Generic Cleanroom Construction Checklist
Category
Item
General 1
2
3
4
5
Establish regular meeting schedule for overall project control and guidance
Get final approved drawings for space
Establish regular meeting schedule with Construction Manager for construction phase
Get final approval for construction costs
Obtain required approvals (building / town permits)
1
2
3
4
5
6
7
8
9
10
construct demising wall
Back up Generator
close warehouse pass-­‐thru doors
paint / patch general repairs (if required)
reconfigure cubicles exterior signage
interior signage
Business park signage
Visitors signs
11
12
13
Alarm system / security
Establish a construction hold area for materials and parts delivery outside the cleanroom space for staging.
Re-­‐label parking spaces in lot
14
Gas line for generator/clean rooms.
1
2
3
4
5
6
7
8
9
10
Clean room construction
DEMOLITION OF RX SPACE
Primary Engineering controls (Hoods)
Prep Area stools
Clean room carts
Clean room stools
Stainless Steel Carts
Prep Area fixtures
Carts (Metro ™ or Similar )
Rubbermaid ™ (bins etc.)
11
12
13
14
15
16
17
18
19
20
21
Forms and labels (if changes are made/needed)
Personal Protective Equipment
Cleaning equipment & supplies
Drug Inventory
Compounding supplies
Pharmacy required equipment list
Refrigerator (Rx)
Ordering of automated Compounders
Ordering of Zebra Printers Individual UPS for clean room and other critical components
Bloc-­‐freezer
1
2
3
4
5
6
7
8
9
Datacom Circuit
Datacom Equipment
Voice telecom Equipment
Cabling
Move of existing service from 11-­‐H to 11-­‐B
Computer Equipment
printers / faxes
Complete computer/tele closet in warehouse
set-­‐up of VMX, phones, & system passwords for all new employees
10
Battery back-­‐ups
General construction
Pharmacy / Compounding Area
Information Systems / Technology
Vendor
Generic Cleanroom Construction Checklist
Office Space 1
2
3
4
5
6
7
8
9
10
12
13
14
15
16
Office Furniture (General / waiting areas)
Office Furniture (office)
Office Furniture (Office)
Office Furniture (Filing cabinets)
Office Furniture (break room)
Office Furniture (Conference Room)
Conference room (media equipment)
Office Furniture (side chairs)
Office Furniture (task chairs)
Office Furniture
Break room equipment
Office Supplies
Business machines (copier, fax, postage)
Artwork / wall hangings
Legal postings
1
2
3
4
5
6
7
Generator
Fixtures & Furniture
Tools & equipment
Warehouse or storeroom racking / shelving
Fork lift or Walk behind straddle lift if needed
Walk-­‐in Refrigerator
Loading Dock Plate
1
2
3
FDA application
DEA certificate
CDS application
4
5
BOP application/ renovation package
Weights & Measures Inspection
6
Certification of clean room environments
1
2
3
4
5
6
7
8
9
10
Finalize staffing model
Extend "in-­‐house" offers
Re-­‐run ads?
Re post with recruiters?
Schedule phone interviews RPh's
Schedule phone interviews techs
Check references / OIG / License status
In-­‐person interviews
Drug screens
Offer letters
11
12
13
14
Training &Orientation materials
Schedule training & Orientation
Schedule media fills (x3)
Job Descriptions written & approved
1
2
Critical failure & disaster plan for facility Emergency supplies
Warehouse Legal / Regulatory
Human resources
Misc. Items
Generic Cleanroom Construction Checklist
Primary Responsibility
Status
Completion date
Lead time needed
Notes / comments
6 weeks for generator if required
area preparation -­‐once demolition is complete
2-­‐3 weeks
2-­‐3 weeks
2 weeks
1 week
area out side cleanrooms
signage changes if required
signage changes if required
signage changes if required
Approved design required
Must contact current vendor for space to remove their equipment. MUST PLAN FOR ANY CRITICAL FAILURES IN ALARMS AND ENTRY SYSTEM! Project to be done in 2 phases. Perimeter first, then cleanrooms after their completion.
The generator & clean room air handler may require gas lines, this element should be included in the plumbing scope of work. Final delivery date of the components are critical.
1 week
check with vendor
2 weeks
3 weeks
2 weeks
4 weeks
3 weeks
2 weeks
2 weeks
2 weeks
4-­‐5 weeks
2 weeks
4 weeks
na
4-­‐6 weeks
May re-­‐use existing equipment
to allow data entry
compounding rooms, ante room, prep room racking,
Proofs required prior to order (need at least a mock-­‐up prior to filing with BOP) should standardize format consistent with ISMP standards
(for compounding and OSHA regs.) incl eye wash stations
Establish accounts for new distributor if required.
BOP mandated equipt.
if needed
we must standardize on 4" wide label
2-­‐4 weeks
If needed for freezing shipping ice-­‐blocks
2 weeks
2 weeks
Must check Spec, alarm should be included on back-­‐up or use cellular. Door locks an building access needed to be accounted for. Fail safe system to allow for entry in case of total power outage.
Generic Cleanroom Construction Checklist
for waiting area, and misc. (lobby table, book cases, plants, etc.)
2-­‐3 weeks
Table, chairs, telephones, Media boards
Projector or other AV equipment?
Lobby, reception, pvt offices 2 weeks
Fridge, Microwave, dishwasher ?, etc.
opening order + working stock
need to coordinate full install once front offices are done.
6-­‐8 weeks
2 weeks
6 weeks 1 week
Minimum wage, workers comp. etc. to be installed in office area
if needed
commercial type for racking, packing / staging area
basic hand tools
lift preferred due to warehouse configuration & lay-­‐out
must coordinate with electrician for hook-­‐up & final install IF Required…. Need spec! 6 weeks
4 weeks
30 day lead time to schedule inspection
if needed
if required
if required
varies upon availability of field techs
6 wks prior to start
4 wks prior to start
6 wks prior to start
6 wks prior to start
4 wks prior to start
4 wks prior to start
4 wks prior to start
4 wks prior to start
2-­‐3 wks prior to start 2-­‐3 wks prior to start 2 weeks prior to start
2-­‐3 wks prior to start 2-­‐3 wks prior to start Fix FT PT and Per diem numbers. ID of PIC.
Proper protocol must be maintained
do we have enough in pool to select a full staff from? REQUIRED
REQUIRED
REQUIRED
new employee documents, driver tests, etc. need to be assembled and copied
REQUIRED
REQUIRED
for disaster plan (flashlights etc.)