An overview on Drilling and Geothermal Energy Projects in Turkey

An overview on Drilling and Geothermal
Energy Projects in Turkey- 2014
Tevfik Kaya
[email protected]
Schlumberger Geothermal Services
IPM
Schlumberger
The geothermal resource potential is high
Distribution off hot springs and major geothermal fields in Turkey
Geothermal exploration in Turkey started in the early 1960s. The first geothermal well for power
generation was drilled in 1968 on high enthalpy fields for potential power production.
2
11/6/2014
Geothermal fields in Turkey for ELECTRICTY and DIRECT USAGE
•
•
•
Direct use application for heating - 35%
Thermal usage (spa) - 56%
Power generation - 9%
Comparison of Geothermal Application in Turkey
Utilization
Power Generation
9%
2002
2014
15 MWe
410 MWe
30,000 RE
89,000 RE
~ 275 MWt
~ 813 MWt
500,000 sq m- 500
acre ( 100 MWt)
2,985,000 sq m 3,000 acre(
~600MWt)
175 pc
350 pc
(~300 MWt)
(~600 MWt)
Residences Heating
56%
35%
Greenhouse Heating
Thermal Facilities,spa
Suitable for Heating (50-110 oC)
Suitable for other application
Electricity demand growth is strong in Turkey
National Installed (65,159MW)
Demand Growth
Installed
Installed
2013
Capacity MWe Capacity
(Sepetember)
Ratio
Natural Gas
19,304.8
31.60%
Hydro
21,132.7
34.50%
Lignite
8,215.2
13.40%
Imported Coal
3,912.6
6.40%
Fuel
3,895.6
6.40%
Coal
300.0
0.50%
Wind
2,604.0
4.30%
2002
2010
410.0
0.70%
2014
3.300
2023
6.000
Geothermal
Liquid fuels
1,203.3
2.00%
Asphaltite
135.0
0.20%
Others
209.0
0.30%
61,204.2
99.70%
Total
Source: T.R. Ministery of Energy
Year
Consumption
kW/capita
1.485
2.871
Installed Capacity and Demand Growth for Electricity
Turkey (September 2014)
Geothermal installed capacity is growing
Start of Geothermal Electricity
Development Per Country
County
Geothermal Generation Capacity for 12 Countries
(Gross MWe, 2012)
USA
3094
Philippines
1904
Indonesia
1197
Mexico
958
Italy
843
New Zeland
628
Iceland
575
Japan
Elsalvador
The top 12 countries cover 95%
of the world’s geothermal power
capacity
535
>410 MWe (2014)
204
Kenya
167
Costarica
166
Turkey
165
573 MWe
292 MWe (2013)
165 MWe (2012)
22 MWe (2008)
Italy
New Zealand
USA
Japan
Russia
México
El Salvador
Iceland
Philippines
China
Kenya
Indonesia
Nicaragua
France
Turkey
Costa Rica
Portugal
Guatemala
Ethiopia
Papua New Guinea
Germany
With the more than 60 geothermal developers, at the different stages .
%50 exploration stage, 27 % drilling stage and 23 % drilling and operation stage
Date
1916
1958
1960
1966
1966
1973
1975
1978
1979
1981
1981
1983
1983
1984
1984
1994
1994
1998
1999
2001
2008
Name of PP
Owner
Place
Kızıldere 1
Dora-1
Bereket
Germencik 1
Tuzla
Dora-2
Zorlu
Mege
BJE
Gurmat
Enda
Mege
Under Operation
Denizli-Sarayköy
Aydın-Salavatlı
Denizli-Sarayköy
Aydın-Germencik
Çanakkale Tuzla
Aydın-Salavatlı
Kızıldere 2
Zorlu
Denizli-Sarayköy
Irem
Pamukoren 1+2
Gumuskoy 1
Gumuskoy 2
Sinem
Deniz
Dora 3U1
TR1
Dora 3U2
Germencik 3
Kerem
Total
Maren
Celikler
BM
BM
Maren
Maren
Mege
Turkerler
Mege
Gurmat
Maren
Aydın-Germencik
Aydın-Pamokoren
Aydın-Germencik
Aydın-Germencik
Aydın-Germencik
Aydın-Germencik
Aydın-Salavatlı
Manisa-Alasehir
Aydın-Salavatlı
Aydın-Germencik
Aydın-Germencik
Installed Capacity Technology
(MWe)
Provider
15.00
7.50
6.50
47.50
7.50
12.00
60.00
20.00
20.00
44.00
6.60
6.60
22.50
22.50
21.00
24.00
20.00
25.00
22.50
Ansaldo
Ormat
Ormat
Mitsubishi
Ormat
Ormat
Fuji
TAS
Ormat
Atlas Copco
TAS
TAS
Ormat
Ormat
Ormat
Ormat
Ormat
Ormat
Ormat
410.70
Germencik 2
Ken
Germencik 4
Germencik 5
Gurmat
Maren
Gurmat
Gurmat
Zorlu Alasehir
Zorlu
Tosunlar
Sultanhisar
Pamukoren 3
Umurlu
TR2
Tuzla
Dora64
DST111/6/2014
Akca
Celikler
Celikler
Karadeniz
Turkerler
MTN
Mege
Greeneco
Under Construction ( 370 MWe)
Aydın-Germencik
Aydın-Germencik
Aydın-Germencik
Aydın-Germencik
Denizli-Sarayköy
Denizli-Sarayköy
Aydin Sultanhisar
Aydın-Pamokoren
Aydin Umurlu x2
Manisa-Alasehir
Canakkale - Tuzla
Aydin-Salavatli
Denizli-Sarayköy x2
47.5
22.5
25
25
50
10
3
44
44
24
24
8
21
22
Mitsubishi
Ormat
Ormat
Ormat
Toshiba
TAS
Exergy
Atlas Copco
Atlas Copco
Exergy
Ormat
Exergy
Ormat
Exergy
Geothermal
Power Plants
Existing and
Ongoing in
Turkey in
September
2014
2013- 82 Wells drilled
2014 -104 wells (estimated)
Geothermal Energy; an overview on Drilling and Projects in Turkey
Feed –in Tariff and Legal Framework for Geothermal Energy in Turkey:
•FIT was introduced in 2005 as a unique tariff btw 5 – 5,5 € cents, applicable for defined renewable energy
sources (18.05.2005, Law No.5346, entitled “RES Law for the)
•Implementation Regulation of FIT was not adopted at that time.
•In Turkey, geothermal energy is separately regulated by the Act numbered 5686 (Jun 3rd, 2007).
•New RES Law was adopted in Dec 2010
•It proposes below mentioned FIT at differentiated rates (7,3 10,5 – 13,3 $ cents) for different renewable
energy sources.
•Implementation Reg. is adopted & Domestic Manufacturing incentive introduced.
Power Plant Type
FIT
Hydro Power Plant
7.3
Wind Power Plant
7.3
Geothermal Power Plant
Biomass
Solar
Domestic Manufacturing
Turbine
Generator and Power Electronics
Blade
Generator and Power Electronics
Tower
Rotor and Nacel (all mechanic)
Steam or Gas Turbine
10.5 Generator and Power Electronics
Steam Injector or Vacuum Pump
13.3 Equipments
Fotovoltaik Equipments
13.3
Concentrated olar Power Equipments
Additional Local
Content
($cebt/kWh)
1.3
1.0
0.8
1.0
0.6
1.3
1.3
0.7
0.7
Max FIT
($cent/kWh)
9.6
11.0
13.2
18.9
20.0
22.5
t.kaya 2012
•
•
9
11/6/2014
>30 rigs are active in
geothermal drilling
>%90 of them is active in
Menderes and Alasehir Graben
Drillings are in two main graben, Menderes and Gediz….
Rig Count in Geothermal Power Projects in Turkey
(2014) tkaya
Capacity
(w/ 4
#
Rig
Place
Contractor
1/2" DP)
1 F-320/5
Denizli
6210 m/2000 HP
TPIC
2 F 200/11
Aydın
4000 m/1350 HP
TPIC
3 F200/10
Manisa
4000 m/1350 HP
TPIC
4 IRI 100/1
Aydın
425 HP/W.OWER
TPIC
5 MR8000
Manisa
4300 m/1080 HP
BORDRILL
6 MR8000
Manisa
4300 m/1080 HP
BORDRILL
7 Not Specified
Manisa
3000 m/1080 HP
BORDRILL
8 MR8000
Manisa
4300 m/1080 HP
BORDRILL
9 MR8001
Manisa
4301 m/1080 HP
BORDRILL
9 MR8000
Aydın
4300 m/1080 HP
MAREN
10 MR8000
Aydın
4300 m/1080 HP
MAREN
11 IDECO H44
Aydın
3000 m / 750 HP
POLMAK
12 F. Cooper LTO-750 Aydın
2500m/750 HP
GYP (AME)
13 Wilson 75
Aydın
2500m/900 HP
GYP (AME)
14 NAT 80 B
Aydın
3500 m/1000 HP
GYP (AME)
15 F200
Aydın
4000 m/1350 HP
GYP (AME)
16 Nat 32
Aydın
2500 m
GYP (AME)
17 BD125
Denizli
1600 HP
DEĞİRMENCİ
18 Gefco 185 K
Konya
2000m/600 HP
GM Müh
19 MR6000
Turkey
2000 m/540 HP
MTA
20 MR6001
Turkey
2000 m/540 HP
MTA
21 NAT N80
Turkey
3500 m/1000 HP
22 IDECO H 44
Ankara
2700/912 HP
ARAR
23 Not Specified
Manisa
2000m/600 HP
Merty
24 Not Specified
Manisa
2000m/600 HP
Petrogaz
25 Not Specified
Simav
2000m/600 HP
Umran Boru
26 Not Specified
Aydın
2500 m/1000 HP
Viking
27 Not Specified
Alasehir
1500 m/400 HP
Sonsuzluk
28 Not Specified
Aydın
2500 m/1000 HP
Pars
29 Not Specified
Aydin
2700 m/1080
KARIZMA
30 Not Specified
Aydin
4000 m/1500
KARIZMA
10 31 Not Specified
Alasehir
4001 m/1500
Enerji A
11/6/2014
.+6 Domestic manufactued rigs
Rig Count in Geothermal
Power Projects in Turkey
(2014)
Cost Breakdown for Geothermal Well
Drilling in Turkey 2014
2500
(45 days)
Price (USD)
3500 m
( 60 days)
Price (USD)
40,000
50,000
50,000
80,000
120,400
120,400
350,000
607,440
850,000
Fuel
228,000
352,000
460,000
Mob & De-mob
Total Operating Cost
(18.500$/day)
200,000
300,000
300,000
555,000
832,500
1,110,000
Mud Service
90,000
120,282
160,000
Cementing Service
120,000
160,000
220,000
Wireline logging
40,000
150,000
150,000
Acidizing
40,000
70,000
70,000
Well tests
35,000
40,000
40,000
Drilling and Geolog.
Supv.
40,000
40,000
40,000
Miscoulenous
40,000
60,000
60,000
Services
Land Acqusition and
permission
Pre-Spud Services,
waste handling
Material Purchase
(casing, bit, welhead
etc.)
Total Budget (%10
contingency)
11
11/6/2014
1,858,000
2,902,622
3,630,400
• Drilling in Turkey are not high
enthalpy well like Indonesia,
Philippines etc. so cost of casing,
well head and cementing services
less than others
• Low rig rates ($ 15-19 K/day in
Turkey, it is around $25-27 K/day
in global
• Low management cost for
company many, driller, tool
pusher,
• Low services costs for mud,
cementing
Schlumberger Confidential
1500 m
(30 days)
Price (USD)
November 2013- tkaya
According to current drilling experiences in Menderes (1500-3500) and Alaşehir (25003500 m) graben mostly metamorphic, shiest, limestone, sand stone and marble
formation,
Average penetration day for 1500-2000 meter is 35-40 days, 2000-2500 meter is 45-50
days for production wells, for the 2800-3500meter production or exploration well’s
12
average
penetration days is more than 60 days.(60-70 days)
.
thank you…