Progress of blocking water at connection of trenches and the Units 2

The Committee on Supervision
and Evaluation of the Specified
Nuclear Facilities (25th)
Extract from Material 1
Progress of blocking water at connection of trenches
and the Units 2 / 3 reactor facilities
July 23, 2014
Tokyo Electric Power Company
00
1. Trench location at Units 2 and 3
■Plan
seaside
N
既閉塞済
Vertical立坑B
shaft B
Vertical 立坑B
shaft B
Unit2号機海水
2 Seawater
配管トレンチ
Piping
Trench
Tunnel B
ト
ン
ネ
ル
A
Tunnel A
Tunnel A
ト
ン
ネ
ル
C
トンネルB
Tunnel C
ト
ン
ネ
ル
A
Tunnel C
トンネルB
Tunnel
B
立坑Cshaft C
Vertical
立坑Cshaft C
Vertical
ト
ン
ネ
ル
C
Unit
3 Seawater
3号機海水
配管トレンチ
Piping Trench
立坑D
Vertical
立坑A shaft A
立坑Ashaft A
Vertical
Freezing started
2号機タービン建屋
Unit 2 Turbine Building
Vertical 立坑D
shaft D
Under excavation
3号機タービン建屋
Unit
3 Turbine Building
Under excavation
Freezing started
Open-cut
duct
開削ダクト
Unit 2
Unit 3
Vertical shaft A
Freezing started (April 28)
Vertical shaft A
Excavation started (July 2)
Open-cut duct
Freezing started (June 13)
Vertical shaft D
Excavation started (May 2)
1
New approaches to removing trench water
Purpose
Measure
Install additional pipes to carry coolant around
the trench
Install additional coolant pipes inside the trench
-Excavate new holes
Upgrade the
cooling
-Use holes in which thermometers are installed
capacity of the Change coolant operation
freezing system -Increase coolant flow speed
-Change temperature of coolant
-Change coolant material
-Use liquified nitrogen as coolant
Add ice
Suppressing
Add dry ice
the flow of the
water
Install additional coolant pipes in vertical shaft
Progress
adopted
(under preparation)
PLAN
difficult to implement
adopted
(under preparation)
implemented
difficult to implement
difficult to implement
difficult to implement
adopted
(preparation completed)
adopted
(preparation completed)
under discussion
立坑部
Lowering water temperature
A
A
Upgrade cooling capacity
2号機
Unit
2
2号T/B
タービン建屋
Inject liquified nitrogen inside the building frame under discussion
Install additional "packers" (nylon bags filled with adopted
(under preparation)
Exploring other cement)
adopted
methods of Fill space with grout
(reviewed)
lowering the
adopted
Fill space with other materials
water's
(reviewed)
temperature Other measures to suppress water flow within adopted
the buildings
(reviewed)
Suppressing water flow
2
Schedules for Unit 2 Vertical shaft A
8月
August
7月
July
項 目
Measure
20
30
10
20
30
preparation
投入準備
STEPⅠ
①氷投入
Add ice
Add
投入ice
Test
試験投入
preparation
投入準備
Add dry ice
①ドライアイス投入
Test
試験投入
Installing
pipes
凍結管交換
Add
dry ice
投入
Freezing
凍結運転
②既設測温管を凍結管へ変更
Install additional coolant
Add
thermometer *currently
reviewing points
測温管追加設置
※現在,設置位置含め検討中
pipes
Build
trestle
架台設置
③躯体外側への凍結管設置
Install additional coolant
Insert
pipes
凍結管挿入
pipes around the trench
Build
trestle
架台設置
STEPⅡ
Install additional
④追加パッカー設置
“packers”
Build
trestle/excavation
架台設置・削孔
Freezing
凍結運転
Excavation/confirm
削孔・内部確認 inside
Insert “packer”
パッカー挿入
Prepare
plant
プラント準備
Fill space with filling
⑤間詰め材の投入
material
Add
material
材料投入
*The schedule is due to change according to the weather and progress of each measures.
3
(Reference) Sampling results of water inside seawater piping trenches
Place of sampling
Radioactive material
density(Bq/cm3)
Sampling
date
Cl
(ppm)
Cs-134
Cs-137
Unit 2 T/B
2013/07/22
約100
1.1×104
2.5×104
Unit 2
Vertical shaft C
2013/07/31
700~
7,500
1.1~3.0
×105
2.3~6.5×105
Unit 3 T/B
2013/06/13
約200
1.5×104
3.1×104
Unit 3
Vertical shaft C
2013/07/31
16,000~
17,000
1.0~1.3
×105
2.2~2.6×105
4