FACILITY CONNECTION REQUIREMENTS Georgia Transmission Corporation Effective date March 3, 2014 Individual Making Edits Date Version Number 03/24/2005 1 04/13/2005 2 04/13/2007 3 04/19/2007 4 01/29/2008 5 J. W. Chiles 03/31/2009 6 S. G. Miller 05/07/2009 7 S. G. Miller 3/15/2013 8 Zakia El Omari 11/22/2013 9 Zakia El Omari Rob Wiley 02/19/2014 10 Zakia El Omari Rob Wiley Reason / Comments FCR Document reviewed and updated to align with the new SERC Supplement. Paragraph 1.18 (Abnormal frequency and Voltage Operation) updated to address GTC connection requirements, per SERC Audit Team request. FCR document reviewed and updated to align with GTC's procedure for maintenance coordination. Section 1.14, 1.15, 3.3 and 4.5 of the FCR document have been reviewed and updated to reflect GTC's current standard operating practice and procedures utilized in the protection of interconnected transmission facilities. Review based on Internal GTC Review by Electronic Maintenance, Protection & Control, Bulk System Planning, Substation Maintenance. Review based on Internal GTC Review by Electronic Maintenance, Protection & Control, Bulk System Planning, Substation Maintenance. Review based on Internal GTC Review by Electronic Maintenance, Protection & Control, Bulk System Planning, Substation Maintenance. Added section to describe compliance with R.2.1.2. Reviewed and updated sections addressing R2.1.1, R2.1.35, R2.1.7-8 and R2.1.14-16 FCR updated to reflect new FAC-001-1 requirements numbering (ex. R2.1.1 changed to R3.1.1). Grammar correction in Purpose statement. Changed document applicability to include sub-transmission system Added clarification statements based on GDS Mock Audit feedback. Updated sections: Purpose, R3.1.1, R3.1.3 to R3.1.6, R3.1.9 to R3.1.11. Added section: A5: Maintenance of FCR document. Additional review based on input from GTC managers and regulatory compliance manager TABLE OF CONTENTS A. INTRODUCTION ...........................................................................................................................................2 A.1. A.2. A.3. A.4. A.5. B. FAMILY OF COMPANIES ..................................................................................................................................2 INTEGRATED TRANSMISSION SYSTEM (ITS) ...................................................................................................2 PURPOSE .........................................................................................................................................................2 APPLICATION OF FCR DOCUMENT .................................................................................................................3 MAINTENANCE OF FCR DOCUMENT...............................................................................................................3 REQUIREMENTS ..........................................................................................................................................4 B.1. FAC-001-1, R3.1.1 PROCEDURES FOR COORDINATED JOINT STUDIES OF NEW FACILITIES AND THEIR IMPACTS ON THE INTERCONNECTED TRANSMISSION SYSTEMS ...................................................................................4 B.2. FAC-001-1, R3.1.2 PROCEDURES FOR NOTIFICATION OF NEW OR MODIFIED FACILITIES TO OTHERS (THOSE RESPONSIBLE FOR THE RELIABILITY OF THE INTERCONNECTED TRANSMISSION SYSTEMS) AS SOON AS FEASIBLE. ...... 5 B.3. FAC-001-1, R3.1.3 VOLTAGE LEVEL AND MW AND MVAR CAPACITY OR DEMAND AT POINT OF CONNECTION. .............................................................................................................................................................7 B.4. FAC-001-1, R3.1.4 BREAKER DUTY AND SURGE PROTECTION ......................................................................9 B.5. FAC-001-1, R3.1.5 SYSTEM PROTECTION AND COORDINATION ....................................................................9 B.6. FAC-001-1, R3.1.6 METERING AND TELECOMMUNICATIONS ...................................................................... 11 B.7. FAC-001-1, R3.1.7 SYSTEM GROUNDING .................................................................................................... 13 B.8. FAC-001-1, R3.1.8 INSULATION AND INSULATION COORDINATION............................................................. 14 B.9. FAC-001-1, R3.1.9 VOLTAGE, REACTIVE POWER, AND POWER FACTOR CONTROL ..................................... 14 B.10. FAC-001-1, R3.1.10 - POWER QUALITY IMPACTS .................................................................................... 17 B.11. FAC-001-1, R3.1.11 EQUIPMENT RATINGS .............................................................................................. 19 B.12. FAC-001-1, R3.1.12, SYNCHRONIZING OF FACILITIES ............................................................................. 21 B.13. FAC-001-1, R3.1.13, MAINTENANCE COORDINATION ............................................................................. 21 B.14. FAC-001-1, R3.1.14, OPERATIONAL ISSUES (ABNORMAL FREQUENCY AND VOLTAGES) ........................ 23 B.15. FAC-001-1, R3.1.15, INSPECTION REQUIREMENTS FOR EXISTING OR NEW FACILITIES ........................... 24 B.16. FAC-001-1, R3.1.16, COMMUNICATIONS AND PROCEDURES DURING NORMAL AND EMERGENCY OPERATING CONDITIONS .......................................................................................................................................... 24 B.17. PROVISIONS FOR FUTURE CHANGES ......................................................................................................... 25 Facility Connection Requirements -i Revised on: 2/19/2014 - A. INTRODUCTION A.1. Family of Companies Georgia Transmission Corporation (GTC) and Georgia System Operations Corporation (GSOC) were formed out of Oglethorpe Power Corporation (OPC), created in 1974 to be the primary supplier of electricity to 38 of the 41 Electric Membership Corporations (EMCs) throughout Georgia. In 1997 Oglethorpe Power Corporation implemented a comprehensive restructuring by moving from the traditional vertically integrated organization to become 3 separate generation, transmission and system operation entities. OPC provides the generation and asset management function. GTC owns and maintains the EMC’s share of the Integrated Transmission System (ITS) and provides transmission services. GSOC provides system operation support. GSOC economically operates the generation and transmission assets of OPC and GTC, respectively while adhering to reliability standards of the North American Electric Reliability Corporation (NERC) and the SERC Reliability Corporation (SERC). A.2. Integrated Transmission System (ITS) To deliver the most cost-effective power to Georgia electric consumers, the state’s major electric utilities participate in a unique statewide network called the ITS, which was formed in 1975. Participants in the ITS include GTC, Georgia Power Company (GPC), MEAG Power (MEAG) and Dalton Utilities (DU). The ITS participants share usage of their combined power transmission lines and substations that are included in the ITS. The ITS is jointly planned by all four companies and is operated as one system. This arrangement benefits customers by eliminating the costly duplication of transmission facilities. A.3. Purpose This document defines the requirements for connecting new or modified transmission, generation, or end user (load serving) facilities to the ITS. The requirements established in this document are intended to ensure that facilities connected to the transmission grid do not have an adverse effect on reliability or public safety and meet NERC/SERC standards. Within this document, the entity requesting interconnection service is referred to as the “customer”. Facility Connection Requirements -2 Revised on: 2/19/2014 - Connection requirements for facilities (generation, transmission, and end-user) not presently connected and modifications of facilities already connected will be consistent in content and application to the requirements used by the ITS. It is recognized that while this document provides guidance on the technical issues that must be considered, it should not be considered as an all-encompassing set of requirements. Specific projects must be reviewed on an individual case by case basis. This document should not be considered as a design specification manual and therefore all final designs are subject to the approval of GTC. Further, this document only covers the technical requirements of connecting facilities to the system. There is no attempt to address legal matters or liability issues. Parties interested in accessing GTC and ITS procedures and guidelines referenced in this document may contact GTC Bulk Planning manager. A.4. Application of FCR Document The requirements set forth in this guide apply to the facilities of GTC as well as those of all other entities who wish to interconnect new or modified generation, transmission, or end-use facilities to the ITS. It applies only to facilities that are connected to the ITS at voltages 40 kV and above. A.5. Maintenance of FCR Document This document is updated as needed. When changes occur to GTC procedures and guidelines, ITS procedures and/or NERC and SERC standards, GTC conducts an assessment to determine if an update of the FCR document is warranted. In addition GTC departments are requested to evaluate the need to modify the FCR document on an annual basis. This process is documented in GTC’s facility connection requirement update process (BP-022) Facility Connection Requirements -3 Revised on: 2/19/2014 - B. Requirements B.1. FAC-001-1, R3.1.1 Procedures for Coordinated Joint Studies of New Facilities and their Impacts on the Interconnected Transmission Systems GTC performs and coordinates joint studies of new facilities (generation, transmission and end-user) and their impacts on the ITS. The following are studies performed by GTC and their corresponding study processes: - Regional Studies (BP-009 and BP-002) (Transmission and End-User Facilities) - Area Studies (BP-001 and BP-002) (Transmission and End-User Facilities) - System Impact Studies (BP-010) (Generation Facilities) and - Facilities Studies (BP-006) (Generation Facilities) Generation Facilities System Impact Studies (SIS) are triggered in response to a Generation Interconnection Request (GI) or Transmission Service Request (TSR). A SIS identifies the impact of the request on the ITS through analyses such as stability, short circuit, closing angle, reactive requirement, power flow, interface, bus ampacity and ground grid. The process includes an initial affected party meeting to discuss the study scope and a second affected party meeting to discuss the study results and solutions with the ITS members. Facilities Studies (FS) are conducted subsequent to System Impact Studies. These studies identify in detail the required system improvements including cost and lead time but also are an opportunity to conduct further system impact analyses as necessary. GTC holds meetings with ITS members to discuss the study results. In the event of changes to study assumptions (including previously provided customer data) a new SIS and/or FS may be initiated based on engineering judgment. Facility Connection Requirements -4 Revised on: 2/19/2014 - Once the GI or TSR requestor signs an Interconnection Agreement with GTC or confirms the Transmission Service Request, the generator data is submitted for inclusion into the base cases per the Base Case Development Process (BP-002). Transmission and End-User Facilities GTC collaborates with the other ITS members throughout the study process. The base cases used to perform the studies are jointly created and reviewed. In particular, collaboration on integrating new or modified end-user and transmission facilities is achieved at this stage as described in the Base Case Development process (BP-002). Regional studies and Area studies are performed annually to identify thermal and voltage constraints in each of GTC’s regions within the ITS for the near term (0-5 years) and long term (6-10 years). The study process includes meetings among ITS members through the year to verify the base cases data, discuss the system violations identified and propose solutions. Any identified solutions are re-evaluated every year. The prior mentioned studies (Regional Studies, Area Studies, System Impact Studies and Facilities Studies) may indicate the need for system improvements such as construction of new transmission facilities or modification of existing transmission facilities. If these improvements are to be implemented, GTC uses the Capital Project Approval Process (BP-004) to review the projects internally then solicit the ITS members approval. Once projects are approved they moved to the construction phase. B.2. FAC-001-1, R3.1.2 Procedures for Notification of New or Modified Facilities to Others (those responsible for the reliability of the Interconnected Transmission Systems) as soon as feasible. The following are GTC’s procedures for notification of new or modified generation, transmission and end-user facilities to others (those responsible for the reliability of the interconnected transmission systems) as soon as feasible: Generation Facilities: Facility Connection Requirements -5 Revised on: 2/19/2014 - Notification of new or modified generation facilities to external contacts and ITS participants is performed through the following processes: BP-010 System Impact Study Process BP-006 Facilities Study Process BP-005 Transmission Facilities Upgrades Process BP-004 Capital Project Approval Process GTC posts all received Generation Interconnections (GIs) and Firm Transmission Service Requests (TSRs) on its OATI webOASIS portal: http://www.oatioasis.com/gtc/index.html. Changes to the rated MW output or Point of Interconnection require submitting a new GI request. Either Party (GTC or the generator owner) shall notify the other in advance of any changes in their respective facilities, which reasonably can be expected to affect the proper coordination of protective devices of either party. Should any changes occur to the customer interconnection facilities, GTC must be notified and provided appropriate data to perform studies as needed. Once a request moves to the System Impact Study phase, the BP-010 process ensures notification of ITS participants of the study scope, analyses and results of the study. At the Facilities Study stage, the BP-006 process ensures the external contacts and ITS participants notification regarding the scope, analyses and results of the FS including project cost and timeline. Should the project move forward, Transmission Facilities Upgrades Process (BP-005) and Capital Project Approval Process (BP-004) identify how GTC notifies the ITS participants and obtains approval of the associated capital projects. Transmission and End-User Facilities Notification of new or modified transmission or end -user facilities to external contacts and ITS participants is performed through the following processes: BP-001 Area Study Process BP-009 Regional Study Process BP-002 Base Case Development Process BP-005 Transmission Facilities Upgrades Process BP-004 Capital Project Approval Process Facility Connection Requirements -6 Revised on: 2/19/2014 - ITS notification of new and modified end-user facilities to ITS members is performed through the Base Case Development process (BP-002). The Regional Study, Area Study, Transmission Facilities Upgrades and Capital Project Approval processes. A Regional or Area study may determine the need for a transmission facility modification to address transmission system constraints. Notification of ITS participants of such modifications is performed through the Transmission Facilities Upgrades Process (BP-005) and Capital Project Approval Process (BP-004). B.3. FAC-001-1, R3.1.3 Voltage Level and MW and MVAR Capacity or Demand at Point of Connection. Generation Facilities The generator shall have the capability to supply or absorb reactive power in accordance with Good Utility Practice, ITS Planning and Operating Guidelines and Procedures (ITS Operating Procedure #23), the generator’s Interconnection Agreement with GTC and applicable operational and/or reliability criteria, protocols, and directives, including those of the Applicable Reliability Council and Applicable Laws and Regulations and this Agreement GTC requires the generators to meet design and operational requirements as described in NERC FAC-001 Reliability Standard and SERC Guideline for Facility Connection Requirements. Design requirements include: Load following capability AGC Reactive power output Remote control functions Coordination of generation control system settings Load shedding Black start capability Dynamic stability and the use of power system stabilizers as appropriate Internal plant systems design (e.g., transformer rating/taps/impedance, cooling systems, generator/exciter rating) should not limit continuous reactive capability. Transmission interconnected equipment should have the tap ranges and self-regulation necessary to accommodate the transmission system's reactive power flow requirements. Facility Connection Requirements -7 Revised on: 2/19/2014 - Transmission interconnections should not have an impact on adjacent areas' voltage and reactive power flow requirements Operational requirements include: Operation at 60Hz nominal Mode of frequency control Operation of generators during frequency decline conditions Coordination between generator controls and under-frequency load shedding programs Speed droop setting Responsibility for coordination with the appropriate operating entity Verification of reactive support capability per NERC Reliability Standards and corresponding SERC documents Generator step-up transformer (GSU) tap changes as necessary to meet voltage schedule and reactive support requirements The generator owner shall respond to requests from GTC to increase or decrease generator reactive power output in a manner consistent with generator's obligation to operate and control the generation facility. The generator facility shall supply or absorb such reactive power in accordance with the voltage schedule or reactive levels prescribed by GTC but not in excess of the amount available from the generation facility’s equipment in operation at the time and within the manufacturer’s design limitations of the generation facility. ITS Operator shall provide the voltage schedule to the generator owner/operator. Transmission and End User Facilities Transmission interconnected equipment should have the tap ranges and self-regulation necessary to accommodate the transmission system's reactive power flow requirements. Transmission interconnections should not have an impact on adjacent areas voltage and reactive power flow requirements Facility Connection Requirements -8 Revised on: 2/19/2014 - B.4. FAC-001-1, R3.1.4 Breaker Duty and Surge Protection Generation, Transmission and End-User Facilities All interconnection facilities must meet or exceed the fault duty capability as determined through short circuit analyses and should fully comply with the latest ANSI/IEEE standards for circuit breakers, switchgear, substations, and fuses. It is the responsibility of the generation interconnection customer and the transmission and load interconnection customer to notify GTC of any changes in their facilities that may cause an increase in fault currents. Additional requirements for Generation Interconnection Customers GTC requires the generation interconnection customers to meet the following design requirements described in NERC Reliability Standard FAC-001 and SERC Guideline for Facility Connection Requirements: Each Party (GTC and customer) is responsible for the short circuit capabilities of their own current carrying elements. Each Party is responsible for the ratings of their own interrupting devices. It is the responsibility of the customer to coordinate their relays and devices with the Transmission System Operator Each Party shall supply the other existing and planned future fault current levels when requested. B.5. FAC-001-1, R3.1.5 System Protection and Coordination Generation, Transmission and End-User Facilities The customer is responsible for providing a protection system that will protect its equipment against disturbances on GTC’s system and minimize the effects of disturbances from the customer facilities on GTC’s equipment and transmission system. The "protection system" arrangement selected by the customer must be compatible with the protection system used by GTC to protect the transmission grid. Compatibility will include protection philosophy, operating speed, types of communication media (such as power line carrier or fiber optic) and communication (carrier) frequency. GTC’s minimum protection requirements can be found in the ITS Operating Procedure #5: ITS Protection System Philosophy. Facility Connection Requirements -9 Revised on: 2/19/2014 - Transmission Facilities Operating voltage and proximity to a generating unit will be a major consideration in the selection of the primary and backup relay units that will be required for protecting a transmission line that connects to the ITS. These considerations, in conjunction with the particular stability classification (critical or noncritical) determined during the facility tests, will determine the extent to which backup coverage is to be incorporated in a transmission line's protection scheme. Generation Facilities The type, size, and location of the generation will determine the specific requirements. At the request of the customer and prior to granting a generation interconnection, GTC conducts a System Impact Study and Facilities Study to determine any ITS system protection and coordination requirements. During the System Impact Study, the customer shall submit its protection scheme for review and approval by GTC. The customer will be responsible for synchronizing its facility to GTC’s electrical system. Anti-Islanding Requirements: Should the generator connect to a transmission line having other tapped load, there may be an additional requirement to prevent islanding. For the purpose of this document, islanding is defined as a generator being isolated such that it is the only source of power to a utility customer. Generation customer’s protection system should be responsible for sensing abnormal frequency and tripping the customer’s own generator to isolate from GTC’s system. End User Facilities The End User is responsible for providing a protection system that will protect the End User equipment against disturbances on GTC’s system and minimize the effects of disturbances from its facilities on GTC’s equipment and transmission system. For facilities larger than 100 MW, the End User shall provide GTC its planned protection system for GTC to review to ensure proper coordination of the protection schemes. Facility Connection Requirements - 10 Revised on: 2/19/2014 - B.6. FAC-001-1, R3.1.6 Metering and Telecommunications Generation, Transmission and End-User Facilities Telemetering and Metering (Communication) A GTC supplied Data Concentrator and/or Remote Terminal Unit (RTU) will be required for gathering customer load and transmission equipment status information that will be communicated back to the GSOC Operations Control Center. The customer will reimburse GTC for the required SCADA devices and GTC shall own and maintain these devices. The Data Concentrator/RTU will have the ability to accept many standard protocols; however, the GTC preference is DNP 3.0 with Level 2 compliance. It is the responsibility of the customer to coordinate and provide the data in a protocol/interface that can be interfaced with the GTC SCADA system. A point assignment sheet will be developed in coordination with the customer showing expected data type and physical interface. It is the responsibility of the customer to ensure timely and accurate translation of the data required and documented by the point assignment sheet. Instantaneous voltage data plus bi-directional analog real power and reactive power flow information must be telemetered directly to the location(s) specified by GTC. The customer will also provide the dedicated data circuit(s) necessary to provide necessary customer data to GTC. The data circuit(s) shall extend from generator’s facility to a location(s) specified by GTC. The customer shall provide, at their expense, an Ethernet or MPLS data circuit dedicated for GTC’s use and have, at a minimum, 1.5Mbps of committed information rate bandwidth and throughput. The customer will provide standard voice and facsimile communications at its facility control room through use of the public telephone system Facility Connection Requirements - 11 Revised on: 2/19/2014 - Typical data requirements include the following: Status of interrupting devices MW flow MVAR flow Amps – three phase and per phase Power factor Voltage at interconnection point Telemetering and Metering (Billing) GTC shall specify, own, and maintain all meters and metering devices (including RTUs) used to measure the delivery and receipt of energy for payment purposes. The revenue metering package consists of a primary revenue meter and a secondary revenue meter as a backup. The secondary revenue meter will be polled in case of failure of the primary revenue meter and utilized for billing purposes. If both meters should fail, GTC will use a metering translation process to determine the usage. Meter accuracy will be maintained within +/- 0.3%. Primary meters in service are tested by GTC on an annual basis, or as requested by the ITS or any other lawfully constituted authority having jurisdiction over meter accuracy. A fiber optic interface, for the purpose of communications between GTC’s metering equipment, RTU, and MPLS communication access shall be provided by the customer at their expense. The customer shall provide, at their expense, an extension of the GSOC Operations Control Center's PBX system in the control room of the customer for purposes of generation scheduling and/or coordination of switching. In addition, GTC shall specify, own, and maintain at customer expense any additional equipment or materials deemed necessary by GTC to protect the aforementioned Telemetering and Metering equipment from cyber/physical threats or comply with NERC or other security standards. At a minimum, generator and load metering data requirements shall include the following: kW kWh Facility Connection Requirements - 12 Revised on: 2/19/2014 - kVAr, leading and lagging kVAr-hour kV 2 -hour Voltage (to monitor voltage schedule compliance) Automatic Voltage Regulation Status Power System Stabilizer Status if applicable Status of interrupting and/or syncing devices GTC will provide kW and kVAr data pulses to the customer upon request if technically feasible. Additional equipment and network connections may be required to be purchased by the customer. The preferred method of data transfer is digitally via serial port from the meter or a solid state pulse initiator. All revenue metering instrument transformers installed shall be of metering class, dedicated solely for revenue metering, and must be strictly in accordance with the latest version of IEEE Standard C57.13 and, if applicable, ANSI Standard C93.1. Metering cables shall be connected directly between the secondary posts and the GTC Revenue Meter Test Switch with no breaks. All such connections shall be inspected by GTC ECS personnel for accuracy prior to being energized. B.7. FAC-001-1, R3.1.7 System Grounding Generation, Transmission and End-User Facilities The interconnecting facility shall have its own independent ground grid if the facility is outside of the GTC substation fence. When the GTC substation and the interconnecting facility are adjacent to each other, the grids shall be connected together. The specifics for coordination of the interties between ground grids are discussed at pre-design meetings. The ground grid to be interconnected with the GTC ground grid shall be of compatible design. The substation grounding system in general shall provide for personnel safety and enable coordinated system protection. Facility Connection Requirements - 13 Revised on: 2/19/2014 - When the interconnecting facility is within the GTC substation fence, the interconnecting facility will be incorporated into the design and construction of the GTC ground grid. The substation grounding design standards can be found in the ITS Operating Procedure #7: ITS Substation Design Standard. The transmission line grounding criteria can be found in the ITS Operating Procedure #13: ITS Overheard Line Design Standards. B.8. FAC-001-1, R3.1.8 Insulation and Insulation Coordination Generation, Transmission and End-User Facilities The insulation coordination must be done properly to ensure electrical system reliability and personnel safety. Basic Surge Levels (BSLs), surge arrester, conductor spacing and gap application, substation and transmission line insulation strength, protection, and shielding shall be documented and submitted for evaluation as part of the interconnection plan. GTC’s standard is to shield substations and transmission lines from direct lightning strokes. Surge arresters are also applied at major components and systems. Interconnection facilities to be constructed in areas with contamination shall be properly designed to meet or exceed the performance of facilities not in a contamination area with regard to contamination caused outages. Additional information can be found in the following ITS procedures: B.9. • ITS Operating Procedure #7: ITS Substation Design Standard. • ITS Operating Procedure #13: ITS Overheard Line Design Standards. FAC-001-1, R3.1.9 Voltage, Reactive Power, and Power Factor Control Generation, Transmission and End-User Facilities GTC requires generators to meet the following design and operational requirements described in NERC Reliability Standard FAC-001 and SERC Guideline for Facility Connection Requirements. Design requirements include the following: The internal plant electrical system design (e.g., transformers, tap settings, motors & other loads, generator/exciter, voltage regulator) should not restrict any mode of project operation Facility Connection Requirements - 14 Revised on: 2/19/2014 - within ITS voltage range and regulation. Anytime the generator plans to replace any of the stepup or auxiliary transformers, the generator shall supply data related to the transformer (e.g. size and type, available tap settings, impedance data, loss data etc.) to GTC for the purpose of determining the optimum tap setting via reactive requirement study. When tap changes are necessary, GTC shall provide the generator with a report that justifies the required tap setting changes and technical justification for these changes. Transmission interconnected equipment should have the tap ranges and self-regulation necessary to operate within the ITS voltage range. Generator step-up and auxiliary transformers shall have their tap settings coordinated to meet the ITS voltage requirements. Voltage regulator load compensation, if required, to control voltage at a point beyond the generator terminals. Voltage regulator droop compensation, if required, for generators whose terminals are directly connected (i.e., cross-compound, hydro) Coordination of excitation system settings with GTC. Transmission interconnection impact on adjacent areas' voltage or reactive compensation devices. The following operational requirements must be adhered to: Load and/or generation operation to be within the acceptable voltage range and regulation as specified by GTC. The interconnection shall not result in any condition where the voltage excursion shall exceed NERC, SERC, ITS or GTC requirements. ITS acceptable voltage level ranges can be found in the ITS Planning Procedure #9. Generator voltage regulator to be operated in automatic modes. A generator voltage regulator is required to be in service and in automatic mode whenever the generator is synchronized to the system. Unless otherwise directed by GSOC operations center, the automatic voltage regulator shall control the voltage output within the reactive capabilities of the generator to maintain the nominal voltage of the connected transmission system. Generator to maintain voltage schedules on transmission as required by the ITS Operator. Generators connected directly to GTC’s transmission system operate in automatic voltage regulation. Any reactive compensation devices to be coordinated with GTC. Facility Connection Requirements - 15 Revised on: 2/19/2014 - Generation Facilities Voltage Schedule GTC requires all generator owners/operators to keep detailed records as to when each on-line operating generating unit is not in automatic voltage control mode. The generator owner/operator shall be responsible for providing detailed reports on voltage deviations from the acceptable voltage ranges and summary report for a specified time period when requested by GTC, the respective NERC region or NERC (within 30 business days of the request). Power Factor Unless otherwise agreed, the generator is required to maintain a power factor within the same range as GTC pursuant to Good Utility Practices. Power factor limits are described in ITS Planning and Operating Guidelines and Procedures (ITS Operating Procedure #23), and the generator’s Interconnection Agreement. Reactive Power Generator shall supply reactive power to or absorb reactive power from the ITS in accordance with Good Utility Practice, ITS Planning and Operating Guidelines and Procedures (ITS Operating Procedure #23), the generator’s Interconnection Agreement, applicable operational and/or reliability criteria, protocols, and directives, including those of the Applicable Reliability Council and Applicable Laws and Regulations and this Agreement. Generator shall respond to requests from GTC to increase or decrease generator reactive power output in a manner consistent with the generator's obligation to operate and control the facility. The generator facility shall supply or absorb such reactive power in accordance with the voltage schedule or reactive levels prescribed by GTC but not in excess of the amount available from the facility’s equipment in operation at the time and within the manufacturer’s design limitations of the facility. ITS Operator shall provide the voltage schedule to the generator owner/operator. Facility Connection Requirements - 16 Revised on: 2/19/2014 - End User Facilities Power Factor All transmission load customers are required to maintain a power factor within the same range as GTC pursuant to Good Utility Practices. The End User facilities shall maintain a minimum power factor of 97.3% (lagging) at transmission level delivery points or as specified in the Service Agreement where applicable. B.10. FAC-001-1, R3.1.10 - Power Quality Impacts Generation, Transmission and End-User Facilities Any interconnection of a generator, transmission or end user facility to the ITS should not compromise or degrade the power quality of the ITS or its existing customers. The connection facility shall also meet any FERC, NERC or SERC reporting and reliability standards. Power quality may include but not be limited to the following: Voltage Unbalance Voltage Flicker Voltage Fluctuation Harmonic Distortion Transient over voltage Temporary over voltage Temporary under voltage Operating frequency Power factor range Interruption / Outage frequency as may be required by regulatory standards A permanent digital fault recorder and/or other monitoring equipment (Power Quality Meter) may be deemed necessary and installed by the transmission owner at the Point of Common Coupling to ensure that Power Quality standards are met and maintained, and Power Quality events are captured and measured. Facility Connection Requirements - 17 Revised on: 2/19/2014 - Frequency Control A speed governor system is required on all generators with a net output greater than 20 MW to regulate the output of the generator as a function of the system frequency. The speed governor system must respond to system frequency changes to help maintain the stability of the power system. The speed governor system shall have a speed regulation (droop) characteristic settable between three and seven percent and typically be set at five percent. Temporary Over/Under Voltage Assuming that temporary is longer than 5 to 10 seconds, then the SCADA scan rate of 2-6 seconds will capture appropriate changes. GTC measures voltage via SCADA at appropriate delivery points (load and generation). Two alarm levels are in place for both high and low voltage. The GSOC Control Center is staffed 24/7/365 and responds as needed to the mentioned alarms. Both GSOC and GPC Control Centers will alter system configuration as needed to control and maintain the voltage consistent with Table 1 of Section 1.10. Assuming temporary is less than 2-3 seconds or even less than a second: GTC has DFRs that will record the duration and magnitude of the abnormalities. GTC will study specific cases upon request and rectify the situation. Power Factor Range End User facilities: The ITS maintains an overall load power factor of 0.93 at the system peak with a minimum power factor of 97.3 lagging. Generators: Unless exempt, Generators connected to the ITS are required to maintain a voltage schedule as determined in the System Impact and/or Facilities Studies. Flicker Requirements Flicker will be assessed at the Point of Common Coupling (PCC) using an instrument in compliance with IEC 61000-4-15 (IEEE Std. 1453-2004), except that the weighting curve used to represent the response of the light bulb shall be based on the 120 volt lamp characteristics as recommended in UIE 96-10. Facility Connection Requirements - 18 Revised on: 2/19/2014 - The flicker measured at the PCC shall be 0.8 or less for the short-term flicker (Pst) and 0.6 or less for the long- term Flicker (Plt). The Pst and Plt values measured shall not be exceeded more than 1% of the time based on a probability distribution calculated for a one-week period. Harmonic and Inter-Harmonic Requirements Harmonic levels will be assessed at the PCC with an instrument that can take individual samples of voltage and current waveforms and determine the probability distribution of the individual harmonic levels for both the current and the voltage. Harmonic distortion levels at the PCC shall meet the current requirements of IEEE Standard 519 with respect to the harmonic current components. Background harmonic voltage distortion levels at the PCC should be in compliance with the recommendations in IEEE 519 In addition, the individual inter-harmonic currents shall be limited to 25% of the values in IEEE 519 and the THD calculation shall include the inter-harmonic components. The Inter-harmonics shall be calculated in 10 Hz increments. The current distortion levels specified in IEEE 519 shall not be exceeded by more than 5% of the time based on a probability distribution calculated for a one-week period. If a transmission outage occurs that does not separate the generation from the transmission system, then a second method of synchronization is used that will allow automatic reclosing relays to reconnect, the control scheme initiates a close only after a synchro-verifier relay determines that the angle and voltage are within preset limits. B.11. FAC-001-1, R3.1.11 Equipment Ratings Generation, Transmission and End-User Facilities All current carrying equipment and devices shall be designed to carry the maximum loads that are projected and used in load flow analysis. Facility loadings exceeding “nameplate” or “normal” design capacities are only acceptable when allowed by manufacturers design documentation or standard industry practices. Facility Connection Requirements - 19 Revised on: 2/19/2014 - GTC shall have the right to review customer design and specifications to verify that equipment ratings are consistent with GTC criteria. GTC’s methodology for determining facility and equipment ratings is discussed in GTC’s “Facility Rating Methodology” document. Facility Connection Requirements - 20 Revised on: 2/19/2014 - B.12. FAC-001-1, R3.1.12, Synchronizing of Facilities Generation, Transmission and End-User Facilities Transmission breakers are closed to connect two energized lines only after the phase angle across the breaker is verified. This is accomplished by one of two methods. In the first method, manual closing utilizes a sync permissive switch. The switch must be turned on to allow breaker closing. Turning on the switch energizes a synchroscope, which shows the phase angle between the lines to be tied together. This method requires the Operator to determine that the angle is within limits. The customer shall be responsible for the synchronization of generation with the transmission system. If a transmission outage occurs that does not separate the generation from the transmission system, then a second method of synchronization is used that will allow automatic reclosing relays to reconnect, the control scheme initiates a close only after a synchro-verifier relay determines that the angle and voltage are within preset limits. B.13. FAC-001-1, R3.1.13, Maintenance Coordination Generation, Transmission and End-User Facilities GTC shall have the right, but shall have no obligation or responsibility to I. Observe generator's tests and/or inspection of any of generator's system protection facilities and other protective equipment, II. Review the settings of generator's system protection facilities and other protective equipment, and III. Review generator's maintenance records relative to the facility, generator interconnection facilities, and/or generator's system protection facilities and other protective equipment. GTC shall maintain its facilities and equipment, to the extent they might reasonably be expected to have an impact on the operation of the facility (ies) in a safe and reliable manner, in accordance with Good Utility Practice and in accordance with the provisions of this document. The generator shall maintain its facilities and equipment, to the extent they might reasonably be expected to have an impact on the operation of the transmission system and GTC’s systems in a safe and reliable manner, in accordance with Good Utility Practice and in accordance with the provisions of this Agreement. Facility Connection Requirements - 21 Revised on: 2/19/2014 - Maintenance requirements are also covered in the General Requirements section of this document. Complete, precise, and timely communication is an essential element for maintaining reliability and security of a power system. Under normal operating conditions, the major link of communication with various interconnects shall be by telephone lines. GTC and the customer shall maintain communications which shall include, but not be limited to, system paralleling or separation, scheduled or unscheduled shutdowns, equipment clearances, periodic load reports, maintenance schedules, tagging of interconnection interrupting devices, meter tests, relay tests, billing, and other routine communication. The Parties shall coordinate inspections, planned outages, and maintenance of their respective equipment, facilities and systems so as to minimize the impact on the availability, reliability and security of both Parties’ systems and operations. Each Party shall provide the other with reasonable notification for routine maintenance, operational tests, inspection activities and Revenue Meter tests. For such activities that do not require major equipment or system outages, the Party performing the maintenance shall provide the other Party with at least twenty-four (24) hours prior written notice. For such activities that will require major equipment or system outages, the Party performing the maintenance shall provide the other Party with not less than five business days prior written notice. All transmission switching will be done through GSOC and GPC Control Centers for scheduled and unscheduled maintenance. Maintenance Requirements The customer shall be responsible for the design, construction, installation, maintenance and synchronization of generation with the transmission system and ownership of all interconnection facilities located on its side of the Interconnection Points. GTC shall be responsible for the design, construction, installation, maintenance, and ownership of all interconnection facilities located on GTC’s side and revenue metering equipment located on the customer’s side of the Interconnection Points. Facility Connection Requirements - 22 Revised on: 2/19/2014 - In order to perform certain maintenance, testing, and repair activities, GTC’s transmission line(s) must be de-energized. Under this condition, station service power may be interrupted to the customer. GTC will require periodic transmission line(s) outages to perform protective relay maintenance. GTC will coordinate protective system checks during these outages with the customer. GTC’s circuit breaker(s) are required to be opened periodically in order to exercise the breaker mechanism. In instances where the breaker has not been operated for an extended period, GTC may manually operate the breaker. GTC will coordinate this and any other circuit breaker maintenance with the customer. GTC or the customer may request, from time to time, routine switching of each other’s equipment. In such cases, GTC and the customer will provide reasonable notice to the other Party of any equipment switching that affects electrical service to the other Party. B.14. FAC-001-1, R3.1.14, Operational Issues (Abnormal Frequency and Voltages) Generation, Transmission and End-User Facilities When a customer desires to interconnect a generating, transmission or load-serving facility to the Integrated Transmission System (ITS) through a GTC facility, the general protection settings must be submitted to GTC for review. GTC reviews and ensures that the proper coordination between GTC and customer protection exists. GTC also ensures that customer frequency protection meets GTC requirements and that the proper metering is in place to monitor abnormal voltage conditions. GTC requires its interconnection customers to meet the design requirements described in NERC FAC-001 Planning Standard and SERC Guideline for Facility Connection Requirements: Design requirements that should be addressed include: Consideration for abnormal voltage conditions Consideration for abnormal frequency conditions Consideration for generators connected through a tapped transmission line (e.g., islanding) Relay coordination to maintain stability Load shedding implementation Operational requirements that should be addressed include: Facility Connection Requirements - 23 Revised on: 2/19/2014 - Provisions for abnormal voltage conditions Provisions for abnormal frequency conditions Provisions for load shedding Special procedures for coordination B.15. FAC-001-1, R3.1.15, Inspection Requirements for Existing or New Facilities Generation, Transmission and End-User Facilities Each Party shall perform routine inspection and testing of its facilities and equipment, including secondary low voltage control systems, in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the facility with ITS in a safe and reliable manner. Each Party shall, at its own expense, have the right to observe the testing of any of the other Party’s facilities and equipment whose performance may reasonably be expected to affect the reliability of the observing Party’s facilities and equipment. Each Party shall notify the other Party in advance of performing tests on its own facilities and equipment, and the other Party may have a representative attend and be present during such testing. If a Party observes any deficiencies or defects on, or becomes aware of a lack of scheduled maintenance and testing with respect to, the other Party’s facilities and equipment that might reasonably be expected to adversely affect the observing Party’s facilities and equipment, the observing Party shall provide notice to the other Party that is prompt under the circumstance, and the other Party shall make any corrections required in accordance with Good Utility Practice. B.16. FAC-001-1, R3.1.16, Communications and Procedures during Normal and Emergency Operating Conditions Generation, Transmission and End-User Facilities Complete, precise, and timely communication is an essential element for maintaining reliability and security of a power system. The Parties shall establish a point of contact that shall have the authority and capability to operate customer facilities according to the instructions of GTC or the appropriate Facility Connection Requirements - 24 Revised on: 2/19/2014 - operating entity. Under normal operating conditions, the major link of communication with various interconnects shall be by telephone lines. The Parties shall maintain communications which shall include, but not be limited to, system paralleling or separation, scheduled or unscheduled shutdowns, equipment clearances, periodic load reports, maintenance schedules, tagging of interconnection interrupting devices, meter tests, relay tests, billing, and other routine communication. All customers who are interconnecting generation facilities shall have provisions to obtain approval from Georgia System Operations Corporation (GSOC) prior to starting generation and connecting it to the transmission system. All customers who are interconnecting transmission facilities shall have provisions to obtain proper clearances from Georgia System Operator prior to commencing work on the customer facility. Emergency telephone numbers must be agreed upon by both parties prior to the actual connect date. B.17. Provisions for Future Changes Either Party shall notify the other in advance of any changes in their respective facilities, which reasonably can be expected to affect the proper coordination of protective devices of either party. Should any changes occur to customer interconnection facility, GTC must be notified and provided appropriate data to perform studies as needed. Facility Connection Requirements - 25 Revised on: 2/19/2014 -
© Copyright 2025 ExpyDoc