STIRLING COUNCIL THIS REPORT RELATES TO ITEM 7 ON THE AGENDA ENVIRONMENT AND HOUSING COMMITTEE HOUSING AND CUSTOMER SERVICE 6 FEBRUARY 2014 NOT EXEMPT HOUSING SUPPLY/AFFORDABLE HOUSING 1 SUMMARY 1.1 On 1 October 2013 the Scottish Government notified the Council that a further £598k would be added to the Council’s Resource Planning Assumption for 2013-2015 bringing the total funding for new projects in Stirling to £5.680m. 1.2 On 29 October 2013 the Resource Planning Assumption for 2015/16 was also increased to £3.515m, a considerable increase on the £1.991m previously approved. 1.3 This has resulted in further consideration and a number of changes to the projects previously agreed for Stirling’s Strategic Housing Investment Plan. 1.4 Members of the Strategic Housing Investment Plan (SHIP) Review Group, Housing Advisory Group and the Strategic Housing Forum have now considered and made recommendations on the proposed changes as follows:• Station Square The 53 properties at Station Road should be purchased as part of the NHT Stirling Variant building programme. This will reduce direct cost to the HRA by around £7m and free up the Scottish Government grant funding totalling £1.11m to be spent to support other projects. Overall this switch will allow an additional 42 units to be provided by December 2015. • Murray Court, Fallin After negotiation, an ‘ in principle’ agreement has been reached to purchase 12 flats and 1 house from a developer in Fallin on completion of the properties in March 2014. This project will require £390k of funding freed up from Station Square. • Unfunded properties within the approved programme The current Stirling Council new build programme includes 9 properties that are not currently funded by the Scottish Government. £318k of the funding freed up from Station Square will reduce borrowing on the HRA by a similar amount and improve the affordability of these developments to the HRA. • Additional purchases of second hand properties to assist those impacted by the under occupancy charge The remaining £402k will be available to fund a number of second hand purchases. As the grant usually approved for this is £20k per house, this should assist with the funding of a further 20 houses. • Laurelfields, Drymen The developer of the site at Gartness Road, Drymen has confirmed that they are unable to develop this site to meet the timescales required under the conditions of the Scottish Government grant. An ‘in principle’ agreement has therefore been reached with the private developer of an alternative site at Laurelfields, Drymen to purchase 4 flats and 6 houses for social rent on completion by March 2015. Potentially a further 8 flats for mid market rent to be purchased by Steadfast Homes by December 2015 will also included in the development. • Steadfast Homes Old PO Site, Callander - Following discussions with the National Park planners and Rural Stirling HA, it is proposed that the Council will proceed with the purchase and “back to back” disposal to Steadfast Homes of 23 flats in Callander through the NHT Stirling Variant programme. An ‘in principle’ agreement has been reached with the private developer to purchase the 23 flats and the developer has confirmed that they will be completed by March, 2015 which is within the required timescale. • Forth HA – development of sites at Adamson Place, Cornton and Cultenhove Road, St Ninians As a result of the increased grant now available from the Scottish Government, Forth HA has confirmed that it has capacity to bring their proposed developments in Cornton and Cultenhove forward in the Strategic Local Programme. Under the terms of the regeneration agreements for both Cornton and Cultenhove, it has been agreed that the Council will transfer the land to Forth HA for a nominal or NIL value. 1.5 The Scottish Government has confirmed that these changes would be acceptable. 1.6 The property purchased at 2 Linden Avenue is now ready for occupation and is intended to be transferred to Steadfast Homes for Mid Market Rent. 1.7 2 The Environment and Housing Committee is invited to approve these changes to the revised Strategic Housing Investment Plan. RECOMMENDATIONS The Environment and Housing Committee agrees:- 3 2.1 to note that the Resource Planning Assumption for new projects has now been increased to £5.680m for 2013-2015 and £3.515m for 2015/16; 2.2 to approve the changes to the Strategic Housing Investment Plan identified at Paragraph 3.4 in the report; 2.3 to approve the acquisition of the properties at Murray Court, Fallin, Laurelfields, Drymen to provide new Council housing at a price to be agreed by the Head of Housing and Customer Service and the Head of Assets and Support; 2.4 to approve the acquisition and back to back disposal to Steadfast homes of 23 flats on the site at Old Post Office Callander and 8 properties on the Laurelfields, Drymen; 2.5 to approve the transfer of land at NIL or nominal value to Forth HA for their developments at Cornton and Cultenhove; and 2.6 to approve the transfer of 2 Linden Avenue to Steadfast Homes at a price to be agreed by the Head of Housing and Customer Service and the Head of Assets and Support. CONSIDERATIONS 3.1 The Council submitted its Strategic Housing Investment Plan to the Scottish Government in March 2012. This is the Council’s key statement concerning housing development priorities. The Council was subsequently asked to submit a Strategic Local Programme identifying the project priorities for 2012/13 to 2014/15. 3.2 On 8 May 2012 the Scottish Government issued Stirling’s Resource Planning Assumption for 2012/13 to 2014/15, which provided £2.348m of new money for local programmes. There have been numerous increases to this funding resulting in the latest increase announced on 1 October 2013 that resulted in a Resource Planning Assumption for new projects for 2012-2015 of £5.680m and £3.515m for 2015/16. 3.3 This, together with further consideration of the Strategic Housing Investment Plan, has resulted in a number of proposed changes to the projects. 3.4 Members of the Strategic Housing Investment Plan Review Group have now considered and made recommendations as follows:• The acquisition of 12 flats and 1 house at Murray Court, Fallin The Strategic Housing Investment Plan included the development of 53 flats at Station Road. The original proposal for these properties was that 37 would receive grant assistance from the Scottish Government totalling £1.110m and the remainder would be purchased by Steadfast Homes. All properties are for mid market rent. However, it has now been agreed that it would be more appropriate for the flats to be provided through the NHT Stirling Variant programme and to be let as mid market properties by Steadfast Homes. The Scottish Government has confirmed that this change would be acceptable and that the £1.110m grant can be transferred to alternative projects. Negotiations with the developer in Fallin has resulted in an ‘in principle’ agreement for the purchase of the 13 properties. The developer has been willing to make changes to the layout and specification to meet specific Council requirements. The development has already started on site and the developer has confirmed that construction will be completed by March 2014. The development will receive £390k grant assistance from the Scottish Government. The purchase price for these properties will be approved by the Head of Housing and Customer Service and the Head of Assets and Support. It is also proposed that the funding from Station Road provides grant assistance for 9 bungalows in the Council’s bungalow programme that do not currently have Scottish Government funding. This will provide an additional bungalow in the developments in Cornton, Riverside and Plean, two in Raploch Site 4 and four in Cowie. This will require £318k of the available funding. The remainder of the Station Road funding totalling £402k will provide sufficient funding to assist with the purchase of a further 20 second hand properties. • The acquisition of 4 flats and 6 houses at Laurelfields, Drymen The Strategic Housing Investment Plan included the development of 10 properties at Gartness Road, Drymen to be completed by March 2015. However, the developer has now confirmed that they will be unable to commence this development within the timescales required. A charrette held in the village by Loch Lomond and Trossachs National Park Authority identified a site at Laurelfields, Drymen as the next priority site for housing development. After negotiation with the developer an ‘in principle’ agreement has been reached for the purchase of the 4 flats and 6 houses for social rent. A further 8 flats could potentially be provided on the site for acquisition by Steadfast Homes for mid market rent. The developer has agreed to redesign and change the specification for the properties to meet Council requirements and has confirmed that the social rented properties can be completed by March 2014 and the mid market rented flats by December 2015 which both meet the required timescales. The purchase price for these properties will be agreed by the Head of Housing and Customer Service and the Head of Assets and Support. • Steadfast Homes - Old PO Site, Callander Rural Stirling HA intended entering into a design and build contract with the developer of the Callander site for the provision of 4 flats. The remainder of the flats were either for private sale or purchase by the Council under the NHT Stirling Variant programme. Following discussions with the National Park planners and Rural Stirling HA, it is proposed that the Council will purchase all 23 flats from the developer. This will allow Rural Stirling HA to prioritise their development in Doune in 2013-2015 where a further 14 properties will be provided. In the Callander site, the developer has agreed to redesign and change the specification for the 23 flats to meet Council requirements and has confirmed that the flats will be completed by December 2015 which meets the required timescale. It is therefore proposed that the flats in Callander and the 8 flats in Laurelfields, Drymen be purchased through the NHT Stirling Variant programme. This is likely to involve acquisition by the Council and “back to back” sale on to Steadfast Homes. • Forth HA – development of sites at Adamson Place, Cornton and Cultenhove Road, St Ninians As a result of the increased grant now available from the Scottish Government, Forth HA has confirmed that it has capacity to bring their proposed developments in Cornton and Cultenhove forward in the Strategic Local Programme. Under the terms of the regeneration agreements for both Cornton and Cultenhove, it has been agreed that the Council will transfer the land to Forth HA for a nominal or NIL value. 3.5 The house at 2 Linden Avenue was purchased in 2012 as a vacant and heavily vandalised shell. The property has now been fully renovated and is ready for habitation. As the property has a number of unusual features and in order to maximise our income it is proposed that it be transferred to Steadfast Homes in return for a receipt based on the market value. As with other transactions the sale price will be approved by the Head of Housing and Customer Service and the Head of Assets and Support. 3.6 The property has single glazed timber windows in keeping with the rest of the building and the architectural style. The property also has a large garden area adjacent to a public lane and a driveway opening directly on to dual carriageway. The allocation process for Mid Market rent would ensure that applicants were accepting of the property and its various features. 3.7 These proposals have also been considered by the Housing Advisory Group and the Strategic Housing Forum. 4 POLICY/RESOURCE IMPLICATIONS AND CONSULTATIONS Policy Implications Equality Impact Assessment Strategic Environmental Assessment Single Outcome Agreement Diversity (age, disability, gender, race, religion, sexual orientation) Sustainability (community, economic, environmental) Effect on Council’s green house gas emissions No No Yes Yes Yes Strategic/Service Plan Existing Policy or Strategy Risk Resource Implications Financial People Land and Property or IT Systems Consultations Internal or External Consultations Yes Yes No Decrease Yes No Yes Yes Equality Impact Assessment 4.1 Following a scoping exercise as part of an Equality Impact Assessment and for the same reasons as the Scottish Environment Assessment (below), Stirling Council has decided that a full Equality Impact Assessment will not be necessary for the Strategic Local Programme. Strategic Environmental Assessment 4.2 The Strategic Environmental Assessment process involves scoping the potential impacts on the environment of the outcomes that may result from future strategies and policies. The exercise is carried out in consultation with 3 designated agencies – Scottish Environment Protection Agency, Scottish Natural Heritage and Historic Scotland. 4.3 In future, the Strategic Housing Investment Plan and the Strategic Local Programme will form an integral part of the Local Housing Strategy. Due to a timing mismatch for producing the new Local Housing Strategy, this year’s Strategic Housing Investment Plan and Strategic Local Programme are again stand alone documents. The Local Housing Strategy as a whole will be subject to a detailed Strategic Environmental Assessment, as will the Local Development Plan. 4.4 As required by the Environmental Assessment (Scotland) Act 2005, Stirling Council as a “responsible authority” for the purposes of the Act, has determined that no Scottish Environment Assessment submission is required for this document. This determination has been taken following feedback from the Scottish Environment Assessment Gateway and the responses from Scottish Environment Protection Agency, Scottish Natural Heritage and Historic Scotland in previous years, as the situation has not changed. Single Outcome Agreement 4.5 The Strategic Local Programme will improve the supply of social & affordable housing. Other Policy Implications 4.6 The policy implications are as set out in this report. Resource Implications 4.7 The resource implications are as set out in this report and can be fully accommodated with both the HRA and Steadfast Homes business plans. Consultations 4.6 Detailed consultation has taken place with all the relevant partners involved in the strategic housing planning process. This has included regular meetings of the Strategic Housing Investment Plan Review Group chaired by the Housing Portfolio Holder and opposition spokes persons on housing and involving Registered Social Landlord officer and board members, the Raploch Urban Regeneration Company and representatives from Stirling Council and Loch Lomond and Trossachs National Park Authority planning departments. This Group has considered and commented on the Strategic Local Programme. 4.7 Stirling’s Strategic Housing Forum/Housing Market Partnership has discussed the Strategic Local Programme priorities. 4.8 The Housing Advisory Group has also considered and agreed the contents of this report. 4.9 Discussions with the Scottish Government have also continued throughout the process of preparing this document. Tick ( ) to confirm The appropriate Convener/Vice Convener/Portfolio Holder(s)/Depute Portfolio Holder has been consulted on this report The Chief Executive/Depute Chief Executive/Assistant Chief Executive(s) has been consulted on this report 5 VW, ME, DG, NB BJ BACKGROUND PAPERS 5.1 Stirling Council Strategic Housing Investment Plan 2012/13 to 2014/15, March 2012. 5.2 Housing Advisory Group, Minutes of Meeting held on 7 August 2012. 6 5.3 Strategic Housing Investment Plan Review Group, Minutes of Meeting held on 17 August 2012. 5.4 Strategic Housing Forum, Minutes of Meeting held on 23 August 2012. 5.5 Stirling Council 11 October 2012 – Funding for Affordable House Building. Developing the Council’s Strategic Local Programme. APPENDICES 6.1 Appendix 1 – Draft Strategic Local Programme 2013/14-2017/18. Author(s) Name Designation Telephone Number/E-mail John MacMillan Technical Services Manager 01786 443566 Sandra McGinley Project Officer, Strategy and Development 01786 443956 Designation Signature Approved by Name Tony Cain Date 28 January 2014 Head of Housing Customer Service Service Reference and
© Copyright 2024 ExpyDoc