PPP Project Targets and Achivements

I.
Stages/Timelines for PPP Projects
Part A – Project Details:
Name of the Port:
Name of the Project
Kandla Port Trust
Estimated Cost
Estimated Capacity
Name of Nodal Officer for the project
448 Crores
24.5 MMTPA
B.Rajendra Prasad, Superintending
Engineer (Design)
Development of Marine Liquid Terminal
Facilities Consisting of SPM and Two
Product Jetties in KPT waters at OOT
Vadinar, Kandla Port on Captive Use
Basis
Part B – Stages:
Sl.
No.
1.
2.
Stage
Preparation
Report/DPR
Target Date
of
Feasibility M/s Essar Oil
Limited has
prepared the
Feasibility
Report as this
is being
captive
proposal &
submitted
along with
detailed
application to
KPT on
15/10/2014
Submission of Proposal for Obligation of
Environmental Clearance
concessionaire
3.
Issue of Invitation of RFQ
EOI Invited on
23.9.2014
4.
Submission of Tariff Proposal
to TAMP
Short listing of bidders
Submission
for
Security
Clearance for bidders
Approval of Tariff by TAMP
N/a
5.
6.
7.
Status/Remarks
KPT verified the feasibility
report submitted by M/s
EOL through Transaction
Advisor, M/s Feedback
Infra.Pvt.Ltd.
SPM – VOTL already
obtained.
Two Product Jetties – At
advance stage
Only one application
received from consortium
of M/s Essar Oil Ltd. & M/s
VOTL
Captive Project
20/10/2014
17/11/2014
N/a
Captive Project
8.
9.
Submission of proposal to 21/10/2014
Competent
Authority viz.
PPPAC/SFC/EFC etc.
Receipt of Security Clearance ----------
10. Receipt
of
Clearance
SFC recommended the
proposal in its meeting held
on 17.12.2014
M/s VOTL already having
security clearance granted
by MoS,GoI vide letter
dated 2/5/2013 and as per
Guideline dated
19.12.2012 the same is
valid for three years.
Necessary details have
already been submitted by
M/s VOTL required under
Guideline dated
19.12.2012.
Environment Will be the
obligation of
concessionaire
Competent 20/1/2015
11. Approval
of
Authority
12. Issue of RFP Documents to N/A
Bidders
22/1/2015
13. Issue of LoA
14. Signing
Concession 22/2/2015
Agreement
15. Financial
closure
and 21/8/2015
compliance
of
other
conditions precedent.
16. Commencement
of 22/8/2015
Construction/Project Work
17. Commissioning of the Project
21/8/2018
Captive project
subject to approval from
MoS,GoI
Subject to
Environmental/CRZ
Clearance obtained by
concessionaire for Product
jetties.
Subject to
Environmental/CRZ
Clearance obtained by
concessionaire for Product
jetties.
I.
Stages/Timelines for PPP Projects
Part A – Project Details:
Name of the Port:
Name of the Project
Estimated Cost
Estimated Capacity
Name of Nodal Officer for the project
Kandla Port Trust
Setting up of a Container Terminal at Tuna –
Tekra, Kandla Port on BOT Basis
3097 Crores
2.19 M.TEUs
B. Rajendra Prasad, Superintending Engineer
(Design)
Part B – Stages:
Sl. No.
1.
2.
Stage
Target Date
Preparation
of
Feasibility
Report/DPR
Submission
of
Proposal
for 06.05.2014
Environmental Clearance
Status/Remarks
Feasibility Report submitted to
Board for its approval.
After Public Hearing, KPT
submitted final EIA report to
MoEF, GoI on 06.05.2014
-Expert committee included the
proposal in its meeting held on
31.07.2014 and raised certain
observations, which are under
compliance.
-CRZ recommendation from
State Coastal Zone
Management Authority is still
awaited.
3.
Issue of Invitation of RFQ
4.
Submission of Tariff Proposal to Feb., 2015
TAMP
Short listing of bidders
March, 2015
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
Submission for Security Clearance
for bidders
Approval of Tariff by TAMP
Submission
of
proposal
to
Competent
Authority
viz.
PPPAC/SFC/EFC etc.
Receipt of Security Clearance
Receipt of Environment Clearance
Approval of Competent Authority
Issue of RFP Documents to
Bidders
Issue of LoA
Signing Concession Agreement
Financial closure and compliance
of other conditions precedent.
Commencement
of
Construction/Project Work
Commissioning of the Project
Jan., 2015
Feb., 2015
April, 2015
Feb., 2015
April, 2015
Sept., 2015
June, 2015
May, 2015
July, 2015
August, 2015
Feb., 2016
March, 2016
Sept., 2019.
II. Stage / Timeline for projects to be taken up through Internal
Resources
Part A – Project Details:
Name of the Port:
Kandla Port Trust
Name of the Project
Strengthening of Oil Jetty No.1 & 2 at Old
Kandla.
Estimated Cost
15.14 Crores
Estimated Capacity
Capacity Addition – 1.570 MMT
Name of Nodal Officer for the project
M.H. Makati
Sr. Engineer (PL)
Part B – Stages:
Sl. No.
Stage
Target
Date
Status/Remarks
1.
Approval of Feasibility Report by
the Port Trust Board
2.
Appraisal of Standing Committee /
SFC
3.
Invitation of Tender
30.11.2013
4.
Pre-qualification of Bidders
11.02.2014
5.
Approval of Competent Authority
Board
6.
Opening of Price Bid
13.02.2014
7.
Issuance of Work Order
20.05.2014 Clear site handed over on
01.07.2014
8.
Completion of the Project
June 2015
I.
Stages/Timelines for PPP Projects
Part A – Project Details:
Name of the Port:
Name of the Project
Kandla Port Trust
Setting up of Single Point Mooring (SPM) &
Allied facilities off Veera in Gulf of Kutch on
BOT Basis under PPP Mode.
Estimated Cost
Estimated Capacity
Name of Nodal Officer for the project
992.38 Crores
12.00 MMPTA
B.Rajendra Prasad, Superintending Engineer
(Design)
Part B – Stages:
Sl. No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
Stage
Target Date
Preparation
of
Feasibility
Report/DPR
Submission
of
Proposal
for March 2015
Environmental Clearance
Issue of Invitation of RFQ
Submission of Tariff Proposal to
TAMP
Short listing of bidders
Submission for Security Clearance
for bidders
Approval of Tariff by TAMP
Submission
of
proposal
to
Competent
Authority
viz.
PPPAC/SFC/EFC etc.
Receipt of Security Clearance
Receipt of Environment Clearance
Approval of Competent Authority
Issue of RFP Documents to
Bidders
Issue of LoA
Signing Concession Agreement
Financial closure and compliance
of other conditions precedent.
Commencement
of
Construction/Project Work
Commissioning of the Project
Status/Remarks
All Ready prepared
EC for SPM & Pipeline received
SC for COT under submission
Issued
Was sent to TAMP on
14.10.2014
Bidders prequalified pending
security clearance.
Sent to MoS on 15.11.2014
TAMP approve Tariff on
02.01.2015
SFC approved project on
09.12.2014
05.02.2015
Sept. 2015
Excepted by 05.02.2015
Received on 05.01.2015
Starting issuing from
05.01.2015
25.02.2015
24.03.2015
Sept 2015
Sept 2015
Sept 2019
Subject to E.C.
Stages/Timelines for PPP Projects
Part A – Project Details:
Name of the Port:
Name of the Project
Kandla Port Trust
Development of Oil Jetty to handle liquid
cargo & ship bunkering terminal at Old Kandla
Estimated Cost
Estimated Capacity
Name of Nodal Officer for the project
233.50 Crores
3.39 MMPTA
B.Rajendra Prasad, Superintending Engineer
(Design)
Part B – Stages:
Sl. No.
1.
2.
3.
4.
5.
6.
7.
8.
Stage
Preparation of Feasibility Report/DPR
Submission
of
Proposal
for March 2015
Environmental Clearance
Issue of Invitation of RFQ
Submission of Tariff Proposal to
TAMP
Short listing of bidders
Submission for Security Clearance for
bidders
Approval of Tariff by TAMP
9.
10.
11.
Submission of proposal to Competent
Authority viz. PPPAC/SFC/EFC etc.
Receipt of Security Clearance
Receipt of Environment Clearance
Approval of Competent Authority
12.
13.
Issue of RFP Documents to Bidders
Issue of LoA
14.
Signing Concession Agreement
15.
Financial closure and compliance of
other conditions precedent.
16.
Commencement
Construction/Project Work
Commissioning of the Project
17.
Target Date
Status/Remarks
Board approved silent features
and feasibility report and tariff
proposal on 26.12.2012.
EC for SPM & Pipeline received
SC for COT under submission
18.08.2012
27.12.2012
Board approved provisionally
11 applicants prequalified and 2
applicants dis-qualified on
30.01.2013
10.12.2012
TAMP order passed on
22.02.2013
19.01.2013
02.05.2013
Expected within 3 months
Board approved silent features
feasibility report and tariff
proposal on 26.12.2012
28.02.2013
LOI issued to M/s. IMC Ltd. On
26.06.2013
Signed Concession Agreement
with SPV Kandla Oil Terminal
Pvt. Ltd. On 16.11.2013
Board approve extension of
time period for fulfillment of
CPs upto end of Feb 2015.
of May 2015
May 2017
Stages/Timelines for PPP Projects
Part A – Project Details:
Name of the Port:
Kandla Port Trust
Name of the Project
Development of 14th multipurpose Cargo (other
than liquid / container cargo ) berth at Kandla
Port on BOT basis.
Estimated Cost
182.21 Crores –BOT operator, 26.66 Crores – KPT IR
Estimated Capacity
1.5 MMPTA
Name of Nodal Officer for the project
B.Rajendra Prasad, Superintending Engineer (Design)
Part B – Stages:
Sl. No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
Stage
Preparation of Feasibility Report/DPR
Submission
of
Proposal
for
Environmental Clearance
Issue of Invitation of RFQ
Submission of Tariff Proposal to
TAMP
Short listing of bidders
Submission for Security Clearance for
bidders
Approval of Tariff by TAMP
Submission of proposal to Competent
Authority viz. PPPAC/SFC/EFC etc.
Receipt of Security Clearance
Receipt of Environment Clearance
Approval of Competent Authority
Issue of RFP Documents to Bidders
Issue of LoA
Signing Concession Agreement
Financial closure and compliance of
other conditions precedent.
Commencement
of
Construction/Project Work
Commissioning of the Project
Target Date
Status/Remarks
25.09.2008
01.08.2007
19.09.2011 TO 23.12.2011
12.06.2008
28.03.2012
23.01.2012
12.11.2008
27.10.2008
Approved by PPPAC on
20.02.2009
14.09.2012
Sept 2008
31.08.2009
10.04.2012 to 19.04.2012
20.10.2012
14.03.2013
There is in-ordinarily delay in
fulfilling conditions precedent
by concessionaire, hence
proposal for terminate the
concession agreement is
submitted to the Board for its
approval.
II. Stage / Timeline for projects to be taken up through Internal
Resources
Part A – Project Details:
Name of the Port:
Kandla Port Trust
Name of the Project
Up-gradation of Barge Handling Facilities at
Bunder Basin
Estimated Cost
49.20 Crores
Estimated Capacity
3.20 MMT
Name of Nodal Officer for the project
N. M. Parmar, SE(P)
Part B – Stages:
Sl. No.
Stage
Target
Date
1.
Approval of Feasibility Report by
the Port Trust Board
2.
Appraisal of Standing Committee /
SFC
3.
Invitation of Tender
14.03.2013
4.
Pre-qualification of Bidders
19.03.2013
5.
Approval of Competent Authority
Board
6.
Opening of Price Bid
21.03.2013
7.
Issuance of Work Order
19.04.2013
8.
Completion of the Project
April 2015
Status/Remarks