Power Distribution Systems Data Center Power Distribution Modernisation Clint Skinner Northern European Sales Manager Universal Electric Corporation Content Some considerations About UEC Data centre main challenges Overcoming these challenges Why use bus bar, why use Starline? Traditional v Starline Operational considerations Project examples – legacy & new build Power monitoring Benefits summary Some Considerations The trend for bus bar power distribution to the IT rack is growing globally UEC themselves have seen an significant increase in demand for Starline over the last 7 years largely due to the data centre industry Since 2008 Universal Electric Corporation have manufactured nearly 500 miles of busbar and ½ million plug in’s. About UEC Headquarters Canonsburg, PA London India Singapore ♦ ♦ ♦ ♦ Privately held, family owned Serving customers for over 85 years Starline bus way range in operation for over 25 years 80% of UEC business is in the mission critical sector Data Centre Main Challenges Continued optimisation of power consumption Enabling kW ranges per rack from 2kW up to 40kW Enabling Single and Three Phase Loads Meeting the power flexibility demands of the business Maximising revenue potential Maintaining uptime while the business grows Maintaining continuity including spares and design Overcoming these challenges with Starline Circuit identification made easy Improve rack power distribution flexibility Improve speed of deployment Reduce circuit lead-time & circuit addition costs Improve MAC management Improves cooling efficiency (by reducing cable air dams) Reduces risk by reducing the length of time personnel spend in the live IT space eliminating floor tile removal Why use Bus Bar? Bus bar is not a new technology BUT how we deploy and customise supporting products is evolving Rack revenues are being driven down due to the large amount of competition Demand for modular space is growing - very well suited to bus bar applications Maximise the space available i.e. utilisation is desirable so: Flexibility is key Speed of deployment can be essential Pro-active & Reactive – being prepared applies to everyone Why use Starline? • • • • • • Customisation – product flexibility to meet demand UEC will never discontinue a product once sold – continuity of spares and design Open channel design – maximise the bar space Starline does not use bolted or torqued joints - less risk + lower TCO Designed to operate live, no small print caveats – uptime maintained at all times Easiest plug-in installation in the market - very quick to install Traditional Distribution Versus Service Switchboard Bus Bar Distribution Service Switchboard UPS A UPS B UPS A UPS B UPS O/P A UPS O/P B UPS O/P A UPS O/P B Circuit Protection at the PDU Sub PDU A1 Sub PDU B1 Circuit Protection at point of use Sub-PDU’s are required No-sub PDU’s required Cable Whips under floor – circuit ID difficult Plug-ins above rack – circuit ID easy Circuit addition is slow, containment may also be needed Circuits can be added quickly at anytime Traditional system = under floor congestion UPS O/P A UPS O/P B Sub-PDU A Sub PDU-B • Under floor cable are air dams reduce cooling efficiency • Sub PDU’s can take up valuable data center space Data Centers Using Starline Track Busway UPS O/P A UPS O/P B Busway B Busway A More useable space and more efficient cooling with StarLine Operational Considerations The initial Day 1 project is only half the story The end user is left ‘holding the baby’ for many years to come IT refresh rates are likely to increase as technology moves quickly Power densities are likely to increase year on year Managing many contractors and staff for upgrade projects is hard work and a timely process Keeping personnel out of the live DC space is desirable from a risk point of view - minimise time spent in the IT space The Cable Addition Process IT decide equipment is needed Open dead front cover of PDU/RPP IT Order Equipment Whip installation begins Budget Allocated for Project Pre-fab whips are made or made on site SOW raised Project date set, material procured Contractor quotes to the SOW RAMS determined and recorded Project Timeline Decided RAMS issued The Cable Addition Process Remove necessary tiles and secure perimeter Invoice against work order Install cable under raised floor Write report and update schedules Knock out removed, may require drilling Replace floor tiles Install cable in PDU/RPP Replace covers, turn breaker on Cable secured to cabinet with lock nut/bush Inspect each cable and test Terminate phase conductors to breaker Terminate neutrals and ground conductors to common bar The Plug-in Addition Process Plug-ins are tested and approved at the factory before shipping The DC operator provides on site plug-in verification i.e. phasing prior to live installation Live plug-in installation is done with load circuit breaker open to minimise risk Starline live busbar plug-in installation is as safe as an installation of cable into a live PDU The Plug-in Addition Process IT decide equipment is needed IT Order Equipment Budget Allocated for Project Plug-ins energised and ready to use Plug-ins delivered to site and fitted Plug-ins shipped to local rep (if not in stock) Enquiry sent to local Starline rep Plug-ins manufactured and tested at factory Rep quotes for desired plug-in P.O. sent, plug-ins procured Project Timeline Decided Installation date set Legacy Project Legacy site, power upgrade required A & B feeds required per rack ‘Manhattan skyline’ low density racks Low ceiling height Legacy Project Cable Observations Starline 2 x PDU’s with PDU’s no 6 x End Feeds STS’s 4 x 250A Mains cable to PDU’s 1000m+ Cable Containment Final Supplies 150 no. 32A whips longer required No containment required No cable whips required Only 6 x bar runs needed 6 x 225A bar, End Caps, TSections, Joint Packs and Hangers 75 x Dual Single Phase 32A Plug-ins Legacy Project Bars run down aisles due to low ceiling height T-Sections proposed to facilitate future rack deployments Typical Typical Layout Applications Example New Projects with Customisation Problem: Limited head room and limited bar length Brief: Design a system to meet the customers current and future requirements – increase revenue potential Plan: Design, produce prototypes and manufacture the necessary equipment to meet demand End Result: Future proofed customers business needs by increasing circuit capacity by 100% and potentially reducing circuit monitoring costs by 50% Customer Project – End Feed Standard design – bar enters the side of the EF and faces down New End Feed – bar enters the back of the EF and faces sideways Further Designs Centre Feed Socket Feed Top Feed Customer Project – Plug-in Design 32A, 3Ø no monitoring 63A, 3Ø with monitoring and drop cord Wireless Monitoring Module Dual 32A, 1Ø, with wireless monitoring Further Bespoke Designs Starline Bus Bar Design GM100/225 • • • • • • GM250T5 GM400T5 GM800T5 Constant “spring” tension created by the U-Shaped extruded copper conductors Creates an interference fit connection between the stab-in and the receptacle Continuous Access Top and Bottom for maximum flexibility Designed and approved to install plug-ins LIVE = zero downtime Extruded Aluminum Housing Chassis - 100% earthing capability Additional earthing and double size neutral provision if required Unique Paddle Head Design Starline has the simplest and most reliable power take off in the industry. Just one soldered connection from the copper conductors to the plugin unit T5 Paddle Head StarLine Unique Joint Design Copper blades are seated into U-Shaped female busbars • Creates a maintenancefree joint • No bolted joints in system • No specialist team required to install the system Housing couplers are used for mechanical strength and to carry the ground through the aluminum housing Installation Video Web Link (including how to join the bus way) http://www.uecorp.com/busway/content.aspx?f=videos Power monitoring Power monitoring with Starline Individual circuit and row power monitoring insures no overloads The DCM can store historical data to prove customer overloads and defend SLA claims Monitoring alarms in place for throw-over scenario's preventing overloads during redundant circuit failovers (i.e. continuously sum A & B circuits) Wire free implementation reduces connectivity costs and allows remote configuration for the end user i.e. own secure portal to their data only Plug-in Monitoring/Metering End Feed Monitoring & Metering Global Accreditations/Listings • • • • • • • • ISO9001 IEC CE VDE UL NORMAS OFICIALES MEXICANAS CCC And others Benefits Summary • Flexible, reliable and efficient • Continuous access slot allows high density and maximum flexibility • Maintenance-free product • Fully customisable (plug –ins & bus bar) • Faster installation (reduced labour) • Reduces risk of human error • Easiest plug-in installation • Reusable • Ease of Design/Layout • Reduces Op Ex Cost & Risk Thank You!
© Copyright 2025 ExpyDoc