Progress Report

PUBLIC WORKS DEPARTMENT GOVERNMENT OF KERALA KERALA STATE TRANSPORT PROJECT ‐ II UNDER WORLD BANK ASSISTANCE – Loan No. 5284 MONTHLY PROGRESS REPORT JULY 2014 Project Management Team Kerala State Transport Project T.C.11/339, JAGAD Building Keston Road, Nanthancode, Kawdiar P.O Thiruvananthapuram ­695003 Kerala State Transport Project - II
____________________________________________________________
PUBLIC WORKS DEPARTMENT GOVERNMENT OF KERALA KERALA STATE TRANSPORT PROJECT ‐ II UNDER WORLD BANK ASSISTANCE – Loan No. 5284 MONTHLY PROGRESS REPORT JULY 2014 Project Management Team Kerala State Transport Project T.C.11/339, JAGAD Building Keston Road, Nanthancode, Kawdiar P.O. Thiruvananthapuram ­695003 Monthly Progress Report – July 2014 Page 2 Kerala State Transport Project - II
____________________________________________________________
Table of Contents
EXECUTIVE SUMMARY ................................................................................ 6 1.1 Project Development Objectives ................................................................................................... 6 1.2 Project Components....................................................................................................................... 6 1.3 Component A - Road Network Upgrading and Safety Improvement (US$ 413 million) ........... 6 1.4 Component B - Road Safety Management (US$ 22 million) ........................................................ 7 1.5 Component C - Institutional Strengthening (US$ 10 million)...................................................... 7 1.6 Implementation Arrangements ...................................................................................................... 7 1.7 Project Description ........................................................................................................................ 7 1.8 Sub Component A1 ....................................................................................................................... 7 1.9 Sub Component A2 ....................................................................................................................... 8 1.10 Component B – Road Safety Management ................................................................................... 8 1.11 Component C – Institutional Strengthening .................................................................................. 9 1.12 Project Cost ................................................................................................................................... 9 1.13 Project location map .................................................................................................................... 11 2.1 Upgradation Works ..................................................................................................................... 12 2.2 Summary of Progress (works) ..................................................................................................... 12 2.3 Details of Supervision Consultanty Services: ............................................................... 13 2.4 Current Status of Upgradation Works ............................................................................ 14 2.5 Contract Package I ....................................................................................................................... 14 2.6 Contract Details ........................................................................................................................... 14 2.7 Progress of Works ....................................................................................................................... 15 2.8 Summary of progress for major items is as follows: ................................................................... 15 2.9 Progress Considering the Contract price up to July 2014............................................................ 15 2.10 Physical progress Bar Chart ........................................................................................................ 16 2.11 Physical progress S Curve ........................................................................................................... 16 2.12 Payments to the Contractor.......................................................................................................... 16 2.13 Potential Issues ............................................................................................................................ 17 2.14 Implementation of EMP .............................................................................................................. 17 2.15 Institutional Arrangements of Contractor .................................................................................... 17 2.16 Environment Management at Project Ancillary Facilities ........................................ 17 2.17 Compliance with Statutory Clearances .......................................................................... 18 2.18 Environment Management at Work Sites ...................................................................... 19 2.19 Traffic Management and Road Safety Measures ......................................................... 19 2.20 Environmental Quality Monitoring .................................................................................. 19 3.1 Contract Package II ..................................................................................................................... 20 3.2 Contract Details ............................................................................................................ 20 3.3 Progress of Works ....................................................................................................................... 21 3.4 Physical Progress Bar Chart ........................................................................................................ 22 3.5 Physical Progress S Curve ........................................................................................................... 22 3.6 Payments to the Contractor.......................................................................................................... 22 3.7 Potential Issues ............................................................................................................................ 23 4.1 Implementation of EMP ..................................................................................................... 24 4.2 Institutional Arrangements of Contractor ..................................................................... 24 4.3 Staff engaged by the Contractor for EMP implementation. ..................................... 24 4.4 Environment Management at Project Ancillary Facilities ........................................ 24 4.5 Compliance with Statutory Clearances .......................................................................... 25 4.6 Environment Management at Work Sites .................................................................................... 26 4.7 Traffic Management and Road Safety Measures......................................................................... 27 4.8 Environmental Quality Monitoring ............................................................................................. 27 5.1 Contract Package III .................................................................................................................... 27 5.2 Contract Details ........................................................................................................................... 28 5.3 Progress of Works ....................................................................................................................... 28 5.4 Potential Issues ............................................................................................................................ 30 Monthly Progress Report – July 2014 Page 3 Kerala State Transport Project - II
____________________________________________________________
5.5 Nonconforming Product Notification ............................................................................... 30 5.6 Physical Progress Bar Chart ........................................................................................................ 32 5.7 Physical Progress S Curve ........................................................................................................... 32 5.8 Works Programme ....................................................................................................................... 32 5.9 Payments to the Contractor ............................................................................................... 33 5.10 Implementation of EMP ....................................................................................................... 33 5.11 Institutional Arrangements of Contractor ..................................................................... 33 5.12 Environment Management at Project Ancillary Facilities ........................................ 33 5.13 Compliance with Statutory Clearances........................................................................................ 34 5.14 Environment Management at Work Sites .................................................................................... 35 5.15 Traffic Management and Road Safety Measures......................................................................... 35 5.16 Environmental Quality Monitoring ............................................................................................. 35 6.1 Contract Package IVA ................................................................................................................. 36 6.2 Contract Details ........................................................................................................................... 36 6.3 Progress of Works ....................................................................................................................... 36 6.4 Mobilization of Resources ........................................................................................................... 36 6.5 Plant and Machinery .................................................................................................................... 36 6.6 Materials ...................................................................................................................................... 36 6.7 Work Progress ............................................................................................................................. 37 6.8 Implementation of EMP – Contract Package IVA ...................................................................... 37 6.9 General ........................................................................................................................................ 37 6.10 Institutional Arrangements of Contractor .................................................................................... 37 6.11 Environment Management at Project Ancillary Facilities........................................................... 37 6.12 Payment ....................................................................................................................................... 37 7.1 Contract Package IV .................................................................................................................... 38 7.2 Upgradation of Road from Chengannoor to Ettumannoor of SH-1............................................. 38 7.3 Scope of Works (45.40 Km) ........................................................................................................ 38 8.1 Contract Package V ..................................................................................................................... 38 8.2 Pre-Construction Activities ................................................................................................ 38 8.3 Contract Details ........................................................................................................................... 39 8.4 Progress achieved is 0.52% against the target of 5.45%. ......................................... 39 8.5 Pre-Construction Activities ......................................................................................................... 40 8.6 Mobilization of Resources ........................................................................................................... 40 8.7 Work Progress ............................................................................................................................. 41 8.8 Work Programme ........................................................................................................................ 41 8.9 Design changes ............................................................................................................................ 42 8.10 Quality Control ............................................................................................................................ 42 8.11 Mix Designs................................................................................................................................. 42 8.12 Important/Key/Potential Issues.................................................................................................... 43 9.1 Contract Package VI ..................................................................................................... 43 10.2 Description of work ............................................................................................................... 44 10.3 Construction Supervision Services – Package VI ....................................................................... 45 10.4 Consultant – Details .................................................................................................................... 45 10.5 Mobilization Status of works ....................................................................................................... 46 10.6 Quality Control ............................................................................................................................ 47 11.1 Contract Package VII .......................................................................................................... 47 13.0 Contract Package VIII ................................................................................................................. 48 13.1 New work .................................................................................................................................... 48 13.2 Road Safety ................................................................................................................................. 48 13.3 Institutional Strengthening Components – Current Status .......................................................... 49 14.0 Meetings, Site visits & Inspection ............................................................................................... 49 14.1 Package – I .................................................................................................................................. 49 14.2 Package – II ................................................................................................................................. 50 14.3 Package – III ................................................................................................................................ 50 Monthly Progress Report – July 2014 Page 4 Kerala State Transport Project - II
____________________________________________________________
14.4 14.5 14.6 14.7 14.8 14.9 Package – V ................................................................................................................................. 51 Package VI................................................................................................................................... 51 Land Acquisition Status .............................................................................................................. 51 Payment to consultant M/s Egis India JV with M.s Egis International .............. 52 Key action taken on Critical Issues pointed out during World Bank Mission in Aide Memoire 53 List of Annexure: ......................................................................................................................... 55 Monthly Progress Report – July 2014 Page 5 Kerala State Transport Project - II
____________________________________________________________
EXECUTIVE SUMMARY
Consequent to the completion of KSTP-I, the State Govt. decided to take up the KSTP-II,
the delinked portion (Phase-II upgradation) along with one additional road as a separate
project, KSTP-II,. In 2011 the revised, project proposal covering upgradation of 363 Km
SH & MDR, Road Safety and institutional strengthening in PWD (continuation of reforms
process) was presented to the DEA by the State Govt., seeking World Banks (IBRD)
Financial Assistance. The State’s consistent efforts proved to be successful when the
DEA and the World Bank agreed to include this project in the Bank’s pipeline of projects
for assistance for the Fiscal 2012. The Bank’s Board met at Washington and approved
the loan assistance of US$ 216 million for the project, with an overall outlay of Rs. 2403
crores (US$ 445) million. The project implementation schedule has been fixed as 20132018. The Project and Loan Agreements signed on 19-06-2013 at New Delhi.
1.1 Project Development Objectives
The Project Development objective is to improve condition, traffic flow and road safety
with a focus on vulnerable road user on Kerala State Core road networks comprising of
363 Km of state highways. The main beneficiaries of the Project will be the users living
along the Project corridors mainly the travelling public, agricultural and industrial
producers, consumers and local community. The main benefit is in the form of reduced
transport bottlenecks, lower passenger freight transport costs, reduced travel time and
improved road safety in terms of reducing severe crashes and injury. The road identified
for improvement passes through about 87 villages covering eight districts.
1.2 Project Components
1.3
Component A - Road Network Upgrading and Safety Improvement
(US$ 413 million)
This component consists of Road Network upgrading and safety improvement of 363 Km
of important state highways. The existing intermediate line roads will be upgraded to a
full two-lane standard with paved shoulder with 1.5 m on either side. The civil work
includes road widening, strengthening of pavements improving bridges, cross-drainage
and longitudinal drains, improving stability of side slopes, enhancing road safety and
traffic management measures. The sub component is again sub divided as A1 and A2
and procured through FIDIC based Contracts and PPP modified Annuity.
1.3.0.1 Subcomponent A1 (US$ 322 million)
This sub component will include upgrading 281 Km comprising of 8 civil contracts,
consultancies, procurement of goods etc.
1.3.0.2 Subcomponent A2 (US$ 91 million)
This sub component will include upgrading 82 Km of State Highways through a PPP
modified Annuity Concession, a pilot approach in the State. In this component upfront
construction cost support of 40% of the Contract Value (US$ 33 million) will be
supported by World Bank.
Monthly Progress Report – July 2014 Page 6 Kerala State Transport Project - II
____________________________________________________________
1.4 Component B - Road Safety Management (US$ 22 million)
This component consists of Road Safety management System in Kerala with an objective
of reducing accidents across the state roads including project roads. This road safety
component includes safe corridor demonstration project (80 Km of Kazhakkutam –
Taikod – Kottarakara - Adoor), improvement of road safety using challenge fund,
strengthening road safety management capacity of road safety authority, road safety cell
in PWD.
1.5
Component C - Institutional Strengthening (US$ 10 million)
The objective of this component is to improve the sustainability of Kerala’s state road
network with respect to its functional adequacy, financial viability and capacity of key
state road sector institutions to deliver road infrastructure and services. This component
consists of road sector modernization action plan, network maintenance planning and
implementation and community engagement and road user satisfaction.
1.6 Implementation Arrangements
PWD has the overall responsibility for implementation of the Project. PWD has delegated
the offices of KSTP which was formed in KSTP 1 to undertake day to day management of
the Project. The Project management team (PMT) has been established under the control
of Project Director specifically to manage the Project. PMT will be responsible for
planning, budgeting, procurement, implementation, coordination, management and
monitoring of various components such as resettlement action Plan and Environmental
Action Plan. Chief Engineer is also appointed to support the Project Director in all
activities. On ground 5 divisional offices also formed headed by 2 Superintending
Engineers, 5 Executive Engineers and other support staff. An organization chart is
shown as Annexure – 1.
1.7 Project Description
1.8 Sub Component A1
Consists of the following civil contracts:
SI.
NO.
CONTRACT PACKAGE
NAME OF WORK
LENGTH (KM)
1.
KSTP-II/UG-1
Kasargod – Kanhangad
27.78
2.
KSTP-II/UG-2
Pilathara – Pappinisery
20.90
3.
KSTP-II/UG-3
Thalassery – Valavupara
54.00
4.
KSTP-II/UG-4
Chengannoor - Ettumannoor
45.40
5.
KSTP-II/UG-5
Ettumannoor- Muvattupuzha
40.96
6.
KSTP-II/UG-4A
Thiruvalla Bypass along Chengannoor Ettumannoor
2.3
7.
KSTP-II/UG-6
Ponkunnam - Thodupuzha
50
8.
KSTP-II/UG-7
Perumbilavu - Perinthalmanna
41
Monthly Progress Report – July 2014 Page 7 Kerala State Transport Project - II
____________________________________________________________
1.8.0.1 Supervision Consultancy
Under this component 2 supervision consultancies CSC1 and CSC 2, 2 Independent
engineering services, Transaction Advisory Service for PPP are included. Contract
Agreement for Consultancy for CSC 1 for 190 Km of upgradation road has been executed
with M/s Egis International in JV with Egis India Consulting Engineers Pvt. Ltd on
28.02.2013 and mobilized and in place.
Egis has established rented office for Team Leader at Thiruvananthapuram near to
Client’s Office and started functioning from April 2013. Also RE offices at Kanhangad in
Kasargod District for package - 1, Pazhyangadi in Kannur District for package – II and at
Uliyil near Mattannur in Kannur District for package – III are functional. Consultants
mobilized most of the key staff. Resident Engineer for Package 4 & 5 also mobilized.
Vehicles required for CSC have been provided through Civil Works Contract. Payment for
CSC1 up-to October’13 cleared.
The procurement for the Supervision Consultancy, CSC 2 for Ponkunnam – Thodupuzha
Road has been completed and contract signed. M/s MSV International USA is the
identified consultant. The length of road covered is 80 km and the fee quoted is Rs. 4.40
crores. The consultant has been mobilized and commenced services.
1.8.0.2 Procurement of Goods for Utility Shifting
Procurement of goods for electrical, water utility shifting is also included under the
above component. Goods for 3 contract packages 1, 2, 3 for Milestone 1 activities
completed and materials issued to the concerned contractors. Arrangement of issue of
materials for Package V is done and issue in progress. Further requirement of material
both electrical and water supply are being issued as per request of the contractor.
1.9 Sub Component A2
DPR for this sub component (Punalur – Ponkunnam – 82 Km under PPP) completed and
schedule prepared by the consultants. The Technical Proposal received from the
consultant is big evaluated. The RFP has been forwarded to the shortlisted consultant.
The procurement of Independent Engineer will be initiated after the finalization of PPP
Contract.
1.10 Component B – Road Safety Management
The baseline survey for the proposed safe demonstration corridor has been completed by
‘NATPAC’ and report shared with Bank. Consultancy Services for the Capacity Building
and Road safety Management has been initiated and 6 Consultants have been
shortlisted. The RFP has been issued to the shortlisted consultants and five Consultants
have responded the RFP. The technical proposal and financial proposal evaluation has
been completed. M/s VicRoads, Australia in association with M/s Price water house
Cooper has been selected based on QCBS selection process. This was placed before the
Steering Committee held on 28.June 2014 and the committee approved the highest
ranking firm in the combined evaluation, M/s VicRoads, Australia. They are invited for
negotiation on 28.07.2014.
Monthly Progress Report – July 2014 Page 8 Kerala State Transport Project - II
____________________________________________________________
1.11 Component C – Institutional Strengthening
1.11.0.1
Consultancy Services
The following Consultancy services were procured.
1. Consultancy for Road User Perception Survey mobilized and completed for 363
Km of Project Road through M/s Sherwood Consultants and report shared with
Bank during last mission.
2. Consultancy for Prioritization and DPR Preparation for 1000 Km of Improvement
of State roads was entrusted with M/s Egis India Consulting Engineers Pvt. Ltd
and draft report submitted. The Estimate for the 400 Km requires some revision
and will be completed soon. Balance 600 Km, DPR will be completed through
KHRI and is in progress. Government approval has been sought for posing the
Project for World Bank’s loan assistance.
3. Consultancy for Strategic Option Study (SOS) for 8570 Km newly declared MDR
was also mobilized and completed by M/s CDM Smith Associates Pvt. Ltd. Study
report has been handed over to PWD and further action will be taken by them
using their own funds.
4. Consultancy for Developing Multi Model Integrated Transport Hub at 3 cities,
Trivandrum, Kozhikode and Kochi was also included under this component.
Consultancy Services awarded to M/s L&T Ramboll Consulting Engineers. The
draft final report has been submitted.
5. A review of the existing IT initiatives implemented in PWD under KSTP 1 Project
has been completed through an IT expert and report shared with Bank. The SoS
for identifying a Core Road work for PWD and developing a RMS have been
proposed as separate consultancy services and ToRs prepared.
6. The EoI notification for Strategic Road Network Program has been submitted to
Bank and is under review.
7. There are other consultancy services also which are enclosed under the Progress
Review of the respective components.
1.12 Project Cost
Total Project Cost US$ 445 million. World Bank is financing US$ 216 million.
Sl
No
Claim
Date
EXPENDITURE
in Lakh
AMOUNT
CLAIMED
in Lakh
DISBURSED
USD in
millions
BALANCE
FUNDS
AVAILABLE FOR
CLAIM (MUSD)
0.54
215.46
1.69
213.77
In INR
216.00
Front end fee
1
Retroactive
2
1st Quarter
3
2nd Quarter
4
3rd quarter
5
4th quarter
15.06.13 to
15.06.14
1,863.95
1,043.00
213.77
01.07.13 to
30.9.13
01.10.13 to
31.12.13
01.01.14 to
Monthly Progress Report – July 2014 1,355.79
764.00
1.23
212.54
1,906.01
1,071.00
1.71
210.82
2,696.00
1,510.00
2.50
208.32
Page 9 Kerala State Transport Project - II
____________________________________________________________
20.03.14
6
1st Quarter
21.03.14 to
31.03.14
01.04.14 to
18.06.14
Monthly Progress Report – July 2014 53.79
30.00
0.05
208.27
1,826.41
1,023.00
1.70
206.57
9,701.95
5,441.00
9.43
Page 10 Kerala State Transport Project - II
____________________________________________________________
1.13 Project location map
Monthly Progress Report – July 2014 Page 11 Kerala State Transport Project - II
____________________________________________________________
2.1 Upgradation Works
Bids were invited for the Contract Packages 1 & 2 on 31.10 2012, Contract package 3 on
12.12. 2012 and Contracts awarded to the lowest evaluated Bidders after getting NOC
from Bank. The bids for package 4 & 5 were invited on 17.04.2013 and lowest evaluated
bidders selected. Letter of acceptance was issued on 30.11.2013. Bids for Package 4A
invited on 02.07.2013 as per NCB norms and Letter of Acceptance was issued on
29.10.2013. Bids for Package 6 were invited on 27.09.2013 and notice to commence
work was issued on 10.06.2014.
363 Km of upgradation civil works are divided into 9 Contract packages.
SI.
CONTRACT
Contractor
NAME OF WORK
NO.
PACKAGE
1.
KSTP-II/UG-1
Kasargod – Kanhangad
RDS Projects, Kochi
2.
KSTP-II/UG-2
Pilathara – Pappinisery
RDS Projects, Kochi
3.
KSTP-II/UG-3
Thalassery – Valavupara
SACYR-ESSAR JV
4.
KSTP-II/UG-4
Chengannoor - Ettumannoor
Under
rearrangement
5.
KSTP-II/UG-5
Ettumannoor- Muvattupuzha
NAPC Ltd, Chennai
6.
KSTP-II/UG-4A
Thiruvalla Bypass along
(Chengannoor – Ettumannoor)
EKK & Co, Kochi.
7.
KSTP-II/UG-6
Ponkunnam - Thodupuzha
GHV – EKK JV
8.
KSTP-II/UG-7
Perumbilavu – Perinthalmanna (EPC)
-
9
KSTP-II/UG-8
Punalur – Ponkunnam (PPP)
-
The works are being executed under FIDIC (5th edition) Conditions of Contract. The
work involves improvement of State Highways including geometric improvements and
realignments to standard 2-lane of 7 m carriageway, 1.5 m paved shoulders, and soft
shoulders. The Construction Works include:
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
Widening the existing pavement where it is less than design width;
Scarification, clearance, earthworks,
granular sub-base, wet mix macadam base course, bituminous mix surfacing,
Construction of overlays to the existing pavement, inclusive of regulating course
to a designed vertical profile;
Geometric realignments at specific locations;
Construction of paved shoulders;
Construction and maintenance of diversion roads
Construction of lined and unlined longitudinal drains, covered drains and
footpaths in urban areas;
New culverts, new bridges and rehabilitation of existing bridges/culverts and
protective works
Provision of road signs and markings;
Provision of traffic safety features - road furniture and other road safety
appurtenances,
Routine maintenance and maintenance during Defects Notification Period.
Environmental protection measures and Social enhancement works/ landscaping
works etc.
2.2 Summary of Progress (works)
The following tables present the summary of progress in each contract package
considering contract price.
Monthly Progress Report – July 2014 Page 12 Kerala State Transport Project - II
____________________________________________________________
Cumulative
Contract packages
Contract value
target in
(Rs. Crore)
percentage up to
end of July 2014
Achieved
cumulative
percentage upto
Balance period
(months)
end of the July
2014)
KSTP/PMT/UG-I
1,33,05
74.00
10.52
9
KSTP/PMT/UG-II
118.20
65.87
8.18
9
KSTP/PMT/UG-III
234.99
40.40
2.58
17
* KSTP/PMT/UG-V
171.49
5.45
0.58
24
31.80
-
-
-
* KSTP/PMT/
UG-IVA
28
KSTP/PMT/UG-VI
227.13
-
-
(preconstruction
activities in
progress)
Steering
Committee
recommended
KSTP/PMT/UG IV
293.00
-
-
lowest evaluated
bidder M/s
DelmaSreedhanya JV
for award.
* Pre-construction and mobilization in progress
The following sections describe Civil Works Contract packages in detail:
2.3 Details of Supervision Consultanty Services:
Name of consultant
CSC-1 – M/s Egis
International in JV
with M/s Egis India
Pvt. Ltd.
CSC-2 – M/s MSV
International USA
Contract
signed
Contract
Period
Commencement
Date
Contract
Amount (Rs.)
28.02.2013
42 months
04.04.2013
18,36,04,600
14.05.2014
30 months
14.05.2014
4,41,88200
Monthly Progress Report – July 2014 Page 13 Kerala State Transport Project - II
____________________________________________________________
2.4 Current Status of Upgradation Works
2.5 Contract Package I
Upgradation of Road from Kasargod to Kanhangad of SH 57
Scope of Works
Viaduct
Major Bridge
Minor Bridge
Widening Bridge
New culverts
Widening Slab culverts
Reconstruction
Foot path
Drain
Solar Lights
–
–
_
–
_
–
_
_
–
1
2
2
2
16
16
9
6.7 Km
22.20 Km
2.6 Contract Details
Letter of Acceptance Date
06.03.2013
Agreement Date
01.04.2013
Name of Contractor
Contract Price
Notice to Commence
M/s RDS Projects Ltd, Kochi
Rs.133,05,79,485/24.04.2013
Total Length
27.78 Km
Contract Period
24 months
Completion Date
23rd April 2015
Defect Liability Period
365 days
1st Milestone
Km. 0+000 – Km. 10+000 - 22nd February 2014 (original)
24th September 2014 (revised)
2nd Milestone
Km. 0+000 – Km. 20+000 - 22nd October 2014
3rd Milestone
Km. 0+000 – Km. 27+780 - 23rd April 2015
Monthly Progress Report – July 2014 Page 14 Kerala State Transport Project - II
____________________________________________________________
2.7 Progress of Works
2.8 Summary of progress for major items is as follows:
Milestone
I
II
III
Length in km
10
20
27.78
Length handed over to contractor in km
10
20
27.78
Unencumbered land available to the contractor
in km
10
20
27.78
Stretch completed in all respects in km
0
0
0
FW
HW
GSB completed in km
0.88
4.04
WMM completed in km
0.84
2.75
DBM completed in km
0.80
2.52
BC completed in km
0
CD completed in Nos.
12
2.9 Progress Considering the Contract price up to July 2014.
Up to previous
Month
This Month
Cumulative to end of
this Month
Target
Achieved
Target
Achieved
Target
Achieved
74%
9.04%
0%
1.48%
74%
10.52%
Monthly Progress Report – July 2014 Balance period
(months)
9
Page 15 Kerala State Transport Project - II
____________________________________________________________
2.10 Physical progress Bar Chart
2.11 Physical progress S Curve
2.12 Payments to the Contractor
Mobilization advance, Equipment advance and Interim payment Certificate for works
(IPC 5) was paid to the Contractor amounting to Rs.22,53,36648/-
Monthly Progress Report – July 2014 Page 16 Kerala State Transport Project - II
____________________________________________________________
2.13 Potential Issues
•
Lack of experienced staff at site which reflected in planning of works at site, delay in
preparing mix designs, delay in submission of working cross sections, in preparation
of survey data etc.
•
The KSTP and the Contractors are coordinating with various Service Providers like
KSEB, KWA, BSNL, Forest and other departments for shifting of utilities.
•
Crusher operation interrupted by Public and Contractor brought to the notice of Dist.
Collector and Public representatives and Issues are now resolved.
•
Monsoon rain started last month and though the rain is not continuous, Contractor
not taking the risk of carrying out bituminous works. Only concrete works are in
program.
•
Monthly Achieved Progress is not near the targets. Instructions issued to Contractor
for taking measures to enhance the progress of works.
•
Poor cashflow of the contractor
•
Quarry Owners Association started strike for 25.07.2014 and all quarry and crushers
stopped production.
2.14 Implementation of EMP
2.15 Institutional Arrangements of Contractor
The details of staff engaged by the contractor for EMP implementation are
presented below:
Table 10.1: Staff engaged by the Contractor for EMP implementation
Name
Sanal K P
Designation
Environmental Engineer
Mobilisation Date
25 July 2013
2.16 Environment Management at Project Ancillary Facilities
The contractor has established two base camps at the locations detailed below.
Table 10.2: Details of Construction Camps
Camp identity
Camp-1 for Quarry, Crusher,
Workshop, Hot Mix Plant, Labour
camp
Camp-2 for WMM plant, Batching
Plant, Precast yard, Office, Store,
Field Laboratory.
Location
about 5 acres of land, 40Km
away from Ch.27+780
5 acres of Land at Ch.15+100
LHS (6km from project road)
Village
Madhamangalam .
Camp 1 is common to
package 1 & 2
Pallickara
Table 10.3: Environment Management Facilities at Ancillary facilities
Sl.No.
1
Details of
Camp/Plant
Construction
camp
Environment Management Facilities Provided
Provided with sanitary toilet facilities, drinking water supply,
and solid waste collection facilities.
Internal roads are developed partially by utilising the
Monthly Progress Report – July 2014 Page 17 Kerala State Transport Project - II
____________________________________________________________
2
Labour Camps
3
Quarry, Crusher,
Hot mix plant
Borrow area
4
5
Debris Disposal
sites
6
Water Sources
7
Workshop for
Heavy Vehicles
8
Water Sprinklers
construction debris obtained during the tarred surface cutting.
Ornamental plants and banana plants were planted in the free
space Generators are provided with vertical stack of adequate
height.
Waste oil storage facilities are provided with floor and roof.
The solid waste disposal facility like compost pit is not provided.
Oil interceptors are not yet provided.
Water supply and toilet facilities provided to the staff quarters
and labour camps.
The toilets with septic tanks and soak pit
Dust bins provided for collection of solid wastes. Disposal
facilities like compost pits to be provided.
Cooking at labour camp is done partially at open area.
LPG connections are provided for cooking.
Ornamental plants and vegetables are planted in the free space
available.
The details of new site for labour camp not reported to the CSC
for approval.
These facilities are common for package- I & II and are managed
by Package II.
Not identified
Cut earth from roadway may be sufficient
Not identified. Debris heaped along the construction site.
The clay from piling activities at CH-3+392 are collected in
earthen pits and likely to overflow into the stream. Urgent
action has to be taken to identify debris disposal sites.
3 Bore wells at camp. Acceptance from Ground Water
Department for construction of tube well issued.
Workshop established at construction camp site-1. The
floor of the workshop area was seen concreted. Work for
oil interceptor started this month.
Water tankers provided to sprinkle water at construction
sites and camps.
Instructions were given to provide water sprinkling
facilities at the crusher and quarry.
2.17 Compliance with Statutory Clearances
The action taken by Contractor for complying with statutory requirements is
summarized in below:
Table 10.4: Compliance with Statutory Requirements
Unit
Crusher
Hot Mix
Plant
Base camp
Quarry
Status of Compliance
Consent to Establish and Operate from
Kerala State Pollution Control Board
obtained.
Building permit obtained from Grama
Panchayat.
Consent to Establish and Consent to
Operate from Kerala State Pollution
Control Board were obtained.
Consent to Establish and Consent to
Operate from Kerala State Pollution
Control Board obtained.
Obtained Consent to Operate from Kerala
State Pollution Control Board and permit
from Mining and Geology Department.
Explosive Licence from Deputy Controller
of Explosives, Ernakulum obtained
Monthly Progress Report – July 2014 Remarks
A common crusher is planned
for Package-1 & 2.
A common Hot Mix Plant is
planned for Package-1 & 2.
Common for package 1 & 2.
Page 18 Kerala State Transport Project - II
____________________________________________________________
2.18 Environment Management at Work Sites
Site visit conducted by Environmental Engineer of CSC on 14-05-2014 and reviewed the
measures taken by the Contractor for implementing the mitigation measures proposed
in the EMP. Instructions were given to avoid accumulation of debris along the project
site and to remove the debris from the site periodically. Regular sprinkling of water at
active work phase and maintenance of proper records of water sprinkling are to be
carried out.
As the measures adopted by the Contractor for implementing EMP is not satisfactory,
recommended for imposing penalty as per contract agreement. Accordingly RE has
imposed of penalty that is 10% of the interim payment certificate will be withheld from
next IPC as per sub clause 14.6 of part B specific provision.
World Bank Team including the Environmental Specialist visited the project site on 21st
May 2014 and reviewed the progress of implementation of EMP. World Bank Team
instructed the contractor for making the arrangement for solid waste disposal. They also
stressed the need for adequate waste collection bins and proper fencing to electrical
panel board with danger sign board at all major construction sites.
2.19 Traffic Management and Road Safety Measures
The Contractor has provided safety precautions such as flags, safety signboards, traffic
cones, blinkers and safety tapes at the work site. The Contractor is also required to
provide personal safety equipment to his workers such as jackets, safety shoes, face
shields, and hand gloves as appropriate to the nature of their work. The workers at
various locations were seen not using personal safety equipments.
The Contractor has provided safety precautions which was inadequate. Therefore RE has
imposed damages as per sub clause 17.2 of part B specific provision for various
locations.
2.20 Environmental Quality Monitoring
The impact of project activities on environment was checked through water and air
quality monitoring. Air quality monitoring was also conducted through accredited
laboratory on 20-21 March 2014 at two locations. Monitoring report from the laboratory
is awaited.
Monthly Progress Report – July 2014 Page 19 Kerala State Transport Project - II
____________________________________________________________
3.1 Contract Package II
Upgradation of Road from Pilathara to Pappinisery of SH 67
Scope of Works
New ROB
Repair of Bridge
New Box culverts
Widening Slab culverts
Reconstruction
Drain
Foot path
Solar Lights
–
–
_
–
_
–
_
2
2
9
20
8
26.04 Km
12.6 Km
3.2 Contract Details
Letter of Acceptance Date
05.03.2013
Agreement Date
01.04.2013
Name of Contractor
Contract Price
Notice to Commence
M/s RDS Projects Ltd, Kochi
Rs.118,29,77,833/23.04.2013
Total Length
20.90 Km
Contract Period
24 months
Completion Date
22nd April 2015
Defect Liability Period
365 days
2nd Milestone
Km. 0+000 – Km. 08+000 - 22nd February 2014 (original)
26th September 2014 (revised)
Km. 0+000 – Km. 14+000 - 22nd October 2014
3rd Milestone
Km. 0+000 – Km. 20+900 - 22nd April 2015
1st Milestone
Monthly Progress Report – July 2014 Page 20 Kerala State Transport Project - II
____________________________________________________________
3.3 Progress of Works
3.3.0.1
A summary of progress for major items is as follows.
Milestone
I
II
III
Length in km
8.000
14
20.9
Length handed over to contractor in km
8.000
-
-
Unencumbered land available to the contractor
in km
8.000
-
-
Stretch completed in all respects in km
-
-
-
FW
HW
GSB completed in km
3.30
1.24
WMM completed in km
3.30
0.58
DBM completed in km
2.30
1.41
BC completed in km
0
CD completed in Nos.
11
3.3.0.2
Work progress considering the contract price
For previous month
This month
Cumulative to end of this month
Target
Achieved
Target
Achieved
Target
Achieved
Balance
period
(months)
65.00%
7.03%
1%
1.15%
65.87%
8.18%
9
Monthly Progress Report – July 2014 Page 21 Kerala State Transport Project - II
____________________________________________________________
3.4 Physical Progress Bar Chart
3.5 Physical Progress S Curve
3.6 Payments to the Contractor
Mobilization advance and Equipment advance and IPC 3 and 4 were paid to the
Contractor amounting to Rs.180,240,109/ Monthly Progress Report – July 2014 Page 22 Kerala State Transport Project - II
____________________________________________________________
3.7 Potential Issues
•
Lack of experienced staff at site which reflected in planning of works at site, delay in
preparing Mix designs, delay in submission of working cross sections, in preparation
of survey data etc.
•
The shifting of utilities is slow. However Employer and the Contractors are
coordinating with various Service Providers like KSEB, KWA, BSNL and other
departments for utility shifting.
•
Contractor took more time for mobilization of resources which prevented them in
achieving the target as per their programme.
•
Even though buses and trucks were diverted through approved diversions as decided
in the various meeting convened by the District collector, Kannur the diversions for
movement of light local motor vehicles for isolating the work zone could not be solved
yet. One small pocket road identified, and with the consent of Railways light traffic
has been diverted for one way. Since the work area of ROB cannot be isolated by
closing the road after diverting the entire traffic through two way diversions as
mentioned above, the work of piling could not be preceded smoothly as expected and
the progress cannot be achieved as per the target. Hence the initiation for
closing project road (in the ROB Length) and commissioning another loop road is to
be urgently sorted out for the smooth progress of piling work of ROB@ Pappinisseri.
•
There is a proposal for the new additional parallel bridge at Ramapuram @KM 4+200,
the general drawing submitted by the contractor has been received and the soil
investigation work has been completed by the Contractor and investigation reports
submitted to CSC, and forwarded to the Team Leader office for taking up with the
Project Director.
•
Water utility shifting material has been directly supplied to the contractor. But the
items for shifting (Labour Rates) are not included in the contract BOQ. These items
are to be included as separate variation items for which variation proposal are to be
initiated and processed.
•
The contractor has started operation of the Crusher and Quarry with all permissions
and licenses in multiple shifts for increasing the production, however the local
residents have stopped the operation of Quarry and Crusher since 23rd June-2014
on account of their various allegations like pollution, damages to their houses due to
blasting and yet this problem could not be sorted out even though the District
Monthly Progress Report – July 2014 Page 23 Kerala State Transport Project - II
____________________________________________________________
Administration has agreed to provide all sorts of help to sort out this issue. After lots
of efforts by the contractor the Crusher and Quarry operation have been re-started
on 16th July 2014.
•
HT Line at ROB @Km. 19+950 (Pappinisseri) are to be relocated, since this Line and
Poles are fouling with pile rigs while pile boring, cage lowering and concreting works
of piles. The materials for shifting of these HT & LT lines were now received by the
contractor and shifting work commenced.
•
Poor cashflow of the contractor.
4.1 Implementation of EMP
4.2 Institutional Arrangements of Contractor
As defined in the EMP, the Contractor had established the institutional framework for
implementation of EMP as an integral part of the project team.
4.3 Staff engaged by the Contractor for EMP implementation.
Name
Dr. Rajeevan
Designation
Environmental Engineer
Sinoj.T.T.
Esob M Philip
Iajas Ahmed.N.P.
Shijinas.K.A
Christy Varghese
Safety Officer
Jr. Safety Officer
Jr. Safety Officer
Jr. Safety Officer
Jr. Safety Officer
Mobilisation Date
Rajeevan
Resigned
on
30.04.14 and Mr.Harikrishnan
joined on 02.05.14 in the role
01-01-2014
15-10-2013
10-07-2013
10-07-2013
21-10-2013
4.4 Environment Management at Project Ancillary Facilities
As part of the pre-construction activities, setting up of facilities like base camp, labour
camps, quarry, borrow area, crusher, hot mix plant, batching plant, WMM plant,
mobilisation of plants and machineries were almost completed.
Road construction
activities were also started.
Camp-1 is proposed as common facility for Package - I & II.
Table 11.2: Details of Construction Camps
Sl.No.
1
2
Camp Identity
Camp-1 for Quarry and
Crusher Plant, Hot Mix Plant,
Site lab, Workshop, labour
camp
Camp-2 for WMM Plant,
Concrete batching Plant, Field
laboratory, Site office, Staff
quarters, labour camp
Monthly Progress Report – July 2014 Location
At a distance of 20 km away from
project road on OlayambadyPonnampara Road
Village name
Odamuttu
At a distance of 4 km away from
project road
RDS Projects Ltd,
Camp Office, Ornadathchal, Near
New Kannur Bricks Company,
Vilayankode PO., Pilathara,
Kannur -670501
Vilayangode
Page 24 Kerala State Transport Project - II
____________________________________________________________
Table 11.3: Environment Management Facilities at Ancillary facilities
Sl.No.
1
Details of
Camp/Plant
Construction camp
Environment Management Facilities Provided
Provided with sanitary toilet facilities, drinking water supply,
and solid waste collection facilities.
The toilets were provided with septic tanks and overflow
disposed in soak pits.
2
Labour Camps
3
Quarry, Crusher,
Hot mix plant
Internal roads are developed partially by utilising the
construction debris obtained during the tarred surface
cutting.
Ornamental plants and banana plants were planted in the free
space Generators are provided with vertical stack of adequate
height.
Waste oil storage facilities are provided with floor and roof.
The solid waste disposal facility like compost pit is not
provided.
Two oil interceptors are provided.
Water supply and toilet facilities provided to the staff quarters
and labour camps.
The toilets with septic tanks and soak pit
Dust bins provided for collection of solid wastes. Disposal
facilities like compost pits to be provided
Cooking at labour camp is done partially at open area.
LPG connections are provided for cooking.
Ornamental plants and vegetables are planted in the free
space available
Labour camp at crusher site has to be provided with compost
pit, safety measures to electrical installations
Quarry was identified adjacent to the crusher site.
Crusher not covered fully and dust suppression system is
inadequate.
Electrical cables are to be laid in conduits
Internal roads partially tarred
Road to quarry tarred partially
The hot mix plant is installed at space available at
construction camp site-1 for package- I & II.
4
Borrow area
5
Debris Disposal
sites
Not identified
Cut earth from roadway may be sufficient
Disposal site identification pending.
Construction debris heaped along the construction site.
Identified a site for the disposal of piling muck.
6
Water Sources
Bore well
No clearance required
7
Workshop for
Heavy Vehicles
8
Water Sprinklers
Workshop established at construction camp site-2. The
oil storage area was also concreted and roofing provided.
Proper drainage facilities are yet to be provided.
Water tankers provided to sprinkle water at construction
sites and camps. Instructions were given to provide
water sprinkling facilities at the crusher and quarry.
4.5 Compliance with Statutory Clearances
The action taken by Contractor for complying with statutory requirements is
summerised below:
Monthly Progress Report – July 2014 Page 25 Kerala State Transport Project - II
____________________________________________________________
Table 11.4: Compliance with Statutory Requirements
Unit
Crusher
Hot Mix
Plant
WMM Plant
& Batching
Plant
Quarry
Status of Compliance
A common crusher is planned for Package-1 & 2
for which Consent to Establish and Consent to
Operate from Kerala State Pollution Control
Board were obtained.
Building permit obtained from Grama Panchayat.
A common Hot Mix Plant is planned for Package1 & 2 for which Consent to Establish and
Consent to Operate from Kerala State Pollution
Control Board were obtained.
Consent to Establish and Consent to Operate
from Kerala State Pollution Control Board
obtained.
Consent to Operate from Kerala State
Pollution Control Board was obtained on 2203-2014 and license to store explosives
received from the Deputy Controller of
Explosives, Ernakulam on 13-03-2014. The
License from the Grama Panchayat is yet to
be received. Obtained Consent to Operate from
Remarks
Date of Issue of Consent
to Operate-04.04.2014
and Valid Upto
31.03.2017
Date of Issue of Consent
to Operate-16.12.2013
and Valid Upto
15.12.2016
Date of Issue of Consent
to Operate-15.03.2014
and Valid Upto
19.11.2016
Date of Issue of Consent
to Operate-22.03.2014
and Valid Upto
02.10.2014
Kerala State Pollution Control Board and permit
from Mining and Geology Department
Explosive Licence from Deputy Controller of
Explosives, Ernakulam obtained
4.6 Environment Management at Work Sites
Site Visit conducted by Environmental Engineer of CSC on 19-05-2014 and reviewed the
measures taken by the Contractor for implementing the mitigation measures proposed
in the EMP. Instructions were given to avoid accumulation of debris along the project
site and to remove the debris from the site periodically. Regular sprinkling of water at
active work phase and maintenance of proper records of water sprinkling are to be
carried out by the contractor. Instruction have been issued.
As the measures adopted by the Contractor for implementing EMP is not satisfactory.
Resident Engineer has imposed of penalty that is 10% of the interim payment certificate
will be withheld from next IPC as per sub clause 14.6 of part B specific provision.
World Bank Team including the Environmental Specialist visited the project site on 20th
and 21st May 2014 and reviewed the progress of implementation of EMP. World Bank
Team instructed the contractor for making the arrangement for solid waste disposal.
They also stressed the need for adequate drinking water, toilet facilities, first aid box,
waste collection bins and proper fencing to electrical panel board with danger sign board
at all major construction sites.
Monthly Progress Report – July 2014 Page 26 Kerala State Transport Project - II
____________________________________________________________
4.7
Traffic Management and Road Safety Measures
The contractor is required to provide safety precautions such as barricading, flags,
safety signboards and traffic cones at all work zones to ensure safety for all road users.
Personal safety equipment such as jackets, safety shoes, face shields and hand gloves
are to be provided to all workers as necessary. Instructions were given to provide
adequate safety sign boards and fencing all along the active work sites.
The safety measures adopted by the contractor was not satisfactory and due to noncompliance, RE has imposed of damages as per sub clause 17-2 of part B specific
provision for various locations.
4.8
Environmental Quality Monitoring
Air Quality Monitoring Tests were conducted at Contractor’s Base Camp(Vilayankode)
and Crusher site at Odamuttu on 22.03.2014 by Enviro Design Lab(NABL accredited
Laboratory) and Water
samples were collected on 22.03.2014 from Payangadi River
@Km.7+000 and River @ Km.14+950 (Kannapuram) for testing in their laboratory and
test results were submitted by the contractor.
5.1 Contract Package III
Upgradation of Road from Thalassery to Valavupara of SH 30
Scope of Works
Construction of Major Bridges
Construction of Minor Bridge
New Box culverts
Widening Slab culverts
Reconstruction of Culverts
Drain
Footpath
Solar lights
Monthly Progress Report – July 2014 –
–
_
–
_
–
_
3
4
21
88
50
65.30 Km
44Km
Page 27 Kerala State Transport Project - II
____________________________________________________________
5.2 Contract Details
Letter of Acceptance Date
19.03.2013
Agreement Date
06.05.2013
Name of Contractor
M/s SACYR–ESSAR JV, Mumbai
Contract Price
Rs.234,99,31,763/-
Notice to Commence
29.06.2013
Total Length
54.00 Km
Contract Period
30 months
Completion Date
28th December 2015
Defect Liability Period
365 days
1st Milestone
Km. 1+200 – Km. 16+200 28th April 2014 (original)
06th August 2014 (revised)
2nd Milestone
Km. 1+200 – Km. 36+200 - 24th February 2015
3rd Milestone
Km. 1+200 – Km. 55+200 - 29th December 2015
5.3 Progress of Works
Some preparatory work activities, relocation of Electrical Utilities, water pipe line
shifting, road way excavation, pile foundation works for Major Bridges at km 2+910, km
19+750, culvert works
etc. are in progress. Contractor has not executed any other
major work on the project road. Quantum of works done is given as under:
Activities
During
the Month
Total
Remarks
54 km
Approved
29.3 km
54.00
km
29.3 km
Approved
Survey:
Traversing
Staking out of center line (Modified)
Checking and assigning values of
TBM
Recording OGLs
Establishing TBMs
Road Maintenance:
Pot hole filling
Clearance of choked earthen
drain/construction of earthen drain
Clearance of Culverts
54 km
Approved
Approved
Routine checking is in
progress.
0.5
5.0 km
-
13 Nos.
Shifting of Electric poles
22
308 Nos.
Shifting of ‘A’ poles
41
154 Nos
Stringing of HT Line
1045
7885 m
Utility Shifting:
Monthly Progress Report – July 2014 Page 28 Kerala State Transport Project - II
____________________________________________________________
Activities
During
the Month
Total
Remarks
1045
7885 m
.
Stringing of LT Line
Relocation of Transformer
Structure Works:
• Confirmatory Boring
• For A1, A2 and pier locations of
Bridge at km 02+910.
5 Nos.
-
3 No
•
A1 ,A2 and P1 & P2 location
of Bridge at km 19+758
4No.
•
Bridge at km 21+162
1No.
•
Bridge at km 29+405
2No.
•
Bridge at km 35+405
2 No.
•
Bridge at km 42+195
1No.
•
Bridge at km 53+865
Nil
•
SPT Tests for Culvert
Locations
Casting of Precast drains at
base camp
Precast drain units erected at
site.
•
•
For abutment A2 and
pier locations are yet
to start.
Yet to start
81 No.
717m
8017m
357m
2427m
Considering the overall value of work 235 crores, progress up to 31st May 2014 is given in table
below:
Up to
Month
end
of
Previous
This Month
Cumulative to end
of this Month
Target
Achieved
Target
Achieved
Target
Achieved
39.40%
2,26%
1.00%
0.32%
40.40%
2.58%
Balance period
(months)
17
Work progress is summarized in the S-curve in Annex 6.4, which compares programme
and actual progress.
A summary of progress for major items is as follows.
Milestone
I
II
III
Length in km
15
20
19
Length handed over to contractor in km
15
20
19
Unencumbered land
contractor in km
15
20
19
available
to
the
Stretch completed in all respects in km
0
GSB completed in km
0
WMM completed in km
0
Monthly Progress Report – July 2014 Page 29 Kerala State Transport Project - II
____________________________________________________________
Milestone
I
DBM completed in km
0
BC completed in km
0
CD completed in Nos.
II
III
10 (except
aprons)
5.4 Potential Issues
The following issues are very critical which may have adverse impact on the timely
completion of the Project.
• Mobilization of crusher, WMM Plant, Hot Mix Plant is yet to be completed
• Shifting of electrical and water utilities are slow though enough stock of materials
supplied to contractor.
• Identification of adequate sources for construction materials.
• Procurement of POT cum PTFE bearings
• Initial Pile load test is delayed
• Submission of revised Work Programme by contractor
• Submission of corrected cross sections by the contractor
• Procurement of applicable permits for establishing and operating HM Plant and
WMM Plant
• Poor contract management, frequent changes of key contractor personnel and
poor planning
• Poor cashflow to the work from contractor and shortage of labour force.
5.5 Nonconforming Product Notification
Details of Nonconforming Product Notification issued are listed below:
Sl.
No.
1
NCR No.
01/'Marc
h/2014
2
02/'April/
2014
3
4
03/'April/
2014
04/'April/
Details
Statu
s
TVRP/KSTP3/GEN/2 Close
Objection
from
local
People 98 dated 05th March d
regarding Batching Plant Operation 2014.
Pollution caused by muddy water,
slush from pile hole at Km.
19+758. Pit to be provided for
collecting muddy water and slush
with proper bunds to contain
muddy water and slush generated
during piling operations to avoid
spilling over to the river.
Km 19+758 bridge site - Non
procurement of drinking water and
urinal facility for workers
Borrow area at km 33+700 LHS &
Monthly Progress Report – July 2014 Letter No.
TVRP/KSTP3/GEN/4
22 dated 26th April
2014.
TVRP/KSTP3/GEN/4
31 dated 29th April
2014
TVRP/KSTP3/GEN/4
Page 30 Kerala State Transport Project - II
____________________________________________________________
2014
5
05/'May/
2014
6
06/'July/
2014
7
07/'July/
2014
km
20+300
LHSApplicable
permissions
from
competent
Authority for obtaining borrow
earth.
Earth work excavation for pipe
culvert @ km 5+645 RHS without
proper barricading, sign boards
and traffic diversion.
Filling the approach of Eranholi
Bridge (Valavupara side) at km
02+910. The filling carried out
without
raising
RFI,
without
complying
specification
requirements and without quality
testing
During inspection at Construction
of Gabion Wall following points has
been
observed
1) The size of stones are larger
than permitted maximum size of
250mm.
2) The gabion meshes are in a
damaged
and
broken
stage.
3) The cages are not filled properly.
4) The ruble used for filling is not
packed closely and not in line and
level.
5) Mud is mixed with rubble used
for filling
32 dated
2014
29th April
TVRP/KSTP3/GEN/4
63 dated 14th May
2014
TVRP/KSTP3/GEN/5
82 dated 01st July
2014
TVRP/KSTP3/GEN/6
36 dated 22nd July
2014
The CSC has been asked to remind the contractor and issue final warning.
Monthly Progress Report – July 2014 Page 31 Kerala State Transport Project - II
____________________________________________________________
5.6 Physical Progress Bar Chart
5.7 Physical Progress S Curve
5.8 Works Programme
The work programme after incorporating modifications suggested by Engineer’s
personnel has been received on 28th September 2013 and was approved the same as
base programme vide letter no. ET/1A/bd/198 dated 8th November 2013.
The contractor has submitted revision of base programme on 8th January 2014 vide
letter No. SEJV/KSTP/TVRP/SO/344. The Contractor was asked to compress the
programme within the agreed completion period along with other required modifications.
Monthly Progress Report – July 2014 Page 32 Kerala State Transport Project - II
____________________________________________________________
The Contractor resubmitted the revised base programme on 19th April 2014. On perusal
of the resubmitted revision of base programme Competent Authority informed that the
Programme is not in conformity with the Contract Conditions. The Contractor was asked
to revise base programme as per Contract Conditions. The Contractor again resubmitted
revised works programme without complying stipulations of the Contract Conditions.
The contractor has submitted revised time programme on 8th January 2014 vide letter
no. SEJV/KSTP/TVRP/SO/344. The Contractor was asked to compress the time
programme within the agreed completion period along with other required modifications
vide Resident Engineer’s letter TVRP/KSTP3/GEN/196 dated 18.01.2014 and Team
Leader’s letter ET/1A/bd/264 dated 29th January 2014. The Contractor submitted the
revised work programme on 19th April 2014 and the same is under review of CSC.
A summary of progress for major items is as follows:
5.9 Payments to the Contractor
The contractor has sofar been paid Rs. 14,76,02,131/-
5.10 Implementation of EMP
5.11 Institutional Arrangements of Contractor
As defined in the EMP, the Contractor had established the institutional framework for
implementation of EMP as an integral part of the project team. Environmental Engineer
and Safety Officers were mobilized and all are in place.
Table 12.1: Staff engaged
Name
Rajan Pillai. N
Vishnu Gopi
Shambhu Dayal Jat
Releesh Kumar
by the Contractor for EMP implementation.
Designation
Mobilisation Date
Manager – HSE
24-10-2013
Officer – HSE (HED)
04-12-2013
Officer - HSE
18-05-2013
Officer - HSE
08-10-2013
5.12 Environment Management at Project Ancillary Facilities
As part of the pre-construction activities, setting up of facilities like base camp, labour
camps, borrow area, batching plant, WMM plant, mobilisation of plants and machineries
were almost completed. Instead of establishing the quarry and crusher, the contractor
has leased out two quarries and crusher for the supply of raw materials required for the
project. The contractor was requested to report the details of these facilities to the CSC.
Piling works of bridges, construction of culverts, and construction of road side drains
were also started. The contractor has established a base camp near Chavassery where
the construction camp, labour camp, and construction plant site were established. The
details of facilities at Chavassery camp site are shown below:.
Monthly Progress Report – July 2014 Page 33 Kerala State Transport Project - II
____________________________________________________________
Table 12.2: Details of Construction Camps
Sl.
No
1
Camp Identity
Location
Base Camp for Precast yard, Field
laboratory, heavy vehicle workshop,
batching plant etc
7.4 acres of land
about 2 Km from
Project Road
Nearest village
with distance
from camp
Chavassery
Tabe 12.3: Environment Management Facilities at Ancillary facilities
Sl.No.
Details of
Environment Management Facilities Provided
Camp/Plant
1
Construction
Provided with sanitary toilet facilities, drinking water
camp
supply, and solid waste collection facilities.
Solid wastes disposal facility like compost pit is lacking.
The internal roads in the construction camps were not
tarred or concreted.
Fencing the boundaries and restricted entry into the
camp site are partially provided.
One generator is provided with adequate stack height.
Oil interceptors not provided
2
Labour Camps
Water supply and toilet facilities with septic tanks and
soak pits. Dust bins are provided for collection of solid
wastes
Solid waste disposal facilities like compost pits are
lacking.
Cooking at labour is done partially using firewood.
Adequate LPG connections to be provided to avoid usage
of firewood
Not provided with roof top aerodynamic ventilation
system.
Soak pit provided for disposal of waste water from
kitchen is filled with water. The stagnation of water may
cause severe health problem.
3
Quarry, Crusher, Proposed to take on lease. Details not provided
Hot mix plant
4
Borrow area
Identified two borrow area for embankment and subgrade works Final approval of these borrow areas are
pending due to non-submission of clearances from
revenue authorities.
5
Debris Disposal
Not identified
sites
6
Water Sources
Kerala Water Authority
Bore well, No clearance required
5.13 Compliance with Statutory Clearances
The action taken by Contractor for complying with statutory requirements is
summerised below:
Table 12.4: Compliance with Statutory Requirements
Unit
Status of Compliance
Remarks
Crusher and
Three existing quarry and
Documents to show the details of
quarry
crusher were identified for the
the quarry and crushers, the
supply of materials required for
agreement with them, the valid
the project.
Consent to Operate obtained by
Monthly Progress Report – July 2014 Page 34 Kerala State Transport Project - II
____________________________________________________________
Hot Mix Plant
Base camp
and batching
plant
Not identified the location of Hot
Mix Plant. Yet to apply for
Consent to Establish
Obtained Consent to Establish
and Consent to Operate from
Kerala State Pollution Control
Board
them etc were not furnished.
Instructed to identify the site, apply
and obtain Consent to Establish
urgently
Date of Issue of Consent to Operate09.04.2014 and Valid Upto
31.03.2016
5.14 Environment Management at Work Sites
The Environmental Engineer of CSC visited the project site on 16-05-2014 and reviewed
the measures taken by the Contractor for implementing the mitigation measures
proposed in the EMP. Instructions were given to avoid accumulation of debris along the
project site and to remove the debris from the site periodically. Regular sprinkling of
water at active work phase and maintenance of proper records of water sprinkling are to
be carried out.
As the measures adopted by the Contractor for implementing EMP is not satisfactory,
Environmental Engineer recommended for imposing penalty as per contract agreement.
Resident Engineer has imposed of penalty that is 10% of the interim payment certificate
will be withheld from next IPC as per sub clause 14.6 of part B specific provision.
5.15 Traffic Management and Road Safety Measures
The Contractor has provided safety precautions such as flags, safety signboards, traffic
cones and safety tapes at the work site.
The Contractor is also required to provide
personal safety equipment to his workers such as jackets, safety shoes, face shields, and
hand gloves as appropriate to the nature of their work. The workers at various locations
were generally using personal safety equipments. Traffic and road safety measures
adopted by the contractor at work zone are inadequate. Contractor has been instructed
comply with the Road Safety measures.
The safety measures adopted by the contractor were not satisfactory and due to noncompliance, RE has imposed of damages as per sub clause 17-2 of part B specific
provision for various locations.
5.16 Environmental Quality Monitoring
Air quality monitoring conducted at 3 locations on 23-25 January 2014 (Erinholi bridge,
Project office, Mattannur, and base camp). Water quality monitoring conducted at 2
locations on 23-25 January 2014 (Erinholi Bridge, and Meruwambai bridge). Noise
Monitoring conducted at 2 locations on 23-35 January 2014 (Erinholi bridge, Project
office, Mattannur). The monitoring report shows that impact of project activities on
environment was insignificant.
Monthly Progress Report – July 2014 Page 35 Kerala State Transport Project - II
____________________________________________________________
6.1 Contract Package IVA
Construction of Thiruvalla Bypass along Chengannoor - Ettumannoor
Road (SH-1) from chainage 7+390 to 9+400
6.2 Contract Details
Letter of Acceptance Date
29.10.2013
Agreement Date
29.11.2013
Name of Contractor
Contract Price
Notice to Commence
Total Length
M/s EKK & Co, Kochi
Rs. 31,80,45,071/19.12.2013
2.3 Km
Contract Period
24 months
Completion Date
18th December 2015
Defect Liability Period
365 days
6.3 Progress of Works
Bidding was done as per NCB norms. Work awarded to the Contractor and Kickoff
meeting was held on 30.12.2013. Contractor is in the process of identifying locations for
camp and other operations. The contractor has completed survey works, completed
confirmatory spring of PVD area and other locations, completed mix designs. The work
has been stopped due to a case in the National Green Tribunal. The case is posted for
11.08.2014. However the preparatory works and mobilization activities are progressing
as per schedule.
6.4 Mobilization of Resources
6.5 Plant and Machinery
Contractor has not established any equipment like Batching Plant, WMM Plant, HM
Plant and Crusher. They had mobilized at site very few equipment like one JCB, One
Dumper, One Water Tanker, One Low bed trailer, One Generator Set and Two Nos. of
Piling Rig. Contractor has established their site office at Thiruvalla near KM 7 on the
Project Road.
6.6 Materials
Approval for procuring Cement from three sources, Admixture from one, Geo synthetics
from one, Hume pipes from One, Pre stressing strand from one, PTFE bearing from one,
Steel liner from one and Reinforcement Steel from three sources has been issued. Source
approvals submitted for Aggregates will be cleared after receipt of relevant test results.
Monthly Progress Report – July 2014 Page 36 Kerala State Transport Project - II
____________________________________________________________
The Contractor has taken action for source approvals of Water from a well located in
Thiruvalla on the project road which will be cleared after receipt of test results.
6.7 Work Progress
Date of Commencement of project is 19th December 2013. All Survey works and
confirmatory boring required have been completed. Supply of Vehicles for engineer has
been done and are being maintained.
6.8 Implementation of EMP – Contract Package IVA
6.9 General
Environmental impact assessment (EIA) was carried out for the entire project to define
the environmental management requirements to ensure environmental safe guards
during pre-construction, construction and operation phases and presented in Sectorial
Environmental Assessment (SEA). In addition, project/link specific issues were studied
in detail during the environmental impact assessment of each packages and presented
in the Environmental Impact Assessment Reports. The Environment Management Plan
(EMP) prepared for Package IVA describes the environmental issues anticipated during
the execution of the project and suggests mitigation measures to be carried out during
the implementation to minimize the impact on the environment. The EMP has been
made an integral part of the construction contract and is being implemented along with
the execution of the project. The progress of implementation of EMP during the
execution of Package IVA as of 30th April 2014 is summarized below.
6.10 Institutional Arrangements of Contractor
As defined in the EMP, the Contractor is in the process of establishing the institutional
framework for implementation of EMP as an integral part of the project team.
Environmental Engineer and Safety Officers are being mobilized.
6.11 Environment Management at Project Ancillary Facilities
As
part
of
the
pre-construction
activities,
setting
up
of
facilities
like
base
camp, labour camps, borrow area, batching plant, WMM plant, mobilization of plants
and machineries are in progress. In the meantime, a public Interest litigation came up
before
the
National
Green
Court
and
the
Hon’ble
Green
Court
had
issued
orders to maintain status quo. Hence the work is at a standstill now.
6.12 Payment
Mobilization advance has been paid to the contractor Rs. 159,02,000/-
Monthly Progress Report – July 2014 Page 37 Kerala State Transport Project - II
____________________________________________________________
7.1 Contract Package IV
7.2 Upgradation of Road from Chengannoor to Ettumannoor of SH-1
The Bid of M/s Delma-Sreedhanya JV was
approved by the Steering Committee at Rs.
293,58,17,987. The no objection of the World
Bank is awaited for executing agreement and
commencement of work.
7.3 Scope of Works (45.40 Km)
Construction of Major Bridges –
Construction of Minor Bridge
–
New Box culverts
Widening Slab culverts
–
Reconstruction of Culverts
Foot path, Solar lights
8.1
3
5
9
8
59
Contract Package V
Upgradation of Road from Ettumannoor to Muvattupuzha of SH 1
Bids were invited on 06.04.2013 as per World Bank
guidelines. Bid evaluation was done and qualified
bidder was selected based on the combined
evaluation
criteria.
Accordingly
Contractor
M/s NAPC Ltd, Chennai was selected at bid price of
Rs. 171.50 Crores. Letter of Acceptance was issued
to them and Contract Agreement executed on
30.12.2013.
Construction of Major Bridges
Construction of Minor Bridge
New Box culverts
Widening Slab culverts
Reconstruction of Culverts
Foot path, Solar Lights
–
–
–
-
0
4
3
14
75
8.2 Pre-Construction Activities
•
Land hand over
Land handed over to the Contractor.
The KSTP has handed over land to the Contractor and accordingly
acknowledgement of the contractor also received, but some hindrances like
cutting of trees and shifting of utility remain in the work front. Which are being
removed.
Monthly Progress Report – July 2014 Page 38 Kerala State Transport Project - II
____________________________________________________________
8.3 Contract Details
Letter of Acceptance Date
29.11.2013
Agreement Date
30.12.2013
Name of Contractor
M/s NAPC Ltd.,
Contract Price
Rs. 171.49
Notice to Commence
04.02.2014
Total Length
40.60 km
Contract Period
30 months
Completion Date
03.08.2016
Defect Liability Period
365 days
1st Milestone
10 km – BC level 02.05.2015
2nd Milestone
30 km – 30 km BC level 03.02.2006
3rd Milestone
40.960 km whole works by 03.08.2016
8.4 Progress achieved is 0.52% against the target of 5.45%.
No major construction activities commenced. Preparatory works in progress. 16.6% of
the completion period has elapsed.
Quarry & Crusher, Hot Mix Plant : Consent
for
installation
has
been
obtained.
Development of site is under progress. Components
of Crusher and HMP have arrived at site. Installation
not commenced.
WMM Plant
: Erection has been completed. Calibration and
Commissioning not done.
Concrete Batching Plant
:
Erected. ‘Consent to Operate’ from Panchayat is
pending.
Initial Survey
: Traversing and Topo completed. TBM established for
30 Km. Centerline marking and OGL recording
completed for 26 Km. Revised Vertical Profile finalized
for 10 Km. Horizontal alignments up to km 30.00.
Balance will be finalized after receipt of modified
TOPO drawings.
Monthly Progress Report – July 2014 Page 39 Kerala State Transport Project - II
____________________________________________________________
Field laboratory
: Established at their office building. Contractor has to
establish laboratory at base camp.
9 Contractor has done cleaning of 10 Nos. of existing culverts in the Milestone-1.
9 Source approval has been issued for use of coarse Aggregates from 2 sources and
fine Aggregates from one source. Alignment soils for 5 Km have been collected and
lab tests are progressing. Mix designs for concrete grade PCC M15, PCC M 20,
RCC M25 and RCC M30 have been approved. Job mix for GSB is under progress.
9 Work on relocation of electrical utilities has commenced.
Construction Programme submitted on 19.04.2014 has been approved.
In view of the impending Monsoon, the contractor has been instructed to maintain traffic
worthy road during monsoon and steps shall be initiated to provide enough safety
measures.
8.5 Pre-Construction Activities
8.5.0.1
Land hand over
All land has been handed over to the Contractor and accordingly acknowledgement of
the contractor also received,
8.5.0.2
Utilities
Utilities such as water lines, telephone cables and associated accessories, electrical lines
and associated accessories and trees are being removed / shifted. Contractor has
submitted item rates required for relocation of KWA water lines from the project road.
KSTP/PMT has made arrangements with BSNL and other private agencies for relocation
of cables, telephone posts and telephone pillars. KSTP has issued some of the items
required for relocation of electric utilities and relocation work has commenced.
8.6
Mobilization of Resources
8.6.0.1
Plant and machinery
Contractor has established a new concrete Batching Plant and is planning to obtain
consent for its operation from KSPCB and local bodies concerned. Erection of the WMM
Plant is under progress. Area development for establishing crusher is going on although
the Crusher unit has not been mobilized. Apart from this, 2 nos of Weigh bridges have
been erected and commissioned.. Contractor has mobilized the components of Crusher
and HMP. Installation has not commenced. They have mobilized at site very few
Monthly Progress Report – July 2014 Page 40 Kerala State Transport Project - II
____________________________________________________________
equipments mentioned in Annexure 8.3. Considering their poor progress of mobilization,
they have been notified to expedite this activity.
They have taken on lease 7.24 acre of Land near km 31 of project road for the Base
Camp where they propose to establish the above equipments other than Crusher,
Workshop and Field Lab and Labour Camp etc. For establishing the Crusher, they have
arranged another piece of Land near km 33 and they have obtained consent of KSPCB to
establish same. Their application submitted for EMP approval on the specified format
duly supported with site plan, Lease agreement and Consent of KSPCB has been
approved by the CSC. Labour Camp established by the contractor at Km.3+300 (LHS)
has not been approved as it does not satisfy some of the mandatory EMP criteria
specified in the Contract Document.
8.6.0.2
Human Resources
The contractor has obtained Labour registration certificate and deployed adequate
number of labourers for progressing their mobilization and preparatory works. They are
yet to moblize adequate resources for commencement of civil works as scheduled in the
approved programme.
8.6.0.3
Materials
Approval for procuring Cement from 4 sources, Reinforcement Steel from 5
sources,
Admixture from 4 sources, Gabion from 2 sources and Coarse and Fine Aggregate from
one source each and Water from one source has been issued. Procurement of material
not started.
8.7 Work Progress
Date of Commencement of project is 4th February 2014. No major construction activity
initiated except the cleaning of 10 culverts as per the BOQ and construction of one box
culvert and one slab culvert.
Contractor has completed the Traversing and Topo survey for the complete stretch, and
established TBM for 30Kms. Some revision in the horizontal alignment was necessitated
and this was one. Recording of OGLs has been completed for 26 km.
Contractor has pre-cast 627 Nos of RCC drain unites of 1.5m each (941 m) other civil
works are yet to be taken up.
8.8 Work Programme
As per clause 8.3 of GC, Contractor has to submit a detailed time programme to the
Engineer within 28 days after receiving the notice under clause 8.1 of Contract
Monthly Progress Report – July 2014 Page 41 Kerala State Transport Project - II
____________________________________________________________
Conditions. Since the Programme submitted on 23.02.2014 was not in accordance with
the Contract, advised to resubmit the Programme. Detailed Construction Programme as
per Contract provisions was submitted on 19.04.2014 and approved on 08.05.2014.
8.9 Design changes
•
As per DPR, design of pavement was made based on the criteria of 15 years design
life. Later it was discussed to consider 10 years design life for pavement design as per
suggestion in the value Engineering exercise and accordingly Chief Engineer
(Projects) intimated that the pavement thickness of DBM modified to 75 mm instead
of the proposed 90mm considered in the drawing. This is in accordance with the
value Engineering done.
•
In view of the varying land width, will be located near the edge of ROW. Accordingly,
paved shoulder also will be extended up to drain in town portions. Earthen shoulder
to be constructed Upto drain in other reaches.
8.10 Quality Control
The status of material and job mixes and mix designs is shown in Annexure 8.12.
8.10.0.1
Source and Material Approvals
Approval has been given for Steel and Cement, Admixture and Gabion to be used in the
permanent works based on manufacturer’s satisfactory test results. The contractor has
established a Field Laboratory in their office premises near km 22 (RHS) of Project Road
and is functional for performing tests on Aggregates, Soil, Admixture, GSB and Concrete
works.
Contractor has obtained approval of 2 sources of aggregate for use in concrete mixes.
Alignment soils for 5 Km have been collected and lab tests are progressing. Mix designs
for concrete grade PCC M15, PCC M20, RCC M25 and M30 have been approved. Job mix
for GSB is under progress.
The Contractor is yet to identify Borrow source for soil as they do not anticipate use of
outside soil due to availability of Road Way excavated soil.
8.11 Mix Designs
Mix designs for concrete grades PCC M15, PCC M20, M25 and M30 have been approved.
Monthly Progress Report – July 2014 Page 42 Kerala State Transport Project - II
____________________________________________________________
8.12 Important/Key/Potential Issues
The following issues are very critical which may have adverse impact on the timely
completion of the Project.
•
Delay in obtaining consent for operation of Batching Plant and inordinate delay in
installation of Crusher and Hot Mix Plant. The WMM plant though installed, its
commissioning and obtaining consent for operation are pending.
•
Shifting of Electrical and Water utilities.
•
Delay in Identification and procurement of adequate construction materials.
9.1 Contract Package VI
10.1.1.1
Upgradation of Road
from Ponkunnam to Thodupuzha
Bids were invited World Bank guidelines (ICB).
Bid evaluaiton was done and qualified bidder
was selected. Accordingly Contractor M/s GHVEKK (JV), Cochin was selected at bid prince of
Rs.227,13,73,548.
Letter of Acceptance was
issued
and
to
them
contract
executed on 05.05.2014.
agreement
the works are in
progress now.
10.1.1.2 Structures
10.1.1.3 Bridges
Minor Bridges
a.
Reconstruction
-
2 nos.
b.
Widening
-
1 no.
c.
Repair & retain
-
2 nos.
Reconstruction
a. Pipe
-
31
b. Box
-
78
10.1.1.4 Culverts
Retained & widened
Monthly Progress Report – July 2014 Page 43 Kerala State Transport Project - II
____________________________________________________________
a. Box
-
38
-
6
Retained
a. Box
New Construction on Realignment
a. Pipe
-
1
b. Box
-
4
-
2
-
160 nos.
New Construction
a. Box
Total
10.1.1.5 Contractors
Name of Contractor: M/s GHV-EKK(JV)
Address:
2nd Floor, Municipal Building, A.M. Road, Perumbavoor, Eranakulam
District, Kerala State.
Mob: +919048306889, Fax/Tel: +91484 2523603
Letter of Acceptance date
04.02.2014
Agreement date
05.05.2014
Name of Contractor
M/s GHV-EKK (JV)
Contract price
Rs. 227,13,73,548
Notice to Commence
10.06.2014
Total Length
46.363 km
Contract Period
30 months
Completion date
09.12.2016
Defect Liability Period
365 days
1st Milestone
10 km
2nd Milestone
25 km
3rd Milestone
Completion of full stretch & Thodupuzha
Bypass
10.2 Description of work
The
work
involves
improvement
of
State
Highways
including
geometric
improvements and realignments to standard 2-lane of 7 m carriage way,1.5 m paved
shoulders, and 1.00 m slow lanes or soft shoulders and generally wider construction
in built –up areas including median separated dual carriageways . The construction
Works include, but are not limited to:
-
Scarification, clearance, earthworks,
Monthly Progress Report – July 2014 Page 44 Kerala State Transport Project - II
____________________________________________________________
-
New culverts, new bridges and rehabilitation of existing/culverts and protective
works
-
Granular Sub-Base, Wet Mix Macadam base course, Bituminous Mix Surfacing
and Stone Matrix.
- Side drains, sidewalks,
- Road markings, road furniture and other road safety appurtenances,
- Routine maintenance and maintenance during Defects Notification period.
-
Traffic management and environmental protection measures during construction
stage.
- Construction and maintenance of diversion roads, whenever needed.
- Environmental and Social enhancement works/landscaping etc.,
10.3 Construction Supervision Services – Package VI
The
construction
Supervision
Consultancy
agreement
(No.KSTP/PMT/PWD/240/2014dated 14/05/2014was signed on 14th May2014).The
effective date of the services was established on 14th May2014.
The objectives of the consultancy services are:
9 To ensure high quality construction with full compliance to Engineering Designs
and
Drawings, Technical Specifications and other Contract Documents within the
specified
Time schedule
9 To monitor the Pre –construction activities
9 To assist in taking remedial actions to avoid slippages, cost overruns, delays by
the contractor and contract disputes
9 To ensure safety during construction and adherence to all Environment
Management Regulations prescribed under the contract.
9 To ensure that effective Contract Administration is achieved.
10.4 Consultant – Details
The selected contractor for this package is M/s MSV International Inc., USA
Agreement Details:
a.
b.
c.
d.
Contract Signed
Contract Period
Commencement date
Contract Amount
Monthly Progress Report – July 2014 ::
::
::
::
14.05.2014
30 months
14.05.2014
Rs.4,41,88200.00
Page 45 Kerala State Transport Project - II
____________________________________________________________
10.5 Mobilization Status of works
10.5.1.1 Main Camp
The establishment for Main Camp has identified at Kurinji (Km 123+000). In this camp
planning to establish Hot Mix Plant (HMP), Wet Mix Macadam Plant (WMM), Crushing
Plant, Main laboratory, Main office, Labour camp and Staff camp.
10.5.1.2 Sub Camp
The Sub camp will be established at Paika (Km 97+000) and Bharananganam. Land
lease procedure has been done for both the Camps (i.e. for Main as well as for Sub
Camp).
10.5.1.3 Survey Works
Topographic survey has been completed from Ponnkunnam to Thodupuzha. Bench
marks Shifting has been completed for full alignment. Centre line marking is complete
up to a distance of 12.50 Km from the beginning coordinates have been fixed with the
help of GPS along the full alignment of the road. Verification of crust thickness survey
has been completed along the total alignment.
10.5.1.4 OGL Soil Samples Survey
Collection of the OGL Soil Samples from Ponnkunnam to Thodupuzha Road and
Thodupuzha Bypass Road is completed.
10.5.1.5 Box Culvert
Designs for precast Box Culvert are being finalized.
10.5.1.6 Temporary Lab
Existing laboratory and Batching Plant at Kidangoor will be used in the initial stage of
the project, till the laboratory is setup at the main camp both are functional.
10.5.1.7 Equipment Mobilization
In main camp the HMP, WMM, Crushing Plant, Concrete Batching plant, etc shall be
mobilized. Gantry (20 MT) and Batching plant of capacity 20 cum/hour and WMM plant
shall be mobilized at sub camp in the month of August. In initial stage, the existing
Concrete Batching Plant of Kidangoor Batching plant shall be used, which is established
for other works and is very near.
Monthly Progress Report – July 2014 Page 46 Kerala State Transport Project - II
____________________________________________________________
10.5.1.8 Manpower Mobilization
•
Overall 52 persons have been mobilized so far and further mobilization is in
progress
•
Work program has been submitted for scrutiny and approval to Engineer.
10.5.1.9 Facilities for Engineer
•
Office for the Engineer has been setup in leased accommodation at Pala and
furnished.
•
Four vehicles have been procured and supplied for Engineers use.
•
Fifth vehicle has been transferred to KSTRI (PWD) as per instruction of Project
Director.
10.6 Quality Control
The Status of OGL Material and mix designs are given below.
10.6.1.1 Source and Material Approvals
Approval has been given for Steel, Admixture, Cement, Gabion and Geotextile to be
used for the works based on manufacturer’s satisfactory test results. Approval for
procuring Cement (Coromandel, Ultratech) from two sources, admixture (BASF, Fosroc)
from two sources, Gabion (Maccaferri) and Geotextile (Maccaferri) from one source,
Hume
pipes
(Premier
spun
pipe)
from
one
source,
Reinforced
Steel
(SAIL,SYAM,JSW),from three sources, source approval submitted for Fine aggregates
and coarse aggregates,(Cochin blue metals) from one source have been approved
10.6.1.2 Mix Designs
M15 (P.C.C), M20 (R.C.C), M25 (R.C.C) and M30 (R.C.C) Trial Mix are being in
progress for using Coromandel cement.
11.1 Contract Package VII
Upgradation of Road from Punalur to Ponkunnam under PPP Annuity mode Selection of Transaction Advisory
Work has to be arranged under PPP mode (Hybrid Annuity). DPR submitted by
M/s CDM Smith Associates is under review. The procurement process for selection of
Transaction Advisory has been initiated. Out of the six firms shortlisted, five firms have
submitted their Technical and financial proposals. The technical proposals are under
evaluation. The firms are
1. M/s Ernst & Young
2. M/s Darashaw & Co.,
3. M/s Crisil Ltd.,
Monthly Progress Report – July 2014 Page 47 Kerala State Transport Project - II
____________________________________________________________
4. M/s L&T Ramboll
5. M/s Deloitte Touche Tohmatsu India Ltd.,
13.0 Contract Package VIII
13.0.0.1 Upgradation of Road from Perumbilavu – Pattambi Perintalmanna
As per the original program, work has to be arranged under EPC mode. Alignment Plan
completed and the DPR preparation by M/s CDM Smith Associates is nearing
completion. Marking on boundary pillars is in progress and action is taken to publish
4(1) notification. Since delay is expected on land acquisition as per the new LA Act, for
which rules are yet to be framed, it has been decided to carryout improvement to this
road with in the available RoW so as to complete the works during the project period of
KSTP. Estimate is under preparation through KHRI. The works can be arranged after
the approval of restructuring proposal submitted to the Bank
13.1 New work
As the surface of the KSTP I roads which were completed about 6 to 8 years back are
likely to deteriorate after the rainy season, it has been planned to provide an overlay
renewal course in these road sections from the savings anticipated from the reduction of
scope of works for Package VIII (Perimbilavu – Perintalmanna road). Proposal has been
endorsed by the Steering Committee and World Bank has also agreed in principle to this
proposal. KHRI has been entrusted to prepare DPR for these works and will be put to
tender after obtaining approval to the restructuring proposal from DEA and Bank. The
road sections included are about 150 km and are as under
1.
Adoor
-
Chengannur (20.00 km)
2.
Muvattupuzha
-
Thodupuzha (17.83 km)
3.
Muvattupuzha
-
Angamaly (31.40 km)
4.
Thrissur
-
Kuttippuram (33.08 km)
5.
Palakkad
Shornur (45.30 km)
The road stretch from Kazhakkuttom – Venjaramoodu – Adoor (80 km) has been
proposed under SCDP and hence excluded and so also the Alapuzha – Changanassery
road which was renewed about two years back.
13.2 Road Safety
Baseline Road Safety Survey for Safe
1. Corridor Demonstration Project –
Kazhakkoottam – Adoor
Monthly Progress Report – July 2014 :: Study completed
Page 48 Kerala State Transport Project - II
____________________________________________________________
2
Road Safety Capacity Building and
program management
The evaluation (final) has been
approved by the Steering Committee
:: and negotiation with the consultant
fixed on 23.07.2014. The draft
agreement is being prepared
13.3 Institutional Strengthening Components – Current Status
1.
Road User Perception Survey
2.
Prioritization and DPR preparation for
1000 km
3.
::
Completed, report submitted
::
Work completed.
Draft DPR presented and
comments given. Requested
permission of State Government for
posing the Project for World Bank
financing.
::
Work completed and Report
forwarded to Chief Engineer (R&B)
for preparing DPRs of individual
road packages with PWD funds.
SOS for 8750 km MDR
4.
Development of Multi Model (Hub)
5.
Hiring of consultants for Strategic Core
Road Network Program
::
ToRs received from Bank and EoI
being invited short listing.
6.
Developing Integrated Information
Management System
::
EoI invited with last date as 11
August 2014.
7.
Construction of Head Quarters Building
under Green Building concept
::
Architectural and Structural
Design completed under KSTP II
and proposal submitted to
Government for Administrative
Sanction for the construction
through PWD Building Wing.
8.
9.
10.
::
Final report submitted
Community engagement in road
management and Road User Behavior and
Accidents.
::
ToR for implementing the program
is progress
Review and updating information systems
in PWD and developing Integrated
Management Information System for PWD
::
Review of existing IT systems in
PWD completed.
Purchase of Project Management Software
for KSTP
::
Financial offers received from
Bangalore based firms and orders
being placed.
14.0 Meetings, Site visits & Inspection
14.1 Package – I
Project Director (KSTP) visited the site on 18th July’2014, along with, Team Leader.
Monthly Progress Report – July 2014 Page 49 Kerala State Transport Project - II
____________________________________________________________
Mr.Ramana Rao Sr. Safety Specialist visited the site on 04th July 2014 and an
orientation class were conducted regarding safety measures to be followed at
construction site and crusher and Quarry sites.
Progress Review meeting held on 24th July 2014 at contractor’s site office along with
Resident Engineer, Dy. Resident Engineer, client Assistant Executive Engineer and
contractor’s engineers.
14.2 Package – II
•
Mr. Ramanarao Sr. Safety Specialist visited the Site on 03rd July 2014 and an
orientation class were conducted regarding safety measures to be followed at
construction site and crusher and Quarry sites
•
Mr. Shibu Joseph Sr. Structural Engineer of CSC visited the Site on 07th July
2014 along with SE of KSTP and Railway officials to check the railway Gate
shifting location for construction of diversion for execution of ROB @Km 7+420.
•
Progress Review meeting was convened at Trivandrum on 09th July-2014 by the
Hon’ble Minister of Works. Principal Secretary PWD, KSTP Officials, Consultants,
and Contractor’s representatives attended the meeting.
•
Progress Review meeting was convened at Trivandrum on 17th July-2014 by PD
KSTP. KSTP Officials, Consultants, and Contractor’s representatives attended the
Meeting.
•
Utility Shifting meeting convened at KSTP Div. Kannur on 16th July 2014.
•
PD, SE of KSTP & TL of CSC visited the Site on 19th July 2014.
•
Dispute Board members Site visit and meeting convened at RDS Base camp on
19th July 2014.
•
Progress Review Meeting convened at RDS Base camp on 24th July 2014 RE with
CSC Staff’s and Contractor’s representative attended.
14.3 Package – III
•
During this Month Honorable Minister for PWD reviewed the progress of the works on
30th July 2014 at Thiruvananthapuram.
•
Progress review meeting at KSTP level has been conducted on 07th July 2014 at
Thiruvananthapuram.
Monthly Progress Report – July 2014 Page 50 Kerala State Transport Project - II
____________________________________________________________
•
Executive Engineer, KSTP convened a meeting at Mattannur on 01st July 2014 with
Service providers, consultant and Contractor.
•
Project level Monthly Progress review meetings held on 25th July 2014 at RE office,
Mattannur.
14.4 Package – V
Progress Review Meeting Conducted at KSTP, Thiruvananthapuram on 17th July 2014.
Progress Review Meeting Conducted at Thiruvananthapuram by the Hon’ble Minister of
PWD on 30th July 2014 along with the Principle Secretary to the PWD, KSTP officials
with all the Contractors and Supervision Consultant.
Environmental Engineer of CSC visited the site on 15 July 2014 and reviewed the
Implementation of EMP.
14.5 Package VI
Progress of the Project was reviewed by the Honorable Minister of PWD on 30thJuly
2014.
14.6 Land Acquisition Status
Sl
No.
1
2
3
4
5
6
Name of Road
Kasargod –
Kanhangad
Pilathara –
Pappinisery
Thalassery –
Valavupara
Chengannoor Ettumannoor
EttumannoorMuvattupuzha
Ponkunnam Thodupuzha
Total
Requirement
(Ha)
Extent of
pending
acquisition
Percentage
of pending
acquisition
LA
Stage
Date of
taking
Possession
2.983
0
0
-
-
6.234
0
0
-
-
25.32
1.032
4.08
Award
Stage
30.03.2014
15.368
0.246
1.6
DLPC
31.03.2014
17.866
0.07
0.39
DLPC
31.03.2014
35.733
0
0
-
-
7
Perumbilavu –
Perinthalmanna
13.5
13.5
100
8
Punalur –
Ponkunnam
17.705
0.026
0.14
Monthly Progress Report – July 2014 LAO
appointe
d
4(1)
stage
31.12.2014
31.06.2014
Page 51 Kerala State Transport Project - II
____________________________________________________________
14.7 Payment to consultant M/s Egis India JV with M.s Egis
International
KERALA STATE TRANSPORT PROJECT
Report Date
Construction Supervision Phase II
31-Jul-14
Annex 2.3 List of Egis's Invoices and Payments
Invoices
No.
Invoice
No.
Period
Submission
Gross
Amount
Net
Receivable
LC
(Rupees)
LC
(Rupees)
1
Advance
April'13
18,360,460
18,360,460
2
1A
April &
May'13
822,250
776,297
Received
Gross
Amount
Net
Received
LC (Rupees)
LC
(Rupees)
Date
12-Apr13
19-Sep13
Remarks
Date
16,524,414
20/4/13
Mobilization
Advance credited
822,250
591,759
25/10/13
Repayment of
Mobilization
Advance
3
1B
2,011,982
878,208
1,534,899
-1,126,528
25/10/13
4
2A
632,500
104,082
534,667
25/10/13
5
2B
845,829
26,930
19-Sep13
632,500
845,829
-479,601
25/10/13
6
3A
613,525
541,773
613,525
514,200
25/10/13
7
3B
1,916,459
770,878
19-Sep13
1,916,459
663,211
25/10/13
8
4A
594,550
520,453
594,550
469,433
25/10/13
2,955,659
1,938,523
2,955,659
1,772,474
25/10/13
632,500
710,677
632,500
492,026
07/12/13
3,173,829
2,036,076
3,173,829
2,005,353
07/12/13
632,500
710,677
632,500
492,026
07/12/13
3,474,117
2,373,480
3,457,417
2,308,061
07/12/13
588,225
660,930
588,225
447,254
04/02/14
3,569,341
2,497,173
3,562,913
2,442,688
04/02/14
487,025
547,221
487,025
344,916
04/02/14
3,620,100
2,537,506
3,620,100
2,504,084
04/02/14
9
4B
10
5A
11
5B
12
6A
13
6B
14
7A
15
7B
16
8A
17
8B
18
9A
June'13
July' 13
August'13
September'13
October'13
November'13
December'13
613,525
January'14
19
9B
20
10A
4,360,671
632,500
Februaty'14
21
10B
22
11A
5,801,595
632,500
March'14
23
11B
24
12A
25
12B
4985536
April'14
569,250
689,357
19-Sep13
11-Oct13
7-Nov-13
12-Dec13
9-Jan-14
10-Feb14
3,369,612
710,667
11-Mar14
4,988,634
710,667
5,028,442
Monthly Progress Report – July 2014 4,360,671
632,500
5,771,415
632,500
4-Apr-14
4071710
639,609
613,525
4,918,436
12-May14
569,250
4,998,392
480,421
3,166,242
514,602
4,663,411
12/03/14
12/03/14
25/03/14
25/03/14
514,602
Repayment of
Adv. completed
3,790,298
582,684
11/06/14
11/06/14
Page 52 Kerala State Transport Project - II
____________________________________________________________
5,649,957
26
13A
632,500
May'14
27
13B
28
14A
5,096,634
632,500
June'14
29
14B
5,085,977
880,930
5,116,354
632,500
6-Jun-14
5,020,834
6,967,006
800,284
647,427
5,139,326
-
-
-
-
11/07/14
11/07/14
5-Jul-14
6,393,732
Annex 243 List of MSV Invoices and Payments
Invoice-1:
14.8
Received for ` 336667 and being paid
Key action taken on Critical Issues pointed out during World Bank
Mission in Aide Memoire
Component A – Road Network upgrading and Safety Improvement:
Action
Target
date
Action taken
The extension of time of completion for
first milestone has been recommended
up to 6th August 2014 as the contractor
has expressed willingness to speed up
the progress.
The contractor started
piling and other works. Road work could
not be started due to rain. The work is
slow.
Procurement of materials and
utility shifting are in progress.
The
performance is being watched to take
stringent actions.
1.
Complete mobilization and initiate
road works in contract 3, failing
which face stringent contractual
action
2.
Complete mobilization in contract 5
Sept 30
2014
This is progressing
3.
Achieve at least 5 km of completed
road works in contracts 1 & 2
Sept 30
2014
The review meeting in the presence of
the Hon’ble Minister PWD has been
conducted and contractor has been
instructed accordingly
4.
Take a final decision on the approach
for remaining land acquisition
Sept 30
2014
The Government order for direct
purchase of land has been obtained and
action is being taken
June
15
2014
5.
Take a final decision on scope of
contract 8
-
The Steering Committee has approved
the
suggestion
to
carryout
the
improvement works of rehabilitation
nature within the available Right of Way.
The intimation regarding this was
already given to Bank.
6.
Issue RFP for Transaction Adviser for
PPP road
-
The RFP was already issued and
proposals received.
The technical
proposal is under evaluation.
7.
Improve the overall environmental
management and construction safety
following the agreed framework in
-
This is being done
Monthly Progress Report – July 2014 Page 53 Kerala State Transport Project - II
____________________________________________________________
Annexure-5
Component B – Road Safety Management
8.
Engage
Road
Consultant
Safety
Management
9.
Identify the first set of projects for the
challenge fund
-
The negotiation meeting with the selected
consultant is over and agreement being
signed.
-
This will be done after mobilization of the
Road Safety Programme Management
Consultant start the tasks.
-
Actions on this will be taken urgently after
discussion with the higher authorities.
-
Discussed with Mr. Bernard Aritua the
Deputy Task Team Leader and advised to
first select the client Executive Program
Sponsor. However Expression of Interest
for the work Package-II is being invited
which will be followed by Package III & IV.
Component C- Institutional Strengthening
10.
Initiate the process of appointing a
Client Executive Program Sponsor
11.
Issue RFP for the Sector
Option Study Work packages
Strategic
12.
Finalize the ToR for the integrated
Omni-Channel IT and Communication
System
for
improved
public
communication and user engagement
-
The ToR for Integrated
Management System has been
the Bank and Expression
applications invited fixing last
August 2014.
13.
Issue RFP for direct
engagement in road safety
-
The ToR for this is being prepared in
consultation with the Bank.
-
Actions to procure this software from the
supplier taken on sole source basis. The
Bank had expressed no objection for this.
stakeholder
Information
approved by
of Interest
date as 11th
General Issue
14.
Install a suitable Project Management
System for improving overall project
management
FM Actions Agreed
SL
NO
ACTION
DUE DATE
Withdrawal Claim for period
ended 15th June 2014
18/06/2014
2
Withdrawal Claim for period
ended 30th June 2014
15/07/2014
3
Internal Audit report FY 201314
15/06/2014
1
Monthly Progress Report – July 2014 KSTP REMARKS
Claim submitted and disbursement
received.
Audit Completed. Report dated
02.08.2014 received on
11.08.2014.
Page 54 Kerala State Transport Project - II
____________________________________________________________
4
Finalised Accounts to CAG
30/06/2014
Will submit to CAG on receiving
approval from Steering Committee
5
Submit CAG Audit Report
30/09/2014
Can be done.
6
Appoint Internal Auditors for FY
14-15
31/07/2014
As per the agreement with the
Internal Auditors, the term of
appointment is for 3 years, (201304 to 2015-16) extendable subject
to satisfactory performance. Hence
their tem is still on. Also their
output was satisfactory.
7
Internal Audit report for 1st 6
months of FY 14-15
30/11/2014
Can be achieved.
14.9 List of Annexure:
Annex 1
Organization Chart KSTP
Annex 2
Important letters to contractor and minutes of review meeting
Annex 3
Procurement Plan
Annex 4
Photographs
Monthly Progress Report – July 2014 Page 55