Updates from 14 Smart Grid Pilot Projects

Smart Grid Updates: Pilot Projects in India
Telangana Southern Power Distribution Company Limited, Telangana (formerly Andhra Pradesh
Central Power Distribution Company Limited, Andhra Pradesh)
Project Area: Jeedimetla Industrial Area
Number of Consumers: 11,904
Functionality covered: AMI R, AMI I, PLM, OMS, and PQM
Consultant: CPRI
RfP Status: Released on May 23, 2014
Project Update: Pre-bid was held on June 18, 2014 and attended by 31 prospective bidders. Bid
submission date extended twice with no bids received. Hence, fresh tender with relaxed criteria to be
released by September 26, 2014.
Assam Power Distribution Company Limited, Assam
Project Area: Guwahati Distribution Region
Number of Consumers: 15,000
Functionality covered: AMI R, AMI I, PLM, OMS, and PQM, DG
Consultant: Medhaj Techno Concept Pvt. Ltd.
RfP Status: Released on March 4, 2014
Project Update: RfP was released on March 4 2014. Three bids were received and opened on July 16,
2014. Bidders are: (1) AMI Tech + HPL Meters + IBM; (2) EMC + RF Array + SPANCO + L&T Meters and
(3) Rebenius + AToS + SaaS + Siemens. Technical evaluation is in progress.
Chamundeshwari Electricity Supply Corporation Limited, Mysore, Karnataka
Project Area: Additional City Area Division, Mysore
Number of Consumers: 21,824
Functionality covered: AMI R, AMI I, PLM, OMS, and PQM, DG/MG
Consultant: PGCIL for Project Management
RfP Status: Released on October 3, 2013. Project awarded on 30 April, 2014
Implementing Agency: Consortium led by Enzen Global Solutions Pvt Ltd
Project Update: Network survey has commenced – 14 feeders under process.
Chhattisgarh State Power Distribution Company Limited, Chhattisgarh
Project Area: Siltara – Urla area of Raipur District
Number of Consumers: Around 1,900
Functionality covered: AMI I, PLM
Consultant: PGCIL
RfP Status: NIT issued. Awaiting bids.
Project Update: NIT was issued on March 1, 2014. Pre-bid held on August 2, 2014. Extended bid date to
September 26, 2014.
Electricity Department of Government of Puducherry
Project Area: Division 1 of Puducherry
Number of Consumers: 87,031
Functionality covered: AMI I, AMI R
Consultant: PGCIL
RfP Status: Not Released
Project Update: RfP yet to be finalized since the funding approval by Puducherry Government is
awaited.
Himachal Pradesh State Electricity Board Ltd, Himachal Pradesh
Project Area: KalaAmb
Number of Consumers: 650
Functionality covered: AMI I, PLM, OMS, and PQM
Consultant: PGCIL
RfP Status: NIT issued on May 23, 2014
Bidders: LnT, Wipro, Alstom, Sumaro, AMI
Project Update: NIT issued on May 23, 2014. Pre-bid meeting was held on June 16, 2014. Part one
opened on August 25, 2014. 5 bids received. Technical evaluation in progress.
Jaipur Vidhyut Vitaran Nigam Ltd, Rajasthan
Project Area: VKIA Jaipur
Number of Consumers: 34,752
Functionality covered: AMI R, AMI I, PLM
Consultant: PGCIL
RfP Status: Not Released
Project Update: RfP prepared. Board approval awaited.
Kerala State Electricity Board, Kerala
Project Area: Selected Distribution Section offices spread over the geographical area of Kerala
Number of Consumers: 25,078
Functionality covered: AMI I
Consultant: None
RfP Status: Released on December 18, 2013
Bidders: Bids were opened on March 7, 2014. Only two companies (L&T and EDMI) submitted bids.
Project Update: Price bids opened on June 28, 2014 revealed an increase of 219% from estimated cost.
Decision to be taken by utility board either to change scope or go for retender.
Maharashtra State Electricity Distribution Company Limited, Maharashtra
Project Area: Baramati Town
Number of Consumers: 25,629
Functionality covered: AMI I, AMI R, and OMS
Consultant: None
RfP Status: Released on October 28, 2013
Bidders: Four Bids received: Wipro + Alstom, L & T, Ami Tech + OSI Inc, and Rubenius.
Project Update: Revised DPR was submitted. Since lowest bidder was nearly 90% higher than the
estimated cost, a note is under process for decision with the management. Final decision will be taken
soon.
Punjab State Power Corporation Limited, Punjab
Project Area: Industrial Division of City Circle Amritsar
Number of Consumers: 9,818
Functionality covered: OMS
Consultant: PGCIL
RfP Status: Released on June 12, 2014
Project Update: RfP released on June 12, 2014. Pre-bid meeting was held on July 2, 2014. Tender
openings were extended twice and on September 12, 2014 one bid was received. 3 bids were received and
opened on 12 Sep 2014. 1) Chemtrol, 2) Kalkitech, 3) Genus. Likely to award by Oct 1 2014.
Tripura State Electricity Corporation Limited, Tripura
Project Area: Electrical Division No.1 of Agartala town
Number of Consumers: 46,071
Functionality covered: AMI I, AMI R, PLM
Consultant: PGCIL
RfP Status: NIT floated on May 17, 2014.
Bidders: 3 bids were received: TCS, Wipro, Rubenius
Project Update: Pre bid was held on May 23, 2014 and 9 parties participated. First stage bid opening was
on July 28, 2014 and 3 bids were received 1) TCS + L+G 2) Wipro + JnJ Pwercom 3) Rubenious.
Uttar Gujarat Vij Company Limited, Gujarat
Project Area: Naroda of Sabarmati circle and Deesa of Palanpur circle
Number of Consumers: 39,422
Functionality covered: AMI I, AMI R, and OMS
Consultant: None
RfP Status: Released on September 11, 2013
Bidders: Five valid bids received: Infosys + CGL; Wipro + JnJ Powercom Systems; L&T + EDMI; Reliance
+ Accenture; and Tapesh Energy + Corinex
Project Update: Revised price bids were submitted on July 15, 2014. PoC data monitoring has
commenced from August 1, 2014. Price bid expected to be opened in October 2014.
Uttar Haryana Bijli Vitran Nigam Limited, Haryana
Project Area: Panipat City Sub-division
Number of Consumers: 31,914; revised to 11,000
Functionality covered: AMI I, AMI R, and OMS, SCADA/DMS
Consultant: None
RfP Status: No RfP would be released
Project Update: Pre-feasibility study has been completed and presented to MoP on August 2014. UHBVN
and MoP approved the prefeasibility study. NEDO floated tender in Japan for Detailed Feasibility Study
cum Project Implementation. Expected to be finalized by end of October 2014 and work to start from
November 2014.
West Bengal State Electricity Distribution Company Limited, West Bengal
Project Area: Siliguri Town in Darjeeling District
Number of Consumers: 4,404
Functionality covered: AMI I, AMI R, and PLM
Consultant: PGCIL
RfP Status: To be released by 3rd week of July, 2014
Project Update: Pre bid to be held on September 26, 2014. Last date for submission of bid is to be
October 14, 2014. First stage bid opening is scheduled for October 17, 2014.
Abbreviation
Functionality
AMI R
Advanced Metering Infrastructure- Residential
Consumer
AMI I
Advanced Metering Infrastructure-Industrial Consumer
OMS
Outage Management System
PLM
Peak Load Management
PQM
Power Quality Management
MG
Micro Grid
DG
Distributed Generation