2014 Local Program (Lukasz)

The Wisconsin Department of Transportation
2014 WisDOT SE Region
Utility Conference
Local Program Projects
DAAR Engineering, Inc.
SE Region Local Program Management Consultant
DAAR Engineering, Inc. is the Management Consultant (MC) representing the Wisconsin Department of Transportation
CONTACTS
MANAGEMENT CONSULTANT (MC) CONTACTS:
STAN LUKASZ, P.E.
TODD BECKER, P.E.
WisDOT SE Region MC – Program Manager
DAAR Engineering, Inc.
325 E. Chicago Street, Ste. 500
Milwaukee WI 53202
Office (414) 225-9817
Direct (414) 935-4360
[email protected]
WisDOT SE Region MC – Design Manager
DAAR Engineering, Inc.
325 E. Chicago Street, Ste. 500
Milwaukee WI 53202
Office (414) 225-9817
Direct (414) 935-4359
[email protected]
JOE KLARKOWSKI, R.L.S.
RON ANDERSON
WisDOT SE Region MC – Construction Manager
DAAR Engineering, Inc.
325 E. Chicago Street, Ste. 500
Milwaukee WI 53202
Office (414) 225-9817
Direct (414) 935-4410
[email protected]
WisDOT SE Region MC – Utility & RR Coordinator
DAAR Engineering, Inc.
325 E. Chicago Street, Ste. 500
Milwaukee WI 53202
Office (414) 225-9817
Direct (414) 935-4368
[email protected]
MANAGEMENT CONSULTANT
ROLE OF MANAGEMENT CONSULTANT
Retained by WisDOT as an extension of SE Region Staff
Serve as a resource to Municipalities, Utility Companies,
Design and Construction Engineers, and Contractors
Ensure compliance with State and Federal Standards regarding
design and construction projects with utility involvements
Review and Process PS&Es and Utility Documentation for LET
Provide construction oversight including, but not limited to,
facilitating utility conflicts during construction
MANAGEMENT CONSULTANT
MC REVIEWS (PRIOR TO PS&E):
Submittal materials - utility correspondence, emails, letters,
phone logs to ensure all steps of the utility coordination
process have been completed
Municipality approval of WORK PLANS (Roadway Permitting
Authority), design plans, plat, UTILITY LOG, and USR
**Designer provides copy of above to MC for WisDOT Project
File 28 days prior to PS&E Approval
MANAGEMENT CONSULTANT
COORDINATION BETWEEN PS&E & LET
THIS IS WHERE THOSE SPECIAL PROVISIONS ARE IMPORTANT:
If Specials state that they will be moving PRIOR/DURING –ORNOT AT ALL; documentation of utility commitments becomes a
major factor for bidding and scheduling of construction activities
Sponsor or Designer is responsible for monitoring and reporting
progress of utility relocations between PS&E and LET.
UTILITY COORDINATION DURING CONSTRUCTION
MC may assist in resolving utility conflicts
MANAGEMENT CONSULTANT
ROLE OF MANAGEMENT CONSULTANT
MC does NOT :
Ensure the accuracy of plans or utility involvements in
PS&Es
Approve Utility Work Plans on behalf of the Municipality
Grant permits to Utility Companies on behalf of the
Municipality
Issue Notice to Proceed to Utility Companies to begin
relocations or adjustments within Local Road R/W on
behalf of the Municipality
Utility Process Overview
UTILITIES MANUALS AND TOOLS
WisDOT Guide to Utility Coordination
 http://roadwaystandards.dot.wi.gov/standards/util/index.htm
WisDOT Guide to Utility Coordination (Chapter 17 – LPA)
 http://roadwaystandards.dot.wi.gov/standards/util/chapter17.pdf
WisDOT Facilities Development Manual (Chapter 18 – Utility Coordination)
 https://trust.dot.state.wi.us/static/standards/fdm/18-00-000toc.pdf
WisDOT FDM 18-15-1 & State Statutes (Utility Rights & Responsibilities)
 https://trust.dot.state.wi.us/static/standards/fdm/18-15-001.pdf
Title 23 CFR - Federal Aid Policy Guide (FAPG)
 http://www.fhwa.dot.gov/legsregs/directives/cfr23toc.htm
Utility Process Overview
LOCAL PROGRAM (FEDERAL-AID) PROJECTS DO NOT
FALL UNDER ADMINISTRATIVE RULE TRANS 220
 Use of Trans 220 forms is NOT allowed. MC will furnish similar forms that
have been created for the Local Program.
 Despite not falling under Trans 220, utility coordination process for all
Local Program Projects remains the same, including timeframes necessary
for coordination and approval of Utility Work Plans. Following utility
coordination LEAD TIMES during design is KEY (60/90/120 calendar days
afforded to Utilities for return of Work Plans)
UTILITY COORDINATION MEETINGS
Should have TWO (2) Meetings:
 Operation Planning Meeting (OPM) is required
 Recommended meeting for Plan submittal to Utility Companies for request
of UTILITY WORK PLANS
Utility Process Overview
UTILITY WORK PLANS FOR PS&E PURPOSES
Municipality (and Designer) reviews UTILITY WORK PLANS to Account for:
 WHAT the work is
 WHEN the work will be done
 WHO will be doing the work (utility company forces or contractors)
 WHERE they will be doing the work needed to clear construction
***Once ALL questions are answered, a clear picture should emerge of time
lines and activities.
NOTE: When requesting information from a utility, request Station/Outs to describe all
relocations of BOTH EXISTING & PROPOSED facilities.
Utility Process Overview
UTILITY STATUS REPORT (USR)
 NEW USR (DT1080) completed by the DESIGNER & Signed by LPPM
 ALL dates and columns are required to be filled in COMPLETELY with
necessary information
 DT 1080 instructions in Utility Guide CHAPTER 15
PS&E DOCUMENTS - REVIEW AND TIMING
 ALL UTILITY DOCUMENTS/MATERIALS SUBMITTED TO MC TWENTYEIGHT(28) DAYS PRIOR TO FINAL PS&E DATE (FDM 19-1-1)
 UTILITY SPECIAL PROVISIONS based on Municipality Approved utility
work plans
 USR reflects what is stated in APPROVED UTILITY WORK PLANS and
SPECIAL PROVISIONS
 COPIES of correspondence that documents commitments stated in PS&E
SPECIAL PROVISIONS
 STATUS of any compensable utility interest(s) and copies of those
documents
FY 11-14 Local Program Highlighted Projects
KENOSHA COUNTY
#5
3766-00-70
CTH E
Bridge Over Pike
River (Replace)
LET 08/11/2015
#1
3751-00-70
CTH W
CTH F– CTH FR
LET 09/08/2015
(Reconstruct)
#2
3736-00-72
CTH C
CTH KD– CTH W
LET 12/08/2015
(Reconstruct)
#3
3736-05-00
CTH C
CTH U – W Frontage Rd
No Scheduled LET
(Reconstruct)
#4
1693-35-75
Kenosha County
Park & Ride
LLC 05/25/2014
#6
3729-00-74
39th AVENUE
STH 165 – 97th St
LET 3/10/2015
(Reconstruct)
#2
2100-02-71
S. 35th STREET
Burnham to STH 59
LET TBD
(Reconstruct)
#3
2160-10-70
S 76th STREET (CTH U)
600 ft N OF W. High St –
Carter Blvd
LET 2/11/2014
(Cap Expansion)
#5
2660-05-70
S WHITNALL AVE
Bridge over Union Pacific RR
LET 02/10/2015
(Replacement)
#6
2987-00-14
5th AVENUE RELOCATION
STH 32 to Ryan Rd
No Scheduled LET
(Reconstruct)
MILWAUKEE COUNTY
Local Program Highlighted
Projects
#1
2984-16-71
W LLOYD STREET
N 60th St – N 47th St
LET 02/09/2016
(Reconstruct)
#4
2545-03-71
W HAMPTON AVE
Green Bay Ave – Teutonia Ave
LET 04/08/2014
(Reconstruct)
#8
2670-00-71
GREEN TREE ROAD
Jean Nicolet Rd to River Rd.
LET 07/08/2014
(Resurface)
#9
2155-03-71
FOND DU LAC AVENUE
Intersection with Sherman Blvd.
LET 11/11/2014
(Intersection Mod)
#10
2984-39-72
45TH STREET BRIDGE
Over Menomonee River
LET 02/11/2014
(Rehab)
#11
2160-15-70
S 76TH STREET
Intersection with Edgerton & Layton Ave
LET 03/10/2015
(Intersection Mod)
MILWAUKEE COUNTY
FY11-14 Local Program
Highlighted Projects
#7
2500-00-70
N GRANVILLE RD
Bridge over Little
Menomonee River
LET 07/08/2014
(Removal)
#16
2160-14-70
S 76TH STREET
W Greenfield to W Pierce
LET 07/08/2014
(Recondition)
#14
2080-00-71
NORTH TEUTONIA AVENUE
W. Capitol Ave to W. Ruby Ave
LET 3/10/2015
(Pavement Replacement)
#15
2505-00-75
S. 13TH STREET
West Forest Ave to W Windlake Ave
LET 04/14/2015
(Pavement Replacement)
#17
2405-00-74
W. MORGAN AVENUE
W. Forest Home Ave to S 43rd St
LET 8/11/2015
(Reconstruct)
MILWAUKEE COUNTY
FY11 -14 Local Program
Highlighted Projects
#12
2595-00-70
N 60TH STREET
W Fairy Chasm Rd to W Cnty Line
LET 3/10/2015
(Pavement Replacement)
#13
2968-02-70
RANGE LINE ROAD
Bridge over Milwaukee River
LET 11/11/2014
(Rehab)
OZAUKEE COUNTY
FY11 -14 Local Program
Highlighted Projects
#1
2697-00-75 MAIN STREET
Division Street to Concord Place
LET 03/10/2015
(Resurface)
FY11-14 Local Program Highlighted Projects
#1
2699-02-70
MALCINE ROAD
Bridge over Wind Lake Canal
LET 11/10/2015
(Replacement)
#2
3755-00-01
CTH D (Washington Ave)
Bridge over Fox River
NO SCHEDULED LET
(Replacement)
#3
3755-02-00
CTH D
Heritage Rd – Rochester Village Limits
LET 1/13/15
(Reconstruct)
#4
2704-00-73/74
OHIO STREET
16TH St to Washington Ave
LET 04/08/2014
(Reconstruct)
RACINE COUNTY
FY11-14 Local Program Highlighted Projects
#1
3841-00-71
BORG RD
Bridge over Swan Creek
LET 07/14/2015
(Replacement)
#2
3849-00-71
CTH DD
Bridge Sugar Creek
NO SCHEDULED LET
(Replacement)
#3
3849-00-71
SHERIDAN SPRINGS RD
Bridge over White River
LET 7/08/2014
(Replacement)
WALWORTH COUNTY
FY11-14 Local Program
Highlighted Projects
WASHINGTON COUNTY
#1
3944-00-01
CTH N (STATE STREET)
Dodge Cnty Limits to Airport Dr.
LET 1/13/15
(Reconstruct)
#2
2712-00-01
DONGES BAY ROAD
Division Rd. S to STH 145 N
NO SCHEDULED LET
(Pavement Replacement)
FY11-14 Local Program Highlighted Projects
#1 (Replacement)
2949-00-70
CTH CW (MAPLETON RD)
Bridge over Ashippun River
LET 03/10/2015
#2
2718-00-74
SUMMIT AVENUE
2nd St. to Thackery Trail
LET 06/10/2014
(Reconstruct)
#3
2714-04-70
SAWYER RD (CTH P)
Bridge over Bark River
LET 03/10/2015
(Replacement)
#1 (Approaches)
3947-05-71
CTH CW
Amber Ln. to 1000’ of Amber Ln
LET 03/10/2015
#4
2758-01-70
CTH JJ Intersect
with CTH J & CTH SR
LET 07/14/2015
(Intersection Mod)
#5
3853-00-72
WEST LAKE DRIVE
CTH P – Road B
LET 3/10/2015
(Resurface)
#6
2370-00-73
CTH F(REDFORD RD)
Busse Rd to STH 190
South Ramp
LET 02/11/2014
(Recondition)
#7
2722-11-70
LINCOLN AVENUE
Calhoun Rd – CTH O
LET 02/11/2014
(Reconstruct)
#8
2722-10-70
COFFEE ROAD
Calhoun – National
LET 1/14/2014
(Reconstruct)
#9
2718-12-70
S EAST Avenue
Sunset Dr – Wabash Ave
LET 12/9/2014
(Reconstruct)
WAUKESHA COUNTY
FY11-14 Projects & FY13-18 Projects
SUNSET DATES
PROJECTS THAT WERE APPROVED IN THE FY2011-2014
CYCLE BUILT BY JUNE 30, 2017.
PROJECTS THAT WERE APPROVED IN THE FY2013-2018
CYCLE BUILT BY JUNE 30, 2020.
WisDOT Programs for Local Governments
FY13-18 Projects - 28 Roadway & 15 Bridge Projects
HTTP://WWW.DOT.STATE.WI.US/LOCALGOV/INDEX.HTM
Questions/Answers
Thank You for Listening!