Power Distribution Systems

Power Distribution Systems
Data Center Power Distribution
Modernisation
 Clint Skinner
 Northern European Sales Manager
 Universal Electric Corporation
Content
 Some considerations
 About UEC
 Data centre main challenges
 Overcoming these challenges
 Why use bus bar, why use Starline?
 Traditional v Starline
 Operational considerations
 Project examples – legacy & new build
 Power monitoring
 Benefits summary
Some Considerations
 The trend for bus bar power
distribution to the IT rack is growing
globally
 UEC themselves have seen an
significant increase in demand for
Starline over the last 7 years largely
due to the data centre industry
 Since 2008 Universal Electric
Corporation have manufactured
nearly 500 miles of busbar and ½
million plug in’s.
About UEC
Headquarters
Canonsburg, PA
London
India
Singapore
♦
♦
♦
♦
Privately held, family owned
Serving customers for over 85 years
Starline bus way range in operation for over 25 years
80% of UEC business is in the mission critical sector
Data Centre Main Challenges
 Continued optimisation of power consumption
 Enabling kW ranges per rack from 2kW up to 40kW
 Enabling Single and Three Phase Loads
 Meeting the power flexibility demands of the business
 Maximising revenue potential
 Maintaining uptime while the business grows
 Maintaining continuity including spares and design
Overcoming these challenges with
Starline
 Circuit identification made easy
 Improve rack power distribution flexibility
 Improve speed of deployment
 Reduce circuit lead-time & circuit addition costs
 Improve MAC management
 Improves cooling efficiency (by reducing cable air dams)
 Reduces risk by
 reducing the length of time personnel spend in the live IT
space
 eliminating floor tile removal
Why use Bus Bar?
 Bus bar is not a new technology BUT how we deploy and
customise supporting products is evolving
 Rack revenues are being driven down due to the large amount
of competition
 Demand for modular space is growing - very well suited to
bus bar applications
 Maximise the space available i.e. utilisation is desirable so:
 Flexibility is key
 Speed of deployment can be essential
 Pro-active & Reactive – being prepared applies to everyone
Why use Starline?
•
•
•
•
•
•
Customisation – product flexibility to meet demand
UEC will never discontinue a product once sold –
continuity of spares and design
Open channel design – maximise the bar space
Starline does not use bolted or torqued joints - less risk +
lower TCO
Designed to operate live, no small print caveats – uptime
maintained at all times
Easiest plug-in installation in the market - very quick to
install
Traditional Distribution
Versus
Service
Switchboard
Bus Bar Distribution
Service
Switchboard
UPS A
UPS B
UPS A
UPS B
UPS O/P A
UPS O/P B
UPS O/P A
UPS O/P B
Circuit
Protection
at the PDU
Sub PDU A1
Sub PDU B1
Circuit
Protection
at point of
use
Sub-PDU’s
are required
No-sub
PDU’s
required
Cable Whips
under floor
– circuit ID
difficult
Plug-ins
above rack –
circuit ID
easy
Circuit
addition is
slow,
containment
may also be
needed
Circuits can
be added
quickly at
anytime
Traditional system = under floor congestion
UPS O/P A
UPS O/P B
Sub-PDU A
Sub PDU-B
• Under floor cable are air dams reduce cooling efficiency
• Sub PDU’s can take up valuable data center space
Data Centers Using Starline Track Busway
UPS O/P A
UPS O/P B
Busway B
Busway A
More useable space and more efficient
cooling with StarLine
Operational Considerations
 The initial Day 1 project is only half the story
 The end user is left ‘holding the baby’ for many years to




come
IT refresh rates are likely to increase as technology moves
quickly
Power densities are likely to increase year on year
Managing many contractors and staff for upgrade projects is
hard work and a timely process
Keeping personnel out of the live DC space is desirable from
a risk point of view - minimise time spent in the IT space
The Cable Addition Process
IT decide
equipment
is needed
Open dead
front cover
of PDU/RPP
IT Order
Equipment
Whip
installation
begins
Budget
Allocated
for Project
Pre-fab whips
are made or
made on site
SOW
raised
Project date
set, material
procured
Contractor
quotes to
the SOW
RAMS
determined
and recorded
Project
Timeline
Decided
RAMS
issued
The Cable Addition Process
Remove
necessary tiles
and secure
perimeter
Invoice
against
work order
Install cable
under raised
floor
Write report
and update
schedules
Knock out
removed, may
require
drilling
Replace
floor tiles
Install cable
in PDU/RPP
Replace
covers, turn
breaker on
Cable secured
to cabinet
with lock
nut/bush
Inspect each
cable and
test
Terminate
phase
conductors to
breaker
Terminate
neutrals and
ground
conductors to
common bar
The Plug-in Addition Process
 Plug-ins are tested and approved at the factory before
shipping
 The DC operator provides on site plug-in verification
i.e. phasing prior to live installation
 Live plug-in installation is done with load circuit
breaker open to minimise risk
 Starline live busbar plug-in installation is as safe as an
installation of cable into a live PDU
The Plug-in Addition Process
IT decide
equipment
is needed
IT Order
Equipment
Budget
Allocated
for Project
Plug-ins
energised and
ready to use
Plug-ins
delivered to
site and fitted
Plug-ins
shipped to
local rep (if
not in stock)
Enquiry
sent to local
Starline rep
Plug-ins
manufactured
and tested at
factory
Rep quotes
for desired
plug-in
P.O. sent,
plug-ins
procured
Project
Timeline
Decided
Installation
date set
Legacy Project
 Legacy site,
power upgrade
required
 A & B feeds
required per
rack
 ‘Manhattan
skyline’ low
density racks
 Low ceiling
height
Legacy Project
Cable
Observations
Starline
 2 x PDU’s with
 PDU’s no
 6 x End Feeds
STS’s
 4 x 250A Mains
cable to PDU’s
 1000m+ Cable
Containment
 Final Supplies
150 no. 32A
whips
longer
required
 No
containment
required
 No cable whips
required
 Only 6 x bar
runs needed
 6 x 225A bar,
End Caps, TSections, Joint
Packs and
Hangers
 75 x Dual
Single Phase
32A Plug-ins
Legacy Project
Bars run down aisles due
to low ceiling height
T-Sections proposed
to facilitate future rack
deployments
Typical
Typical
Layout
Applications
Example
New Projects with Customisation
 Problem: Limited head room and limited bar length
 Brief: Design a system to meet the customers current and
future requirements – increase revenue potential
 Plan: Design, produce prototypes and manufacture the
necessary equipment to meet demand
 End Result: Future proofed customers business needs by
increasing circuit capacity by 100% and potentially
reducing circuit monitoring costs by 50%
Customer Project – End Feed
Standard design
– bar enters the
side of the EF
and faces down
New End Feed –
bar enters the
back of the EF
and faces
sideways
Further Designs
Centre Feed
Socket Feed
Top Feed
Customer Project – Plug-in Design
32A, 3Ø no monitoring
63A, 3Ø with monitoring
and drop cord
Wireless Monitoring Module
Dual 32A, 1Ø, with
wireless monitoring
Further Bespoke Designs
Starline Bus Bar Design
GM100/225
•
•
•
•
•
•
GM250T5
GM400T5
GM800T5
Constant “spring” tension created by the U-Shaped extruded copper conductors
Creates an interference fit connection between the stab-in and the receptacle
Continuous Access Top and Bottom for maximum flexibility
Designed and approved to install plug-ins LIVE = zero downtime
Extruded Aluminum Housing Chassis - 100% earthing capability
Additional earthing and double size neutral provision if required
Unique Paddle Head Design
Starline has the simplest and most reliable power
take off in the industry. Just one soldered
connection from the copper conductors to the plugin unit
T5 Paddle Head
StarLine Unique Joint Design
Copper blades are seated into
U-Shaped female busbars
• Creates a maintenancefree joint
• No bolted joints in
system
• No specialist team
required to install the
system
Housing couplers are used for
mechanical strength and to
carry the ground through the
aluminum housing
Installation Video Web Link (including how to join the bus
way) http://www.uecorp.com/busway/content.aspx?f=videos
Power monitoring
Power monitoring with Starline
 Individual circuit and row power monitoring insures no
overloads
 The DCM can store historical data to prove customer
overloads and defend SLA claims
 Monitoring alarms in place for throw-over scenario's
preventing overloads during redundant circuit failovers
(i.e. continuously sum A & B circuits)
 Wire free implementation reduces connectivity costs and
allows remote configuration for the end user i.e. own
secure portal to their data only
Plug-in Monitoring/Metering
End Feed Monitoring & Metering
Global Accreditations/Listings
•
•
•
•
•
•
•
•
ISO9001
IEC
CE
VDE
UL
NORMAS OFICIALES MEXICANAS
CCC
And others
Benefits Summary
• Flexible, reliable and efficient
• Continuous access slot allows high
density and maximum flexibility
• Maintenance-free product
• Fully customisable (plug –ins & bus bar)
• Faster installation (reduced labour)
• Reduces risk of human error
• Easiest plug-in installation
• Reusable
• Ease of Design/Layout
• Reduces Op Ex Cost & Risk
Thank You!