CorrespondenceIssues/Review of Construction Programme

@
in Association with
,/
./
INFRASTRUETURE
pRrvar€
con6ull^rr8
LtirtrED
SA INFRASTRUGTURE CONSULTANTS PVT. LTD.
SUGAM TECHNOCRATS PVT. LTD.
Ergrree^
sArcpL-sTpLArH-23 I /TLIPNC/GEN/20
I
4/ I
+o
Date:19.09.2014
To,
Authorized Signatory
M/S PNC Raebareli Highways Private Limited
PNC Infratech Ltd.
Vill: Dandupur, Tahsil: Raniganj Thana
Dist: Pratap garh-230304 (Uttar Pradesh)
Kind Attention: Mr. Aviiit Banariee
i
Sub: - Independent Engineer Services for 2-Laning with Paved Shoulder of Raebareli to Jaunpur
Section of NH-231 from Km. 0.000 to Km. 166.400 in the State of Uttar Pradesh under NHDP - IVA
on BOT (Annuity) DBFOT Mode. Review of Construction Program of Concessionaire- Reg.
Ref:-Concessionaire letter no. PD-PNCRHPL/IE/CONP /201 4/065
dated 31.08.2014
lo' o$'!,614;
(Rec.t
Sir,
"
With reference to the above the work program for the Project
has been submitted by the
Concessionaire vide letter cited above for review and comments from Independent Engineer.
In this context concessionaire has submitted:
(i)
(iD
(iii)
Bar Chart,
S-Curve not in prevalent graphical presentation, and
Month wise quantity break-up.
In this context our comments are as below;
l)
The Construction Period as per C.A. is 24 months where
submitted their program for 18 months.
as "Concessionaire has
2) Month wise quantity break-up is not clear.
to the work program submitted by the Concessionaire it is observed that
concessionaire has targeted for an expense of 50.68 crs in the month of June 2014,
49.l3cr in the of July 2014 and 48.03crs in Aug 2014. The cumulative targeted
3) Pursuant
expenditure are 147.84 crs.
4) Pursuant to the monthly progress report of August 2014, the cumulative progress
achieved is given 22.01% inclusive of collection of aggregates which is 10.33%. The
expenses done in collection of aggregates shall not be considered in the progress of
the project. The expenses done in completion of the different permanent work items
of the project arc 11.68%o which appears realistic expenditure incurred on the project.
5) The work program submitted by the concessionaire establishes their capacity to
perform progress to the tune of more than 50 crs in a month.
Hence, we can say that the program submitted by the concessionaire is not realistic and has
many gaps in achievement of progress. As a consultant we request the concessionaire to
submit the realistic work program compatible with scheduk - G.
SAICPL-Sugam Office:
101-102, CS-I, Gyan IGand - II, Indirapuram, Ghaziabad: 201 014 (UP), India
Tel. No.: +91-120-2607756, Fax. No.: 9l-120-2607757, E-mail: [email protected]
Project Office:
SAICPL-Sugam, C/o Srirama Prasad Pandey House no.720, Pandey Kothi, Near Degree College Chaurah4
Kutcheri Rbad, Raebareli (UP) 229001 Ph. No. 0535-2700136 Email:[email protected],
t
fty
Engineer.
$q
sullmission of the revised work program may
k
Yours faisrfully,
for S.A.I.C.P.L-S.T.P.L (in Association)
I.E for Raebareli-Jaunpur Higfuway (NH-231)
Copy to:
2.
3.
Independent Engineer, SAICPL-SUGAM Ghaziabad.
SAICPT-Suga*1" NII-231,'Slt$ offioe, Prxapgarh.
don€ forttle review of Independent