DAY 2 TECHNICAL PROGRAMME Sequential Downtime Analysis as a Tool for Planning Operations in Harsh Weather Locations Ed Ballard, Orwell Offshore Ltd PRESENTATION OVERVIEW • Introduction to concept and motivation for using Sequential Downtime Analysis (SDA) and comparison with conventional methods - Example Case - Definition of Task Sequence (installation at field in North Sea) Metocean data used Results of analyses Implications for planning of operations - Conclusions 3 SEQUENTIAL DOWNTIME ANALYSIS • Estimation of the likely duration of offshore operations is of interest for the planning, costing and specification of the equipment to be used. 4 SEQUENTIAL DOWNTIME ANALYSIS • Conventionally, expected operability has been assesses using metocean data in the form of: – Scatter diagrams, exceedance curves 5 SEQUENTIAL DOWNTIME ANALYSIS • Conventionally, expected operability has been assesses using metocean data in the form of: – Scatter diagrams, exceedance curves – Monthly Means – Non-exceedance persistence tables 6 SEQUENTIAL DOWNTIME ANALYSIS - Conventional methods cannot account for: - Fluctuations in metocean conditions over short intervals. - Cumulative effect of delays associated with individual tasks. - SDA particularly suitable for: - Lifting operations, for which vessel motions are critical. - Operations involving personnel and/or cargo transfer. - Based on Monte-Carlo Simulations - Large number of simulations performed, accounting for variation in duration of multiple tasks in addition to metocean variation. - Method allows the probability distribution for the duration of a complex job sequence accounting for likely metocean variation to be determined. 7 DEFINITION OF TASK SEQUENCE - DURATIONS • Each task in the job sequence defined in terms of: – Minimum duration – Likely delay (duration variation) on top of minimum duration Task Number 1 2 3 4 5 6 7 Task Description MWA-GB Install Reset Riser1 Install Reset Riser2 Install Reset Riser3 Install Average Duration Duration Variation 36 6 6 1 24 3 6 1 24 3 6 1 24 3 8 DEFINITION OF TASK SEQUENCE - DURATIONS • Each task in the job sequence defined in terms of: – Minimum duration – Likely delay (duration variation) on top of minimum duration – Large number of task durations conforming to selected statistical description randomly generated. Task Number 1 2 3 4 5 6 7 Task Description MWA-GB Install Reset Riser1 Install Reset Riser2 Install Reset Riser3 Install Average Duration Duration Variation 36 6 6 1 24 3 6 1 24 3 6 1 24 3 9 DEFINITION OF TASK SEQUENCE - DURATIONS • Individual random length tasks combined to form a large number of job sequences for use in Monte Carlo simulations. Task Number 1 2 3 4 5 6 7 Task Description MWA-GB Install Reset Riser1 Install Reset Riser2 Install Reset Riser3 Install Delays Zero Delay 50th Percentile (P50) 95th Percentile (P95) Average Duration Duration Variation 36 6 6 1 24 3 6 1 24 3 6 1 24 3 Duration Hours Days 126.0 5.25 139.9 5.83 149.2 6.21 • No metocean effects yet considered. 10 DEFINITION OF TASK SEQUENCE – LIMITING METOCEAN CRITERIA • The complete definition of the tasks making up job sequence requires the setting of limiting metocean criteria: Hs [m] – Limiting sea-states for operations from floating structures will have dependence on wave period. – Define Wave Height vs Peak Period contour using detailed analyses. – Wind and current limits constant values. 3.0 -3.5 FAIL FAIL FAIL FAIL FAIL FAIL FAIL 2.5 - 3.0 FAIL FAIL FAIL FAIL FAIL FAIL FAIL FAIL 2.0 - 2.5 FAIL FAIL FAIL FAIL PASS PASS PASS PASS 1.5 - 2.0 FAIL FAIL FAIL PASS PASS PASS PASS PASS PASS 1.0 - 1.5 PASS PASS PASS PASS PASS PASS PASS PASS PASS 0.5 - 1.0 PASS PASS PASS PASS PASS PASS PASS PASS PASS PASS 0.0 - 0.5 PASS PASS PASS PASS PASS PASS PASS PASS PASS PASS PASS PASS 3.0-3.5 3.5-4.0 4.0-4.5 4.5-5.0 5.0-5.5 5.5-6.0 6.0-6.5 6.5-7.0 7.0-7.5 7.5-8.0 8.0-8.5 8.5-9.0 Tp [s] 11 METOCEAN DATA • Hindcast or recorded time histories of metocean data are required. • Multiple sources, some public (NOAA WaveWatch III) 12 MONTE CARLO SIMULATIONS • Monte Carlo simulations are performed using a large number of realisations of the job sequence. • For each step in the metocean time series, all job sequence realisations are run. • The results of the multiple simulations allow the expected duration of the job sequence if started on a particular date to be determined. 13 MONTE CARLO SIMULATIONS • Durations to complete for all days in 2005. 14 TIMING OF OPERATIONS • The results of the simulations can be used to determine likely durations of job sequence for all months. • This can allow selection of optimum month for the job if there is flexibility in its scheduling. 15 SELECTION OF EQUIPMENT USED FOR OPERATIONS Hs [m] • If the operation must be performed at a particular time of the year, the results of an SDA analysis can be used to optimise the equipment used. • For instance, an alternative vessel could be chartered, which increases limiting Hs for critical lifts by 0.5m over full Hs/Tp contour. 3.0 -3.5 FAIL FAIL FAIL FAIL FAIL FAIL FAIL 2.5 - 3.0 FAIL FAIL FAIL FAIL FAIL FAIL FAIL FAIL 2.0 - 2.5 FAIL FAIL FAIL FAIL PASS PASS PASS PASS 1.5 - 2.0 FAIL FAIL FAIL PASS PASS PASS PASS PASS PASS 1.0 - 1.5 PASS PASS PASS PASS PASS PASS PASS PASS PASS 0.5 - 1.0 PASS PASS PASS PASS PASS PASS PASS PASS PASS PASS 0.0 - 0.5 PASS PASS PASS PASS PASS PASS PASS PASS PASS PASS PASS PASS 3.0-3.5 3.5-4.0 4.0-4.5 4.5-5.0 5.0-5.5 5.5-6.0 6.0-6.5 6.5-7.0 7.0-7.5 7.5-8.0 8.0-8.5 8.5-9.0 Tp [s] 16 SELECTION OF EQUIPMENT USED FOR OPERATIONS • Effect of increasing the limiting Hs contour can be significant. 17 SELECTION OF EQUIPMENT USED FOR OPERATIONS • SDA analysis results allow assessment to be made of comparative costs. • For example, it can be used to determine whether it is better financially to charter the more capable vessel. Number Required Installation Vessel 1 Barge 1 Tug 2 Total Cost Per Day Vessel Cost Per Day [USD] Original Spread Revised Spread 150 000 200 000 5 000 5 000 25 000 25 000 205 000 255 000 18 SELECTION OF EQUIPMENT USED FOR OPERATIONS • August – Likely worst cost for original spread almost same as revised spread median cost. • October – Worst case for revised spread only slightly higher than original spread. 19 SUMMARY AND CONCLUSIONS • SDA method has been used to demonstrate how the duration of a job sequence made up of a series of tasks can be estimated. • The estimated duration accounts for: – Delays associated with individual tasks – Delays associated with exceedance of metocean limits • The results of the SDA analyses presented have been used to demonstrate how it can be used as planning tool for either: – Selection of the optimum time of year for particular equipment; – Selection of optimum equipment for installation at a particular time of year. 20 Thank You 21
© Copyright 2024 ExpyDoc