project Roads
Readiness of award of work is being acheived by the time PDA is signed.
Kuwapani to Num and Num to Dam site : Roads constructed by the Deptt of ro
up to Num. Approx. 3.5km road from Dam site/Transit camp to Dam top is yet to b
for which estimate has been prepared, and approved.
Chainkutty to Diding(Power House): Tender was invited for construction of acce
Power House(approx 28.69km) on item rate basis through e-procurement . Case
tendering process. Period of construction is 2 years. Estimated cost is 60 crs.
Access roads to various sites:
i) Power House township to Phaksinda(20.87 Km) : Case is under tendering pr
ii) Bridge Dovan to Contractor Facilities & Clay Quarries (4.10 )km :Tendering
iii) IP544 of Chainkutty to PH Road to the bottom of Surge Shaft & Adit IV( 0.8
is under tendering process.
iv) IP529 of Chainkutty to PH Road to the top of Surge Shaft ( 1.04 Km): Case
tendering process.
Project Land
The land requirement along with cadastral map(180.32 hectares) submitted to Go
Land owned by GoN to be transferred to SJVN within 180 days and Land owned b
be transferred to SJVN within 1 year of submission of complete information of la
per terms of MoU and subject to PDA.
It has been proposed by SJVN by inserting a clause in PDA for transferring Pvt. la
obligation of GoN.
8
9
13-03-14
RSS comp/d:/official/MPR/MPR-Arun III for Feb 14.xlsx
3 of 4
Transmission
line
10
(a)
i)DPR(Transmission lines):
DPR submitted to CEA on 05.04.11.CEA observation regarding cost of tran
was attended and revised cost estimate was submitted to CEA on 20.11.13
DPR being pursued.
ii)IEE report:
IEE report submitted to GoN on 10.08.12. Ministry of energy,GoN had raised com
study report. After incorporation of comments. final report submitted to Ministry
by NEA on 14.08.13. MoE,GoN again raised some observations and re
submitted. IEE report is likely to be approved by 31.03.14.
Extension
of Survey Licence has been extended upto 21.05.14.
10(
Transmission
b)
Survey licence
Establishment of VSAT have been installed at Imchung and Num . Installation work and trans
communication PH& Dam sites through routers will be taken up after signing of PDA.
system at Project
11 site and with
Corporate office.
13-03-14
RSS comp/d:/official/MPR/MPR-Arun III for Feb 14.xlsx
4 of 4