Tuen Mun District Council 2014-2015 Environment

EHDDC Paper No.73/2014
For Information on 21 Nov. 2014
Tuen Mun District Council
2014-2015 Environment, Hygiene and District Development Committee
Progress Report as at 31.10.2014
No.
A.
Items
Responsible Departments
Progress
(i)
Drainage Improvement
Works in Tuen Mun District
(ii) Progress
of
Channel
Desilting at Tuen Mun
River
Channel
(as
at
31.8.2013)
and
Maintenance
Programme
for the Coming Year
Drainage Services
Department
Annex I
(iii) Dredging Works at Fish
Wholesales
Market
and
Tuen Mun Typhoon Shelter
(iv) Tuen
Mun
Sewerage
B.
Village
Report on Environmental
Monitoring of Mud Pit V
C.
Report on Water Seep age
Problems at Buildings in Tuen
Mun District
D.
Progress Report of
Main Laying Works in
Tuen Mun District
* Chinese version only.
檔號:
HAD TMGR 1-90/8/176
HAD TMD/17-230/4/06 Pt.III
HAD TMD/17-122/10/13
HAD TMGR 17-20/1/85 Pt.III
Civil Engineering and
Development Department
Annex II
Building Department and
Food and Environmental
Hygiene Department,
Joint Office
Annex III *
Water
Water Supplies
Department
Annex IV
Annex I
Drainage Services Department ’s Progress Report
I.
Drainage Improvement Works in Tuen Mun District
Drainage Impr ovement Works by Drainage Services Depart ment: -
(i) Construction of Intercepting Drains at Shun Tat Street, Tuen Mun
Location
Shun Tat Street near Sun Fung Wai and
near the j unction of Castle Peak Road
(Hung Shui Kiu Section)
Castle Peak Road (Hung Shui Kiu
Section) near Sun Fung Wai San Tsuen
The construction commenced in May 2010.
August 2013.
Length ( m)
600
Drain t ype
Under ground
pipe
100
Under ground
pipe
drainage
drainage
The wor ks were substantially completed in
II. Progress of Channel Desilting at Tuen Mun River Channel (as at 31.10.2014) and
Maintenance Programme f or the Coming Year
Location
Pui To Road to
Siu Hong West
Rail Station
Length
(m)
2400
Department
DSD
(Anticipated
Commencement
Date)
(Anticipated
Completion
Date)
Actual
Commencement
Date
Actual
Completion
Date
(11/2014)
(2/2015)
(6/2014)
(9/2014)
6/2014
9/2014
(1/2012)
(8/2012)
12/2011
4/2012
(9/2013)
(1/2014)
10/2013
12/2013
Progress/Remarks
Works under
planning
Works completed
Wong Chu Road
to Pui To Road
Estuary to Tuen
Yee Street
850
600
CEDD
CEDD
Works completed
Works completed
III. Dredging Works at Fish Wholesales Market and Tuen Mun Typhoon Shelter
CEDD completed the dredging wor ks at Fish Wholesales Mar ket , Public Car go Wor king Area
and the central part of Tuen Mun Typhoon Shelter in earl y 2010, May 2011 and December
2013 respecti vel y. MD has not instructed any dredging wor ks.
IV. Tuen Mun Village Sew erage
The proj ect includes t he construction of four village sewerage systems in partial area of Tsing
Shan Tsuen, Tseng Tau Sheung Tsuen, Tsing Chuen Wai and Tuen Tsz Wai. The progr ess of
wor ks is satisfactory. The Works were scheduled to be complet ed in July 2015. Details of
these villages are as f ollow s:
Location
Works
Tsing
Tsuen
of Length
(m)*
Actual
Pipe Size
Commencement
(mm)
Date
150 to
11/2011
250
Anticipated
Completion Date
Shan
4543
Tseng
Tau
Sheung Tsuen
959
150
225
to
12/2011
6/2015
680
Tsing
Chuen
Wai
Tuen Tsz Wai
549
150
225
150
225
to
5/2012
6/2014
549
to
9/2012
10/2014
163
163
6/2015
Completed
Length (m)
up to 31/10/2014
3962
Progress
Approx.
87%
completed
Approx.
71%
completed
Works
completed
Works
completed
Notes:
* denote: The length shown on the table is estimated only and may subject to review based on the actual site
condition.
Drainage Services Department
October 2014
Annex II
Capping of Mud Pit IV
The capping layer of mud pits IVa and IVb was completed. Contaminated mud disposal at
mud pit IVc has ceased since 10 February 2012. We are currently constructing a capping
layer for this mud pit by using uncontaminated mud.
Progress of Mud Pit V
Contaminated mud disposal at mud pit Va has ceased since 27 August 2013. We are currently
constructing a capping layer for this mud pit by using uncontaminated mud. It is anticipated
that the disposal at mud pit V would only be resumed in early 2016.
CEDD
Annex III
屯門區議會
環境、衞生及地區發展委員會
屋宇署 / 食物環境衞生署 聯合辦事處2 (屯門分處)
屯門區樓宇滲水問題
(截至2014年10月31日)
1
2
3
1.7.06 至 31.10.2014
14187
3%
13102
92%
1085
8%
接到的投訴:
完成調查的個案
尚在調查的個案
上述第2項完成調查的個案包括:
2A
經甄別後不需作進一步調查
2B
確認滲水源頭
2C
滲水情況在調查期間停止或有所改善
2D
未能找到滲水源頭
共
註: 需要作進一步調查的個案中 (即 2B, 2C
及 2D項), 成功找到滲水源頭的比率為
7330
2194
2789
619
12932
57%
17%
22%
5%
100%
39%
個案數目
2014年 9月
196
203
104%
-7
-4%
113
42
40
8
203
56%
21%
20%
4%
100%
47%
2014年10月
176
204
116%
-28
-16%
123
46
33
2
204
60%
23%
16%
1%
100%
57%
上述第 2A 項經甄別後不需作進一步調查個案包括:
2Aa 滲水位置濕度非常低
2Ab 問題已獲解決
2Ac 業主取消投訴
2Ad 重覆投訴
2Ae 並非本處的樓宇滲水個案
共
-------------
-------------
77
0
31
0
5
113
68%
0%
27%
0%
4%
100%
70
0
44
0
9
123
57%
0%
36%
0%
7%
100%
上述第 2C 項滲水情況在調查期間停止或有所改善:
2Ca 滲水位置濕度非常低
2Cb 有關業主表示已進行維修
2Cc 業主取消投訴
-------
-------
33
7
0
83%
18%
0%
29
4
0
88%
12%
0%
---
---
40
100%
33
100%
共
屯門區滲水個案統計數字 (由2009年4月起計)
2014年 6月
2014年 7月
2014年 8月
2014年 9月
2014年 10月
1. 接到投訴個案數字 (按月份)
174
168
191
196
176
2. 投訴個案的累積數字
9887
10055
10246
10442
10618
3. 完成第 一, 二 階段調查個案的累積數字及其佔累積投訴個案的百分比
9006
4. 完成第一, 二 階段調查個案平均所需工作天
91%
9176
91%
9346
91%
9484
91%
9756
43
43
43
43
43
5. 進入第 三 階段調查個案的累積數字
3087
3125
3174
3213
3243
6. 完成第 三 階段調查個案的累積數字及其佔進入第三 階段調查個案的百分比
2504
7. 完成第 三 階段調查個案平均所需工作天
8. 完成調查個案的累積數字及其佔累積投訴個案的百分比
81%
95
8423
2572
82%
95
85%
8623
2637
83%
95
86%
8809
2706
84%
95
86%
8977
2767
85%
95
86%
9280
9. 申請入屋令的累積數字
35
35
35
35
35
10. 發出妨擾事故通知的累積數字
828
843
857
873
892
11. 檢控的累積數字
31
33
33
33
33
註: (i) 第一、二階段調查主要是確定滲水滋擾及進行基本調查(例如進行渠管色水測試),若未能找出滲水源頭而滲水情況持續,
便會進入第三階段的專業調查,期間會就各個可能滲水源頭 (排水渠管、供水喉管、地台等)作出評估及進行所需測試。
92%
87%
Annex IV
Tuen Mun District Council
Environment, Hygiene and District Development Committee
Progress Report of Water Main Laying Works in
Tuen Mun District
1.
This purpose of this paper is to report to the Committee on the latest progress of
water mains laying works in Tuen Mun District.
2.
In order to improve the condition of water supply network in Tuen Mun District,
Water Supplies Department is currently implementing one major water main laying project in the
district:
(i) Replacement and Rehabilitation of Water Mains;
3.
Currently, four works contracts of the above-mentioned water main laying projects
are under construction stage. The scope of works, construction period and progress of each
works contract are detailed in Appendix I. We would keep close monitoring on the works
progress and ensure the contractors to provide adequate resources to complete the works as soon
as possible.
4.
To facilitate the District Council Members to monitor the works progress of each
area, a summary of the progress of works at major carriageways and footways in Tuen Mun
District as at 31 October 2014 is detailed in Appendix II.
5.
We would keep close liaison with the District Council Members. Should District
Council Members have any comments on the progress or arrangement of works, please do not
hesitate to contact the responsible project officers of Water Supplies Department and our
Resident Site Staff. The contacts of responsible project officers and resident site staff are
detailed in Appendix III.
Water Supplies Department
November 2014
Appendix I
Progress Report of Water Main Laying Projects and Contracts in Tuen Mun District
(as at 31 October 2014)
Project Item /
Contract No.
Anticipated
Works
Works
Commencement
Completion
Date
Date
Name of Project/Contract
(Name of Main Contractor)
Brief Description of Works/Progress
(1)Replacement and Rehabilitation of Water Mains
186WC
Replacement and Rehabilitation
02/2009
6/2015
about 39 km aged water mains in Tuen Mun District.
of Water Mains Stage 3
14/WSD/08 Replacement and Rehabilitation of
Water Mains Stage 3
02/2009
6/2015
The works areas include Castle Peak Road (Hung Shui
Kiu to Lam Tei), Tuen Mun North, Tuen Mun South,
Pillar Point, Castle Peak Road – So Kwun Wat and
Castle Peak Road – Tai Lam, etc. About 90.5% of
the works was completed in Tuen Mun District.。
04/2011
12/2015
The project includes replacement and rehabilitation of
about 97.7 km of water mains in Tuen Mun District.
- Mains in Tuen Mun & Yuen Long
(Chun
Wo
Construction
Engineering Co. Ltd.)
191WC
Replacement and Rehabilitation
of Water Mains Stage 4 Phase 1
The project includes replacement and rehabilitation of
&
Appendix I
Project Item /
Contract No.
Anticipated
Works
Works
Commencement
Completion
Date
Date
Name of Project/Contract
(Name of Main Contractor)
8/WSD/10 Replacement and Rehabilitation of
Water Mains Stage 4 Phase
04/2011
12/2015
1 –Mains in Tuen Mun, Yuen Long,
North District and Tai Po
Brief Description of Works/Progress
The works areas include Tuen Mun North, Castle Peak
Road East, Tsing Shan Tsuen, Lung Kwu Tan, Tai Lam,
etc. About 98.2% of the works was completed in Tuen
Mun District.
(Hsin Chong Construction Co., Ltd.)
9/WSD/10 Replacement and Rehabilitation of
Water Mains Stage 4 Phase 1 –
Major Mains in Western New
Territories
(Chun
Wo
Construction
Engineering Co. Ltd.)
12/2015
The works areas include Tuen Mun North, Castle Peak
Road – San Hui to Castle Peak Bay, Choi Yee Bridge,
Lung Mun Road, Fung On Street, etc. About 78.6% of
the works was completed in Tuen Mun District.
10/2013
12/2015
The main works areas include Tuen Mun North, Tuen
Mun Kau Hui, Sam Shing Hui, So Kwun Wat, Siu Lam,
etc in Tuen Mun District. About 39.5% of the works was
completed in Tuen Mun District.
&
6/WSD/13 Replacement and Rehabilitation of
Water Mains Stage 4 Phase
1 –Mains in Kwai Tsing, Tsuen Wan
and Tuen Mun
(Ming Hing Waterworks
Engineering Company Limited)
07/2011
Appendix II
Works under Construction at Major Carriageways and Footways in Tuen Mun District
Progess Report as at 31 October 2014
(A)Hung Shui Kiu, Lam Tei and Castle Peak Road - Lingnan Areas
No.
A13
A9
Contract No.
Location
Carriageway/
Footway
8/WSD/10
Fuk Hang Tsuen and Fuk
Hang Tsuen Road
Carriageway and
footway
9/WSD/10
Tuen Fu Road
Carriageway
Commencement
Date (Month/
Year)
02/2013
06/2012
Anticipated
Pipe
Completion
% of
Length
Date
Completion
(m)
(Month/ Year)
11/2014
11/2014
2004
755
Remark
98%
The works was substantially
completed. The remaining service
connection is scheduled to be
completed in November 2014 due
to liaison with affected customers.
97%
Pipe laying works were almost
completed at carriageway and the
carriageway was resumed to the
public. The remaining connection
works at carriageway are
scheduled to be completed in
November 2014.
(B)Pui To Road North, Ming Kam Road and Castle Peak Road - San Hui Areas
No.
Contract No.
Tsing Lun Road
(near Tuen Mun Hospital
Entrance)
B24a
B24b
Location
14/WSD/08
Carriageway/
Footway
Carriageway
Tsing Lun Road
(near the glasslands between
Footway and glasslands
Siu Hong court and Kei Lun
Wai)
Commencement
Date (Month/
Year)
02/2012
12/2011
Anticipated
Pipe
Completion
% of
Length
Date
Completion
(m)
(Month/ Year)
01/2015
03/2015
300
300
Remark
88%
The footpath has been resumed for
public use. Further liaison with
MTRC regarding the remaining
works at the concerned location
has been carried out and the
MTRC's consent was granted in
October 2013. The construction
method has to be revised in respect
of the obstruction of the
underground hard materials.
Further liaison with MTRC
regarding the revised construction
method at the concerned location
has been carried out. The MTRC's
consent for the revised
construction method at the
concerned location was granted in
May 2014. The works is scheduled
to be completed in January 2015.
88%
The WSD's works have to be
revised to incorporate with the
proposed site formation work of
Tuen Mun Area 54. Further
liaisons with MTRC and the local
residents had been carried out and
the works were commenced in late
August 2013. Regarding the
ground condition near the MTRC
tracks, additional grouting works
was required to be carried out. The
MTRC's consent for the additional
grouting works was granted in
June 2014 and the grouting works
is in progress. The works is
scheduled to be completed in
March 2015.
Tsing Lun Road
(near the main entrance of
Castle Peak Hospital)
B24d
Yip Wong Road
(near Tsing Wun Road)
B26c
Carriageway
Carriageway
04/2013
07/2013
06/2015
01/2015
600
120
55%
The works at Tsing Lun Road near
the main entrance of Castle Peak
Hospital could not be commenced
in respect of the current traffic
condition. The works location was
thus revised and the length of
proposed water mains has been
increased. With due consideration
of the adverse effect of deep
excavation on the nearby LRT
rails, further liaison with MTRC
regarding the construction method
at the concerned location has been
carried out. The work is
rescheduled to be completed in
June 2015 tentatively.
90%
After several liaison with DSD
regarding the proposed pipe laying
works at the concerned location,
the works programme has to be
revised. The works at Tsing Wun
Road could not be commenced in
respect of the current traffic
condition. The works location was
thus revised and the length of
proposed water mains has been
increased. The works was
substantially completed. However,
the remaining water connection
works is required to be carried out
at the same time with the water
supply suspension proposal of
Contract No. 9/WSD/10 in order
to reduce the number of water
supply suspension in Tuen Mun
district. In this regard, the works is
rescheduled to be completed in
January 2015.
65%
The WSD's works have to be
revised to incorporate with the
Construction of Sewage Pumping
Station near Tsz Tin Road and
Associated Sewerage Works in
Area 54, Tuen Mun (Contract No.
CV/2012/02). The works is
scheduled to be completed in
December 2014.
98%
The works was substantially
completed. The remaining
connection shall be carried out
after completion at Tuen Mun
Road, it is therefore it is scheduled
to be completed in December
2014.
14/WSD/08
B44
San Fuk Road
Adjacent to Tuen Mun River
Channel
B36
Carriageway and
Footway
Cycle track
08/2014
03/2013
12/2014
12/2014
230
735
Adjacent to Tuen Mun Road
Carriageway and
footway
05/2013
12/2014
1945
84%
The works was substantially
completed. However, the
remaining works at San Hui Park
shall be sought consent from
LCSD. The works is scheduled for
completion in December 2014.
B41
Leung Tin Tsuen (2)
Carriageway and
10/2013
07/2014
1940
100%
The works was completed in July
B42
Tuen Mun (N) Water
Service Reservoir
90%
The works was substantially
completed. The remaining service
connection is scheduled to be
completed in December 2014 due
to liaison with affected customers.
B37
9/WSD/10
Carriageway
01/2014
12/2014
30
(C)Lung Mun Road to Lung Kwu Tan and Tuen Mun Ferry Pier Areas
No.
C4a
Contract No.
14/WSD/08
Location
Wu Chui Road
(Melody Garden to Tuen
Mun Salt Water Pumping
Station)
Lung Mun Road
(Glorious Garden to Tuen
Tsing Lane)
C5a
Carriageway/
Footway
Carriageway
Carriageway
Commencement
Date (Month/
Year)
03/2011
12/2012
Anticipated
Pipe
Completion
% of
Length
Date
Completion
(m)
(Month/ Year)
06/2015
06/2015
550
100
55%
After several liaison with MTRC
regarding the proposed relocation
of equipment cabinets at Wu Chui
Road near Melody Garden, the
works programme of WSD's works
has to be revised. As the
completion date of MTRC's works
at the carriageway of Wu Chui
Road near Melody Garden was
delayed, the date for resuming the
WSD's works was revised. In
addition, with due consideration of
the adverse effect of deep
excavation on the nearby LRT rails
at Wu Chui Road near Tuen Mun
Salt Water Pumping Station,
further liaison with MTRC
regarding the construction method
at the concerned location has been
carried out. The permit-to-work
was being reviewed by MTRC.
The works is scheduled to be
completed in June 2015.
48%
Further liaison with DSD and
MTRC regarding the revised
construction method had been
carried out. The works is
scheduled to be completed in June
2015 tentatively.
14/WSD/08
C10
C11
14/WSD/08
C6
9/WSD/10
C9
Remark
Wu Shan Road
(J/O between Wu Shan
Road / Wu King Road)
Glasslands
09/2013
01/2015
100
90%
The progress of reinstatement
works has been affected in respect
of current traffic condition. The
works is rescheduled to be
completed in January 2015
tentatively.
Ho Yeung Street
(near Chu Kong Warehouse)
Carriageway
12/2013
10/2014
200
100%
The reinstatement works was
completed. The carriageway was
resumed for public use.
Siu Lang Shui Road and
Lung Mun Road
Carriageway
06/2012
07/2015
2235
69%
The works was in progress.
40%
As portion of works area was
currently occupied by DSD
project, the works is scheduled for
completion in November 2014.
The pipe laying works is
anticipated to commence in
December 2014.
Siu Lang Shui Road and
Butterfly Beach Park
Carriageway and
footway
08/2013
04/2015
1338
(D)Pui To Road (South), Tuen Mun Town Centre and Castle Peak Road - Castle Peak Bay to Tai Lam Areas
No.
Contract No.
Location
Tseng Choi Street
(Tuen Mun Bound)
D19a
Carriageway/
Footway
Carriageway and
glasslands
Commencement
Date (Month/
Year)
09/2012
Anticipated
Pipe
Completion
% of
Length
Date
Completion
(m)
(Month/ Year)
03/2015
125
87%
The works at Castle Peak Road
could not be commenced in respect
of the current traffic condition. The
works location was thus revised
and the length of proposed water
mains has been increased. The
original location of the receiving
pit has to be revised due to
congested underproung utilities.
Liaison with the another contracts
nearby has to be carried out. In this
regard, the works is scheduled to
be completed in March 2015
tentatively.
77%
The existing water mains were
found deviated from the mains
record plan, the construction
method and connection details
have to be revised. In this regard,
the length of proposed water mains
has been increased. The works is
scheduled to be completed in
March 2015 tentatively.
65%
The newly laid water main was
found defective. Additional time
would therefore be required for
identification of the leak point for
rectification followed by further
pressure test and thus the schedule
of the water main connection
works has to be revised. The
identification works is in progress.
The works is scheduled to be
completed in January 2015
tentatively.
55%
The WSD's works have to be
revised to incorporate with the
Design and Build of Traffic
Improvements to Tuen Mun Road
Town. Centre Section (Contract
No. HY/2009/03). The works is
scheduled to be completed in
March 2015.
Due to the working area at
carriageway was currently
occupied by other party, the
remaining works would be
completed in late December 2014.
14/WSD/08
Glasslands near Castle Peak
Road
(near Brilliant Graden and
Fu Tei Bound)
D28b
Hoi Wing Road
(near Gas Station)
D60a
Carriageway and
glasslands
(across Castle Peak
Road)
Footway and
Carriageway
02/2012
06/2014
03/2015
01/2015
180
120
14/WSD/08
D67
Tsing Hoi Circuit
Footway and
Carriageway
06/2014
03/2015
1300
D58
Castle Peak Road - Castle
Peak Bay
(Near Tuen Shing Street)
D64
9/WSD/10
So Kwun Wat Tsuen
Kwun Tsing Road
Tsing Tai Road
D65
D66
D67
D68
Fung On Street
D62
D63
6/WSD/13
D65
D66
Nim Wan Tsuen (3)
Carriageway
Carriageway and
footway
Footway
Footway
Carriageway &
Carriageway &
Footway
09/2013
12/2014
30
98%
03/2014
08/2014
1491
100%
07/2014
08/2014
08/2014
11/2014
12/2014
01/2015
334
658
689
85%
40%
8%
10/2014
04/2015
854
5%
Tsing Tai Road
Footway
02/2014
12/2014
80
100%
Access road at Castle Peak
Road -Tai Lam
(Near Marine Police Tai
Lam Chung Base)
Carriageway
02/2014
12/2014
980
90%
05/2014
12/2014
185
95%
06/2014
05/2015
480
70%
Tsing Bik Street
Siu Sau village
Carriageway and
footway
Carriageway and
footway
Remark
The works was completed in
August 2014.
The works was in progress.
The works was in progress.
The works was in progress.
The works was commenced in
October 2014.
The works was completed in June
2014.
Appendix III
Staff Contact List for Works Contracts under Water Supplies Department in Tuen Mun District
Works Contract No.
Name of Project / Contract
Department/Company
Name
Post
Telephone
Fax
Email
2634-1800
[email protected]
(Name of Main Contractor)
14/WSD/08
Water Supplies Department
Replacement and Rehabilitation of Water Mains
Stage 3
- Mains in Tuen Mun & Yuen Long
(Chun Wo Construction & Engineering Co.
URS CDM Joint Venture
Ltd.)
Mr. KWOK Wing Cheong
Senior Engineer/Consultants
Management (2)
Mr. WONG Kin San
Engineer/Consultants Management (12)
2634-3686
2634-1800
[email protected]
Mr. CHEUNG King Tak
Senior Resident Engineer
2443-2704
2475-7124
[email protected]
Mr. LIU Tin Man
Resident Engineer
2443-2704
2475-7124
[email protected]
Ms. Leung Yan Yee
Resident Public Relations Officer
2443-2704
2475-7124
[email protected]
6323-0136
--
--
24-Hour Hotline (operated by resident site staff)
8/WSD/10
Mr. TSE Kam Kwan
Senior Engineer/Consultants Mgt (1)
2634-3771
2634-1800
[email protected]
Mr. Michael YIP
Engr/Consultants Mgt (2)
2634-3506
2634-1800
[email protected]
Mr. PAU Kam Tim, Mason
Chief Resident Engineer
2653-7853
2653-7087
[email protected]
Ms. LUI So Yin, Jenny
Senior Resident Engineer
2653-7853
2653-7087
[email protected]
Black & Veatch Hong
Mr. CS CHEUNG
Resident Engineer
9664-3350
2653-7087
[email protected]
Kong Limited
Mr. Stephen LAU
Resident Engineer
9827-2524
2653-7087
[email protected]
Ms. YIU Ming Yan, Yan
Resident Public Relations Officer
6828-6543
2653-7087
[email protected]
9827-2508
--
--
Water Supplies Department
Replacement and Rehabilitation of Water Mains
Stage 4 Phase 1–
Tuen Mun, Yuen Long, North District and Tai
Po
(Hsin Chong Construction Co., Ltd.)
2634-3573
24-Hour Hotline (operated by resident site staff)
Mr. TSE Kam Kwan
Senior Engineer/Consultants Mgt (1)
2634-3771
2634-1800
[email protected]
Mr. WONG Kin San, Ricky
Engineer/Consultants Management (12)
2634-3686
2634-1800
[email protected]
9/WSD/10
Mr. PAU Kam Tim, Mason
Chief Resident Engineer
2653-7853
2653-7087
[email protected]
Replacement and Rehabilitation of Water Mains
Ms. LUI So Yin, Jenny
Senior Resident Engineer
2653-7853
2653-7087
[email protected]
Stage 4 Phase 1–
Mr. CHEUNG Chi Shing
Resident Engineer
9664-3350
2478-7929
[email protected]
Mr. Alex TUNG
Resident Engineer
9664-3366
2478-7929
[email protected]
Ms. YIU Ming Yan, Yan
Resident Public Relations Officer
6828-6543
2653-7087
[email protected]
--
--
Water Supplies Department
Major Mains in Western New Territories
(Chun Wo Construction & Engineering Co.,
Ltd.)
Black & Veatch Hong
Kong Limited
24-Hour Hotline (operated by resident site staff)
6/WSD/13
Replacement and Rehabilitation of Water Mains
Stage 4 Phase 1–
Mains in Kwai Tsing, Tsuen Wan and Tuen
Water Supplies Department
AECOM Asia Co. Limited
9665-3721
Mr. CHENG Kei Chung
Senior Engineer/Project Management (1)
2829-5633
2586-1696
[email protected]
Mr. LAM Kwan, Leonard
Engineer/Project Management (3)
2829-4783
2586-1696
[email protected]
Mr. WONG Chung Tak
Chief Resident Engineer
3698-6001
3542-5033
[email protected]
Mr. LO Chi Hang, Robo
Senior Resident Engineer
3698-6005
3542-5033
[email protected]
Works Contract No.
Name of Project / Contract
Department/Company
Name
Post
Telephone
Fax
Email
Mun
Mr. LAM Kong Keung, Paul
Resident Engineer
5185-5058
3542-5033
[email protected]
(Ming Hing Waterworks Engineering Company
Ms. LAW Man Kwan, Lawman
Resident Public Relations Officer
6622-2608
3542-5033
[email protected]
3586-0473
--
--
(Name of Main Contractor)
Ltd.)
24-Hour Hotline (operated by resident site staff)