Presentation of IWE Work to USAID

Indonesian Wind Sector Impact
Assessment
ICED Task Order #11
Status Report
Pramod Jain, Ph.D.
K. Balaraman, Ph.D.
Rashmi Shekar
March 5, 2014
Innovative Wind Energy, Inc.
Activities Performed
1. Distributed Generation connection guidelines, PLN
2. Evaluation of Nusa Penida Wind Farm, PLN
3. Wind Resource Assessment & Financial Feasibility of Taman
Jaya Wind Farm in Sukabumi, Pertamina
4. Java-Bali-Madura Grid code enhancements for
interconnecting RE, PLN
5. Steady state modeling for impact of 194.2MW wind power in
South Sulawesi, PLN
6. Dynamic stability modeling for impact of 194.2MW wind
power in South Sulawesi, PLN
7. Training on system impact modeling and analysis, hands-on
with MiPower software, wind resource assessment, PLN
2
Distributed Generation Connection Guidelines
• Status:
– Completed draft guidelines. PLN is finalizing based on comments from
Wilayahs
• Involvement:
– Developed Renewable Energy Generation Plant (REGP) Connection
Application and Power Procurement Process
– Technical requirements for REGP: Protective functions,
Voltage/frequency regulation, power quality
– Generation specific requirements: Wind power, solar power
– Testing, certification and commissioning
• Comments:
– In-depth involvement in most aspects of DG connection guidelines
– DG connection guidelines should serve as the rule book for equipment
manufacturers and developers, and significantly streamline approvals
3
Evaluation of Nusa Penida Wind Farm
• Status:
– Completed site visit, analysis and recommendations
• Involvement:
– Visited Nusa Penida with PLN and Whypgen
– Recommendation to PLN:
• Do not invest in refurbishing turbines as it is not financially viable
• Start from scratch: Perform wind measurement using tall met-masts (60
or 80m), perform wind resource assessment and if project is financially
feasible then install utility scale turbines
• Comments:
– Projects done by government for “other than” financial reasons are
rarely successful
– PLN should not own or manage wind farms; it is best left to private
sector.
4
Wind Resource Assessment & Financial Feasibility of
Taman Jaya Wind Farm in Sukabumi
• Status:
– Completed wind resource assessment and financial feasibility analysis
• Involvement:
– Worked with Pertamina to assess viability of 10MW wind fram in
Sukabumi
– Analyzed Viron Energy’s wind measurement data
– Performed detailed wind resource assessment using WAsP
– Performed financial feasibility analysis with P75 and P90
– Recommendations: Project is not feasible with the current PPA and
Pertamina’s return on equity hurdle rate
• Comments:
– Pertamina has accepted the recommendations
5
Java-Bali-Madura Grid code enhancements for
interconnecting Wind Power Plants
• Status:
– Completed draft grid code has been submitted to PLN. Presented to Renewable
Energy and System Planning divisions. Awaiting PLN review
• Involvement:
– Developed grid code enhancements for interconnecting 10MW and higher size
wind plants to 70KV and higher transmission lines. Application and Power
Procurement Process
– Developed Connection Code, Operating Code, Metering Code,
Scheduling/Dispatching Code, and Data Requirements Code
– Technical requirements for: Active and reactive power, frequency ad voltage
regulation, Low Voltage Ride Through, protective functions, and power quality
– Generation type specific requirements: Induction versus full power conversion
• Comments:
– Authors of the grid code enhancements for interconnecting wind power plants
– Grid code will be part of PPA for developers
– Grid code should streamline interconnection study & approval process
6
Steady state modeling for impact of 197+MW wind
power in South Sulawesi
• Status:
– Completed steady state modeling of South Sulawesi system: 2015
scenario with 70MW of wind, 2019 scenario with total of 194.2MW of
wind
– Submitted draft report of the impact study. Presented to System Planning.
Awaiting PLN review and comments
• Involvement:
– Data collection of current network in South Sulawesi and connections to
other provinces
– Steady state modeling using MiPower
– Load flow analysis and short-circuit analysis
– Scenario definition
– Determination of impact under the scenarios
• Comments:
– PLN will use results as basis for interconnecting 3 wind farms of sizes
70MW, 62.5MW, 64.8MW in South Sulawesi
– Recommendations are for PLN to improve system operations practices in
order to integrate wind power successfully
7
Dynamic stability modeling for impact of 197+MW wind
power in South Sulawesi
• Status:
– Completed dynamic stability modeling of South Sulawesi system: 2015
scenario with 70MW of wind, 2019 scenario with total of 194.2MW of
wind
– Submitted draft report of the impact study. Presented to System Planning.
Awaiting PLN review and comments
• Involvement:
– Data collection of current network in South Sulawesi and connections to
other provinces
– Dynamic stability modeling using MiPower
– Transient stability and frequency response analysis
– Scenario definition
– Determination of impact under the scenarios
• Comments:
– PLN will use results as basis for interconnecting 3 wind farms of sizes
70MW, 62.5MW, 64.8MW in South Sulawesi
– Recommendations are for PLN to improve system operations practices in
order to integrate wind power successfully
8
Training on system impact modeling and analysis, hands-on
with MiPower software, wind resource assessment
• Status:
– Completed 5-day training at the PLN Renewable Energy Academy in
Makassar
• Involvement:
– Conducted training on theoretical aspects of system modeling and
analysis in general and with wind generation in particular
– Hands-on training on MiPower, a software for modeling load flow,
short circuit and dynamic stability of system
– Wind Resource Assessment—Wind measurement, wind resource
modeling using WAsP, Average Annual Energy Production
• Comments:
– 25+ attendees from PLN Pusat and PLN regional offices from System
Planning, System Operations and Renewable Energy divisions
– Attendee feedback: Need more training
9