HOUSING & DEVELOPMENT COMMITTEE MEETING – 18th MARCH 2014 PRESENT: Cornelia Condren (Chairperson), Noeleen Diver (Vice Chair), Liz Marsh, Kathy Mackenzie and Karin Eyben. IN ATTENDANCE: R Nicholl, Director of Housing and Development 1. ITEM Declarations of Conflicts of Interest REPORT All members present were asked to declare any interest in the items of business on the agenda. No conflicts of interest were identified. ACTION None 2. Apologies Apologies were received from Lorna Dougherty None 3. Minutes of Last Meeting None. Chair to sign 4. Matters Arising There were no matters arising from previous meetings: None 5. Schemes on Site Committee received an update on the progress and status of all schemes that were currently on site. Committee noted that *We have been advised by consultants that KPL is involved in the Ramoan Road Scheme (as sub-contractor of NIE), and as a result of this, an early warning notification of possible delay has been received from the contractor. At this stage it is difficult to estimate the likely extent of delay, as no doubt NIE will have to retender these works and try to programme within an already busy programme. However, if not resolved quickly, it could result in a delay of weeks, possibly months. At this stage, it is difficult to assess if there will be any impact on 29a Annadale Avenue. We do not have a programme date for NIE trenching and supply. The main contractor has planned to have the new main supply ducted through the site in May 2014, but nothing has been confirmed by NIE to date. Ramoan Road, Ballycastle 6. 2013/14 Programme Committee reviewed the performance update report for all schemes included in the 2013/14 programme year, which outlined the risk profile of each scheme and the projected number of starts and completions for the year. None RESP TIMESCALE CC Immediate 7 Annadale Avenue Committee noted that the scheme was due to go on site on 24th March 2014 None Cushendall Road, Ballymena Committee noted that the scheme commenced on site on 10th March 2014 None Hilmount Crescent, Tobermore Committee noted the contents of the technical assessment report. The Association has been permitted to claim an additional area band for 2 terraced properties with pens. The consultants estimate has been reduced as this had included rain water harvesting in error. This has resulted in the costs coming in at close to TCI. Committee gave approval to proceed to purchase the site at £25,500, subject to project approval. Refer land acquisition to Board CEO March 14 Mullaghaboy Crescent, Magherafelt Committee noted that following Magherafelt Council’s decision to defer the planning application on 11th March, an office meeting had taken place earlier in the day. The principle argument put forward by the objectors was that they were under the impression that the land was green space. Planning Service has indicated that it will consider the proposal at Group this week. It is hoped that a green form will be issued next week. Committee also discussed the higher cost estimate received from the consultant, following inclusion of additional retaining walls at the rear of the site. The Director reported that the Association has been permitted to claim an additional area band for the 2 first floor apartments, which had mitigated against this increase. The likely tender return would reduce these costs further and a departmental adjustment may be granted for the NIW water works costs. Committee gave approval to proceed to purchase the site at £62,000, subject to project approval and receipt of green form. Refer land acquisition to Board CEO March 14 O’Neill Park, Ballymaguigan Committee noted that the planning application had been approved by Council on 11th March 2014. The technical assessment report has not been received from the DPG as it had been sent to the DSD with a recommendation for a departmental adjustment for the additional NIW works. These costs were brought to the Association’s attention after the last Committee meeting and significantly impacted on the project’s viability. Committee gave approval to proceed to purchase the site at £20,000, subject to project approval and receipt of green form. Refer land acquisition to Board CEO March 14 104 Ballinderry Bridge Road, Cookstown Committee noted that the Association was still awaiting the technical assessment report. DPG is liaising with DSD regarding potential for departmental adjustment for NIW works. At this stage, the planning application is unlikely to be approved before the end of the financial year as Planning Service and Roads Service have differing views on the road layout and additional information has been requested to establish the principle of development under PPS21. Committee gave approval to proceed to purchase the site at £35,000, subject to project approval and receipt of green form. Refer land acquisition to Board CEO March 14 Henderson Park, Stewartstown Committee noted that the application for project approval was not submitted to DPG as the planning application did not make the Council schedule for March 14. Committee gave approval to proceed to purchase the site at £35,000, subject to project approval and receipt of green form. Submit for project approval in April DOH April14 Refer land acquisition to Board CEO March 14 290-292 Holywood Road, Belfast Following an update on the progress of the planning application and review of the returned tenders, Committee gave approval to the Director to submit an advanced land purchase application, subject to receipt of written confirmation from the planning service that the application would be submitted for approval to the council in April 2014. Submit ALP application if written confirmation can be obtained from planning service DOH ASAP Hillsborough Old Road, Lisburn Following review of the tabled report and discussion regarding the responsibility for funding of SMART technology, Committee approved the full business on the condition that a departmental adjustment is secured for the capital cost of the SMART technology and written assurances are also provided regarding the revenue funding. Committee did not give approval to start onsite, unless the Trust Business Case is approved with explicit commitments to the funding of the SMART technology element. Following review of the tender report, Committee approved the award of the works contract to Donaghamore/Farrons. Table full business case at next meeting DOH March 14 Harpurs Hill, Coleraine Following review of the tabled report, Committee approved the full business, subject to confirmation of the site valuation from LPS. Following review of the tender report, Committee approved the award of the works contract to MJ McBride. Committee gave approval to proceed to purchase the site, subject to receipt of a LPS valuation Refer land acquisition to Board CEO March 14 thate was not materially higher than the assumed rate of £200,000 and subject to project approval. 7. YPLC, East Antrim Following consideration of the tabled report, Committee agreed not to proceed with the proposed development on this site, unless the higher offer for the site is rejected by the NHSCT and the legal issues regarding the restrictive covenant relating to the 1918 lease can be resolved. Committee authorised the Director to commence a search for alternative sites outside of the Larne area. Report at next meeting Clerk of Works Service for 2013/14 Schemes Committee approved the proposal to use the Fold Clerk of Works service for all schemes in the 2013/14 development programme. None 8. Mid Ulster Tender Returns 9. Holywood Road Tender Returns 10. Planned Maintenance DOH March 14 29a Annadale Avenue 7 Annadale Avenue Hillsborough Old Road Hillmount Crescent Holywood Road Cushendall Road Harpurs Hill Mullaghaboy Crescent O’Neill Park Ballinderry Bridge Road Henderson Park Committee reviewed the results of the tender returns for the Mid Ulster schemes. The Director reported that the lowest tenderer may pull out. Committee agreed to approve the award of the works contract to Dixons or MJ McBride (in the event that Dixons withdraws), subject to receipt of a satisfactory tender report. . Committee reviewed the results of the tender returns for and agreed to approve the award of the works contract to Donaghmore/Farrons, subject to receipt of a satisfactory tender report. Arrange pre-start meeting when appropriate DOH March 14 Arrange pre-start meeting when appropriate DOH March 14 Committee approved the award of the following contracts: None Tower Court – Active Maintenance Solutions Kilns Court – D Magee and Sons 37 Castlehill Place, 3 Breda Ave, 40 Donaghadee Road, 28 Elmwood and 17 Ambleside – PK Murphy 11. Any Other Business There were no other items of business. None 12. Date for Next Meeting The next full meeting of the Committee will be held on 14th April 2014 Circulate agenda and relevant papers Signature: _______________________________________________________ (Chairperson) Name: _______________________________________________________ (Block Capitals) Date: _______________________________________________________ DOH Week before meeting
© Copyright 2024 ExpyDoc