Financing renewable CHP plants

Financing renewable CHP plants
Estover Energy
5 November 2014
About Estover
•
Developer of local-scale biomass plants
– 10-25MWe range
– £75m-£125m per development
– Financed with third party equity & debt
•
Combined Heat & Power (CHP)
– Co-located with industrial partners
– Grid-connected for bankability
– Proven technology
•
•
Fuel from local, sustainable forestry
Estover Energy Ltd
–
–
–
–
Operating since 2010
Backed by private investors
Leading developer in biomass CHP
Team involved in 8 of operating biomass CHP
plants in the UK
Confidential
Reminder!
These guys support local biomass from UK woodlands
Confidential
The Macallan, Speyside – financed Summer 2014
Confidential
Cramlington, Northumberland
Project overview estimates
Aesica & Merck pharmaceutical plants
Planning status
Granted - Jan 2013
Size Mwe / MWth
27 / 6+
Financial close
target
June 2014
Operations start
2015
Tonnes of fuel per
year
240,000
Contractor
BWSC (Denmark)
Confidential
Discovery Park, Sandwich, Kent
Project overview estimates
Pharma manufacturing & office park
Planning status
Granted - Oct
Size Mwe / MWth
15MWe / 12MWth
Financial close
target
Mid-late 2015
Operations start
Late 2017
Tonnes of fuel per
year
135,000
Contractor
Gestamp Biomass
(Spain)
6
ArjoWiggins Stoneywood Mill, Aberdeen
Project overview estimates
Paper mill, Aberdeen’s second largest employer
& maker of Conqueror paper
Planning status
Granted - Jan 2013
Size MWe
15MWe / 15MWth
Financial close
target
2015 – 2016
Tonnes of fuel per
year
150,000
Contractor
TBC
Confidential
Why do industrial sites like biomass CHP?
•
Main commercial benefits
– Reduce energy costs / carbon taxes§
– Decarbonise energy supply for
marketing benefits
– Future carbon tax risk mitigation
– Security of steam and power supply
separate from gas & electricity grids
•
Estover’s offer is a complete package
– We option land, gain relevant consents
– Our consortium engineers & finances
the plant
– Estover finds the fuel
– Plant operates independently
Finding biomass CHP sites is long, hard work
Criteria sites have to meet:





Land
Grid
Heat load size & type
Counterparty risk
Counterparty appetite for
contracting
 Selling through an organisation
153 sites
evaluated
93 site meetings
15 met criteria
9 exclusivities
4 in financing
Taken us 4+ years and millions of
development money to finance one!
1 financed
How is renewable
CHP financed?
Biggest challenge?
Renewables policy mismatch between RO and RHI
Current CfD system doesn’t work for biomass CHP
•
The current CfD for biomass CHP
isn’t a “contract” as your
“difference” is taken away based on
your heat load’s performance
•
Means big risk
•
Puts everything on the business of
your customer – no longer an
infrastructure investment but a bet
on a heat customer
Key messages
• Biomass CHP can be done
– Yes we are building one, and financing another
– But it’s a lengthy, expensive and extraordinarily difficult
process to develop & finance biomass CHP
• ROCs work but RHI doesn’t
– The mismatch makes financing extremely difficult
• CfD doesn’t work at the moment
– Dependence on heat makes biomass CHP unfinanceable
without major changes
Thank you
[email protected]