CaseStudy UV Cured Lining Customer: Thames Water Location: Farnham Project: UV Cured in-Situ Sewer Lining A problematic drain at a rail crossing adjacent to Farnham Railway Station was repeatedly flooding, causing pollution of a nearby river and leading to serious concern from the Environment Agency. The failing drain had already been jetted, with a CCTV survey being carried out to determine the cause. The survey showed that the 70m long drain constructed from 225mm diameter vitrified clay pipe that was suffering from serious root infiltration and was also suffering from a number of structural defects. Several of the lateral connections were intruding into the pipe, which combined with a very steep fall and high flow rate meant that flooding was almost inevitable. In-Situ cured lining was identified as the ideal solution to stabilise the pipe’s and act as a barrier to prevent further re-growth of roots and prevent blockages. Other companies approached by Thames Water had declined this contract due to its demanding nature. On investigation OnSite determined that a UV cured in place pipe (CIPP); with its much smaller site footprint compared to hot cure lining; greatly reduced curing time of just 90 minutes compared to around 6 hours for a hot cure liner; and no requirement for hot curing water and its associated problems with disposal of polluted liquid on completion; offered clear advantages over hot water systems. Because the project was located on an active rail crossing, it required working under the supervision of a crossing guard within a strict six hour overnight ‘possessions’ allocated by Network Rail. The location also meant that flow control had to be achieved using tankers and that all lining plant had to be positioned outside the crossing, with cables running from the cutting and lining rigs, with a system of pulleys set up to run under the crossing gates even when shut. “I was genuinely impressed with the planning and execution of the Station Hill sewer lining work, given the proximity of the live railway track. It was fantastic to see the team working through the night to ensure the job was completed on time.” Martin Perrin, Thames Water South East Area Network Manager. CaseStudy UV Cured Lining Lining and lateral cutting was controlled remotely from the dedicated operations vehicle. The UV ‘light train’ used to cure the liner in a tenth the time required for hot water cured systems. “The project was a success on all fronts, not least in meeting and exceeding stakeholder expectations. It enabled Thames Water to rehabilitate a drain which had given repeated problems. The Environment Agency is pleased to now see prevention of further flooding and pollution to the nearby river. Network Rail, owner of the land and assets, incurred no damage to property and minimal disruption to its services. Finally domestic users connected to the drain experienced no interruption to supply. All in all, this was a well planned, managed and executed project and we’re proud of our team’s efforts.” The project was programmed to be carried out over three consecutive night time ‘possessions’, each of six hours. Steve Ovington, OnSite 89 Blackpole West • Blackpole • Worcester WR3 8TJ. From OnSite’s survey of the site it was established that the lateral connections were sufficiently long to accommodate being blocked off for a 24 hour period without affecting the properties that they served. However a leaflet drop was made to ensure local residents that might be affected by the works were kept fully informed. Night one saw the Robotic Root Cutter, Jetter and Tankers mobilised to carry out all the preparatory on-site work. On the second night the Lining Rig, Jetting unit and Tankers were utilised to install the lining, which was cured in place in just sixty minutes; a feat impossible for hot water systems that would have required the entire six hour possession simply to be cured. During the final night the Robotic Cutter was utilised to reopen the lateral connections. An OnSite traffic management team were in attendance throughout the project. An OnSite main line CCTV rig was also in attendance to provide support surveying of any problem areas that might arise. [email protected] www.onsite.co.uk 08454 600 365 A member of
© Copyright 2024 ExpyDoc