State Policy by Managing Director, KREDL.

www.kredlinfo.in
Karnataka Renewable Energy Development Limited
• KREDL was established in 1996 by the Government of
Karnataka.
• Forerunner for Ministry of New and Renewable Energy (MNRE)
and BEE.
• Nodal Agency for the Non-Conventional Energy Sources and the
implementation of various energy conservation activities.
Objective
To promote renewable energy and to initiate all necessary actions
for the Energy Conservation in the State.
Renewable Purchase Obligation specified by KERC vide
Notification No. S/03/1 dated 16.03.2011
Every Distribution Licensee shall purchase a minimum quantity of electricity from
renewable sources of energy expressed as a percentage of its total procurement during a
year as specified below :
ESCOM
RPO for RE sources other than Solar
Solar RPO
BESCOM
10 %
0.25 %
MESCOM
10 %
0.25 %
CESC
10 %
0.25 %
HESCOM
7%
0.25 %
GESCOM
7%
0.25 %
Hukkeri Society
7%
0.25 %
Provided that, a distribution licensee may in case of non-availability of solar power
generated in the State of Karnataka procure from other renewable sources of energy or
REC to the extent of shortfall in its RPO in any year
Renewable Energy Status in Karnataka
Sl No.
Renewable
Energy Sources
Capacity
Potential in
MWs
Allotted
capacity in
MWs
Installed Capacity
in MWs
1
Cogeneration
2500
1560.35
1144.55
2
Small Hydro
3000
2893.81
736.06
3
Wind
50 Mtr Height
8391
80 Mtr Height
13983
12752.61
2358.535
4
Biomass
1000
258.50
102.54
10000
222
KREDL- 17
KPCL – 14
Total – 31
29736
17687.27
4372.225
5
Solar
Renewable Energy Status in Karnataka
Renewable
Energy
Sources
Wind
Installed
Capacity In
MWs
2358.135
Small Hydro
736.06
Biomass
102.48
Solar
31.00
Cogeneration
Total
1144.55
4372.225
Contribution of RE Sources- 2008-2013
Annual Generation
RE Sources
Mini/Small
Hydro
Cogen
Biomass
Wind
2008 - 09 2009 - 10 2010 - 11
MW
429.05
MU
853.959 775.476 1586.696 1907.106 2527.312
State
Generation
RE Share
579.05
615.55
650.4
554.6
694.1
930.66
MU
295.328
300.76
302.458 222.696 240.496
MW
86.5
86.5
86.5
914.66
701.41
MW
87.5
1082.54
90.5
MU 2369.408 2763.713 2650.071 3661.216 4329.021
MW 1366.19 1511.59 1765.64
MW
MU
RE Generation
2012-13 2008 - 09 2009 - 10
MU 1324.348 1180.187 1564.521 1836.411 1201.122
MU
Solar
2011 - 12
CUF
Nil
0
6.356
8.176
16.481
6
6
9
14
2011 - 12 2012-13
35.53% 23.41% 29.18% 32.40% 19.54%
17.58% 12.75% 24.79% 23.80% 26.65%
38.97% 39.69% 39.92% 29.39% 30.33%
19.80% 20.87% 17.13% 21.10% 22.64%
Nil
Nil
12.09% 10.37% 13.44%
4843.04 5020.13 6110.10 7635.60 8314.43 22.72% 19.94% 21.79% 23.96% 22.52%
MW 2436.34 2877.24 3404.35
MU
1980.69 2182.34
2010 - 11
3642.25 4070.79
44260.4 47783.5 44997.3 56981.0 57476.3
10.94% 10.51% 13.58%
13.40% 14.46%
* CUF – Capacity Utility Factor
MU – Million Units
MW – Mega Watts
Contribution of RE Sources- 2013-14
Status of RE Generation in the State of Karnataka (In Million Units)
RE Source
Apr-13
May-13
Jun-13
Jul-13
Aug-13
Sep-13
Oct-13
Nov-13
Mini Hydel
17.451
11.791
93.027
271.970
334.702
282.448
249.079
167.533
275.733 251.518
40.314
18.978
20.913
54.639
96.543
202.207
14.977
8.468
7.691
11.106
10.607
12.736
9.587
712.855
829.369
587.219
326.166
258.033
231.800
Co-generation
Bio-mass
Wind
16.850
213.872 403.725
Solar
2.352
1.603
2.166
2.312
4.000
1.385
2.735
3.107
Total
524.39
685.49
856.83
1130.3
957.939
675.245
619.126
614.234
Karnataka Solar Policy :2011-16
Sl
No
Category
Capacity
reserved
(MWs)
Capacity
Allotted
Remarks
1
Solar RPO
200MW
200MW
KERC has issued regulations for
procurement of 0.25% of total
power consumed,
from
solar
resource.
2
Solar REC
Mechanism
100MW
-------
Proposals to enhance capacity is
under consideration by Govt
(through policy revision) and
projects will be allotted only after
issue of guidelines from the Govt
3
Bundled
Power
50MW
70MW
BESCOM has signed PPA of
70MWs with NVVN on behalf of all
4 ESCOMs. This is excluding
50Mws allocation in solar policy.
8
Sl
No
4
Category
Cumulative
Capacity for
allotment
(MWs)
Captive
solar No Limit
power plants and
sale to third party
Remarks
Captive power plants and those put
up for sale of power to third party
(not to ESCOMS) do not form part of
the target of 200 MW envisaged in
the
policy.
In such
cases
the
wheeling charges have to be paid
at the rates determined by the
KERC/CERC as the case may be.
At present there is no wheeling and
banking charges within the state,
where open access is granted to
any developer.
9
Progress of projects allotted under RPO
ESCOMs
BESCOM
Company
Helene Power Pvt
Ltd
Jindal Aluminum
Limited
United Telecoms Ltd
HESCOM
Essel Infra projects
Limited
Essel Infra projects
Limited
Phase-I: 70MWs
MWs
Rate/Unit
Remarks
Project to be commissioned by
July,2014
10
7.94
10
8.25
Commissioned on 26.06.2013
3
8.46
Lands acquired. Financial closure
under process
5
8.37
5
8.46
Project to be commissioned by
July,2014
Project to be commissioned by
July,2014
Project to be commissioned by
May ,2014
GESCOM
GKC Projects Ltd
10
8.46
CESCOM
SaiSudhir Energy
Limited
10
8.49
MESCOM
Welspun Solar AP
Pvt Ltd
7
8.50
Commissioned on 09.12.2013
GESCOM
Atria Power
Corporation
Ltd(Solar Thermal)
10
11.32
Conditions precedent yet to be
achieved
10
Phase-II: 130MWs
ESCOMs
Capacity (MW)
Rate/Unit
Remarks
Sun Pharma Medication Private Limited
10
5.51
Not complied LOA
Bhoruka Power Corporation Limited
10
7.16
Heidelberg Solar Pvt Ltd
5
8.05
Complied LOA .
Signed PPA.
United Telecoms Ltd
3
7.92
Azure Power Karnataka Private Limited
10
7.47
ESD Builders and Developers Private Limited
3
7.98
Lanco Solar Energy Private Limited
10
6.31
Not complied LOA and filed petition
in High Court
Alfa Infraprop Private Limited
10
5.53
Not complied LOA
Astonfield Solar II Private Limited
10
7.13
Complied LOA .
Yet to sign PPA.
Hero Future Energies Pvt Ltd
10
7.47
Complied LOA .
Signed PPA.
GESCOM
Sharda Construction and Corporation Private Ltd
6
6.93
CESC
Waa Solar Private Limited- Tumkur 1
Waa Solar Private Limited- Tumkur 2
Raghu Infra Pvt Ltd
Aditya Medisales Ltd
5
5
3
10
7.20
7.47
7.85
6.05
ACME Jaipur Solar Power Private Limited
10
6.03
Not complied LOA and filed petition
in High Court
Welspun Solar Kannada Private Ltd.
10
8.05
Complied LOA .
Signed PPA.
BESCOM
HESCOM
Company
MESCOM
Complied LOA .
Yet to sign PPA.
Complied LOA .
Signed PPA.
Complied LOA .
Signed PPA.
Not complied LOA
11
Challenges in developing solar power
projects
• Identification of lands with clear deeds for purchase is a
difficult task.
• Permissions to purchase agriculture lands u/s109 of Karnataka
land reforms Act and Subsequent conversion of land for non
agriculture use is time consuming.
• Other statutory permissions are not happening within time
limits.
• Vetting of PPAs by competent authority is time consuming.
• Developers are facing difficulties in achieving financial
closure.
Solar Power Projects 2012 - 2013
Budget of Rs 2 Cr. have been released from the Govt. of Karnataka for the Solar Power
project.
•
Solar Roof Top Scheme 2012-13 in 5 Cities : Total Cost of the project Rs 10 Cr.:
 Subsidy from Govt. of Karnataka – Rs. 2 Cr.
 MNRE contribution – Rs. 3 Cr.
 Beneficiary Contribution – Rs. 5 Cr.
 Tender is under process.
Capacity
No. of Beneficiaries
1 KW
238
0.5 KW
476
Total
714
13
Solar Power Projects 2013 - 2014
•
Budget of Rs 10 Cr. have been released from the Govt. of Karnataka for the Solar
Power projects.
Solar Water Pumping System : Total Cost of the Projects is Rs 8.31 Cr.:
 Subsidy from Govt. of Karnataka – Rs. 4 Cr.
 MNRE contribution – Rs. 2.46 Cr.
 Beneficiary Contribution – Rs. 1.85 Cr.
 Total 131 Beneficiaries : General – 99 Nos., SC – 19 Nos., ST – 13 Nos.
 Installation of 5 HP irrigation water pumps.
 Tender is under process.
• Distribution of Solar Lantern for the beneficiaries living in the remote villages
: Cost of the Project is 4 Cr.:
 Subsidy from Govt. of Karnataka – Rs. 3 Cr.
 Cost of each solar lantern – Rs 1500
 Distribution of Solar Lantern to 26,666 beneficiaries.
 Beneficiaries contribution is Rs 375/-.
 Implementation through ESCOMs.
14
• Solar Roof Top Scheme 2013-14 in 3 Cities: Total Cost of the project Rs 9.44 Cr.:
 Subsidy from Govt. of Karnataka – Rs. 3 Cr.
 MNRE Contribution – Rs. 2.83
 Beneficiary Contribution – Rs. 3.61
 Total 669 Beneficiaries.
Category
1KW
0.5 KW
Total
General
119
238
357
SC
52
104
156
ST
52
104
156
Total
223
446
669
 For General Category – Rs. 1 Cr., for SC – Rs. 1 Cr and ST – Rs. 1 Cr.
 Tender is under process.
• Central Government D.D.G. Scheme:
DPRs for 58 villages/ Hamlets have been approved by REC. The implementation will
carried out by respective ESCOMs.
15