Pilot Treatment Plant Along RBOD System

PAKISTAN
WATER AND POWER DEVELOPMENT AUTHORITY
Web Matter for Updating of WAPDA
Website
Installation of Pilot Treatment Plant Along
Right Bank Outfall Drain (RBOD) System
JANUARY 2015
PROJECT DIRECTOR
INSTALLATION OF PILOT TREATMENT PLANT
ALONG RBOD SYSTEM WAPDA DADU
Installation of Pilot Treatment Plant Along RBOD System
1. Project Background
Pakistan's economic potential is unlimited due to its strong agricultural base, human
resource, its climate and geographic position but water might be one serious
bottleneck to its growth. Therefore, we need a paradigm shift and should focus on
water conservation and management approach to fulfill the needs of growing
population.
Considering water scarcity in the Country, the Drainage Effluent of Right Bank
Command Area of Sukkur and Guddu Barrages is about 750,000 acres ft. which
should not be wasted or disposed of unutilized into the sea/ lake. It has to be used
as such or after treatment for drinking, agriculture, fisheries or other economical
uses.
In recognition of this need, WAPDA under the directions of the President of Pakistan
carried out Feasibility Studies through Consultants during Year 2009 and 2010 for
treatment and reuse of RBOD effluent.
In the feasibility study, the Consultants proposed installation of Treatment Plants
along RBOD system so that the hazardous base flow of RBOD Effluent can be
treated for its various uses. As first step, a Pilot Treatment Plant at RD + 93 of
MNVD (RBOD) will be installed. Location map of the Pilot Project site attached vide
(Figure-I).
During a presentation on May 18, 2010 at Karachi, the President of Pakistan
appreciated the initiatives introduced by WAPDA regarding water conservation
strategy through reutilization plan for RBOD effluent and approved the plan for
Installation of Pilot Treatment Plant Project. PC-1 of the Project prepared by WAPDA
was approved by the ECNEC in its meeting held on 26.05.2011 at the rationalized
cost of Rs 3353.373 Million subject to availability of foreign funding.
2. Salient Features
Project Location
Type of Plant
Design Capacity
Area to be benefited
Access Road
Link Channels
Structures
• Cross Drainage Culverts
• Aqueduct
• Culverts across Link Channels
• Water Distribution Tank
Electricity Network
Project Cost
Project Annual Benefits
Project Annual O&M Cost
B/C Ratio
EIRR
Plant will be installed on left side of MNVD
at RD + 93 in Johi Tehsil of District Dadu
Pellet Extraction + RO
40 (+ 15%) cusecs
10,984 acres
6.25 miles
49,600 ft.
25 Nos.
01 No.
06 Nos.
01 No.
15 km long HT Line
Rs. 3353.373 M
Rs. 643.680 M
Rs. 237.000 M
1.18 : 1
15.06%
3. Project Objectives/Benefits
4.
Provide 28958 Acre ft of water for irrigation of
10,984 acres of land.
Availability of 20 lac gallons per day of potable
water for about 05 lac of local populace
residing in Dadu, Johi Towns and adjoining
villages of Project area.
Extraction of salts as byproduct which covers
about 50-60% of the O&M cost.
Conservation of Ecology of Manchar Lake by
treating hazardous effluent of RBOD.
Socio-economic uplift and poverty reduction.
Updated Progress
The First Stage Bids for EPC Contract submitted by pre-qualified Bidders were
opened on March 13, 2014 at WAPDA House, Lahore. The evaluation is under
process for approval by competent authority.
The EPC Contract will be ready for award during 3rd Quarter of Year 2014-15.
The Tender Documents for construction of Access Road upto Plant Site have been
completed by the Project Consultants.
The Project Consultants have also submitted the draft design report for infrastructure
Development Component.
The construction of residences and offices for the Pilot Project has been completed.
The Gazatte Notifications under Section-4, 6 & 17 of Land Acquisition Act for the land
required for Pilot Treatment Plant area have been issued.