UPDATES ON APPROVED SCHEMES

GOVT OF KHYBER PAKHTUNKHWA HOUSING DEPARTMENT
APPROVED ADP 2014-15 SCHEMES AND THEIR PROGRESS
S.No
1
2
521/50147 : For Payment to Pakistan Housing
Authority on A/C of Purchase of Housing Colony
Nasapa Payan, Peshawar SH: Completion of Balance
Works on Housing Colony Nasapa Payan
Constructed under Supervision of PHA, Islamabad.
S.H: Completion of Balance Works.
522/100349 - F/S & Construction of Flats at Civil
Quarters, Peshawar.
3
523/100353 - Construction of High-Rise Flats for Govt.
Servants at Phase-V Hayatabad, Peshawar.
4
524/120818 - Launching of Housing
Schemes for Government Servants and General Public
at Jalozai Nowshera. (Self Finance)
5
1
Name of the Work with approval status
525/50191 - F/S for Establishment of Housing
Schemes for Govt. Servants and General Public in
Khyber Pakhtunkhawa. S.H: Mulazai Housing Scheme
Warsak Road Peshawar.
Approved
cost
349.566 m
1087.630
m
1115.126
m
Allocation dg;
CFY
Physical progress
44.840
Construction of 06 Nos flats in Block “J” is in process.
Construction of main sewerage line is completed only main holes
and small portions near C.N.G station and adjacent abadies are
remaining. . Provision of Gas Pipe line is still awaited.
200.000
Construction of 2600sqft & 2000sqft Building is in progress. The
progress suffered due to not allowing further stories by F.C
Authorities.
400.000
The pre-qualification is in process and tender will be floated in due
courses.
Entire road network tendered and work has been started at site.
11494.44
m
(Self Finance)
Basic infrastructure almost 90% completed. Provision of External
Electrification is still awaited.
258.865 m
99.681
6
7
8
2
526/100211 - Development of Various Housing
Schemes on the Existing State Land for Government
Servants / General
Public in Khyber Pakhtunkhawa. S.H: Jerma Township
District Kohat.
526/100211 - Development of Various Housing
Schemes on the Existing State Land for Government
Servants / General
Public in Khyber Pakhtunkhawa. S.H: Havelian
Township District Abbottabad.
527/110142 – Institutional Strengthening of Housing
Department & Conducting of
Various Studies / Seminars /Planning of Different
Housing Activities in Khyber
Pakhtunkhawa.
The physical progress is badly suffered due to local litigations
which are still in process.
263.515 m
186.653
Construction of road is process (Sub base laid). R/Wall completed,
dressing of lawns and construction of O.H.R is in process.
145.948 m
(Self Finance)
54.167 m
19.824
Scheme is in progress