Annexure-PFR - Environmental Clearances

PRE FEASIBILITY REPORT
____________________________________________________________
FOR
Proposed Silica sand and Quartzite Mine over an Extent of 174.83
Hectares,
In Sy. No.894 of Uppaluru Village, Muddanur Mandal,
Kadapa District, Andhra Pradesh
____________________________________________________________
Submitted To
Ministry Of Environment And Forest, GoI,
New Delhi.
Submitted By
________________________________________________________________________________
SHAIK JAMAL VALI
Farm House,RTP Road, Near D.N.Palli Village,
Muddanu , Kadapa (A.P).
PRE-FEASIBILITY REPORT
1.0
INTRODUCTION
SHAIK JAMAL VALLI , has applied for grant of mining lease for Silica Sand and
Quartzite over an extent of 174.83 Hectares in Survey Nos. 894 of Uppaluru Village,
Muddanuru Mandal, Kadapa District of Andhra Pradesh. Based on the recommendation
of the Director of Mines and Geology, the Government of Andhra Pradesh has proposed
to grant Mining lease for quartzite/ Silica sand with a request to submit the approved
mining plan vide GOVT. Memo No 19367 / MIII(1)/2007-1, dated: 16.12.2008. For this
purpose a mining plan has been prepared and obtained approval from Joint Director of
Mines & Geology, Cuddapah Zone vide their approval letter no. 918/MP – YGL/2009
Dated 09/02/2009. Lessee proposes to produce Silica Sand and Quartzite @ 31151 tonnes
per annum and the mining activity will be opencast manual mining without using drilling
& blasting. The total cost of the project is 51.50 Lakhs only
1.1
OBJECTIVE OF THE STUDY
To know the feasibility of the project, study is being worked out for which lessee applied
for the grant of lease to mine 31151 TPA of Silica Sand and Quartzite.
1.2
SCOPE OF THE STUDY
•
Cost of Project
Total investment in this project by the applicant will be around Rs. 51.50 Lakhs
•
Availability of land
The mining operations will be within the proposed ML area of 174.83 Ha, for which the
lessee has obtained necessary approvals from the consented depts.
1.3
MINING PROCEDURE
Mining is being worked by manual opencast method by using drilling & blasting. The
Mining operations are proposed by forming of 3.0m height bench by forming 2slices of
1.5m height each from 260 MRL.
1.3.1
Reserves & Life of Mine
•
Estimated Mineable Reserves
: 42,63,894 tons
•
Expected average rate of production/year
: 31151 TPA
1.3.2
Extent of Mechanization
Elaborate mechanization need not be required, because all the mining operations would
be manual, mechanization is thus limited to drilling of shot holes of blasting by using
jack hammer drills powered by portable air compressor.
The mine will be operated by manual opencast method by using jack hammer drilling and
blasting will be done by using slurry explosives & detonators.
1.3.3
Waste Generation
Here the waste will be in the form of removal of top skin on the mineral and fine sand
with silty soil which is around 10% that generates during the recovery of Mineral
i.e. 3115 TPA of mineral waste is expected
1.3.4
Use of Minerals
The Silica Sand and Quartzite produced from this mine will be sold to local & non local
buyers. There is no proposal for mineral beneficiation.
1.3.5
Transportation
Trucks will be hired for transporting ore to the buyers point.
1.3.6
Site Services
Office Canteen, Rest shelters, Drinking water & medical facilities, transport and other are
proposed to be constructed in the designated area of 10m2.
1.3.7
Employment Potential
The strength of employees would be around 24
1.4
PROJECT DEVELOPMENT AND EXECUTION
1.4.1
Resources Required
•
Man Power
Mostly the labors will be recruited from weaker section of the local surrounding area.
•
Land Requirement & Land use pattern
The land use pattern for the mine lease is given in Table-1.
Table – 1
Land use pattern of ML Area
Sr. No. Type of Land Use
Area of Land use (Ha) As at the
end of planned period of 5 years
1
Area Occupied by the proposed working
1.456
2
Area Occupied by waste dump
0.34
3
Area Occupied by afforestaion
0.15
4.
Area Occupied by site services
0.003
5.
Area Occupied by magazine building
0.001
6.
Area Occupied by stack yard
0.09
7.
Remaining area
Total
172.79
174.83
The remaining area of 172.79 Ha. is used for future purpose
•
Water Requirement
Water consumption is around 10.0 m3/day. The ground water will be drawn from bore
well for water requirement
•
Permits Required
1.
Consent for Establishment form the State Pollution Control Board
2.
Environmental clearance needs to be obtained.
1.5
FINANCIAL FEASIBILITY
Capital investment for Mining and Environmental Management
(Environmental Control, Social Development, etc.)
: Rs. 51,48,750
Say 51.5 Lakhs
Consideration of per ton working cost is given below:
Recurring Cost (Rs./MT)
Expenditure on cost of mining
Expenditure for socioeconomic development
Expenditure for Occupational Health and Safety
Expenditure for Environmental Management
Total
: Rs. 744
: Rs. 25.8
: Rs. 18.0
: Rs. 48.0
: Rs. 835.8/-
Value of Mineral at Pit head
: Rs 1000/MT
Gross profit before interest
Interest on investment of assets @ 14% per annum
Depreciation of assets @ 10%
Operating profit
Provision for taxation @ 30%
Surcharge @5% of tax
Net profit after Tax
: Rs. 164.2
: Rs. 22.4
: Rs. 16.0
: Rs. 125.8
: Rs. 37.7
: Rs. 1.8
: Rs. 86.3/MT
Net profit/annum for 31151 Tonnes
: Rs.26.9 lakhs
The details of capital and recurring expenditure are given in following Table:
Activities
Area of Investment
Capital Investment
i
land
a. Land cost expenditure
Budget for proposed mining
Method of calculation
Entire area is a govt. waste
land and no amount is required
to pay
b. Cost on relief and rehabilitation action
plan
c. Compensation to the land ouseets
ii.
iii.
iv.
Basics
Area : 174.83 ha Govt.
waste land
Rehabilitation not
required
No land oustees
d. Cost of acquiring Surface Rights
Mining
a. Cost for infrastructure & equipments
Environmental Protection
a. Pollution Control (check dam, gully plug, retaintion wall, settling tank, water tanker, etc.)
Check Dams
2 Nos. (15 m x 2.5m x 1.5 m)
@ Rs. 2000/- per cum
Gully Plugs
6 Nos. (5 m x 1.5 m x 1.5 m)
@ Rs. 500/- per cum
Retention Wall
140 m x 3 m x 2 m
@ Rs. 500/- per cum
Water Tanker
2 No. (Hire)
@ Rs. 10000/- deposit per
tank
Socio-economic Development
a. Infrastructure development (Edu., Medical, etc)
i. Educational facilities
Rs. 2 lakh per village x nearby
2 villages from project site
ii. Medical facilities
Rs. 2 lakh per village x nearby
2 villages from project site
Expenses (in Rs.)
0
0
0
0
0
25,00,000
25,00,000
6,98,750
6,98,750
225,000
33,750
420,000
20,000
14,50,000
12,00,000
4,00,000
4,00,000
iii. Others
b. Income Generation Activities
v.
Occupation Health & Safety
Infrastructure & PPEs
Total Capital Investment
Rs. 2 lakh per village x nearby
2 villages from project site
4,00,000
Nearby 2 villages
2,50,000
500,000
500,000
51,48,750
Say Rs. 51.5 lakhs
Activities Area of investment
Budget for proposed mining
Method of
Basics
calculation
Recurring Expenditure
i.
Mining
a. Expenditure for infrastructure
and equipment maintenance
b. Salaries & Wages of 24 staff
No. of workers x
Wages
c. Royalty on Mineral &
Miscellaneous Exp
d. Ore transportation cost
Rs. Per Ton
ii.
Socioeconomic Development
a. Crop Damage Compensation
b. Corporate Social
5% on capital
Responsibility
investment
c. Income Generation Activities
Nearby 2 villages
d. Community Health checkup
iii
Occupational Health and Safety
a. For routine checkup
24 Persons x budget
per annum
b. Medical aid as under ESI
1.7% of basic salary
scheme
/ employee
c. Budget for training
d. Compensation for accident
Rs 50000 x
and injuries
Anticipated rate of
injuries (No. of
20 % of direct
investment for
infrastructure &
maintenance
Rs. 12000 per month
Expenses (in
Rs.)
Cost per ton (in
Rs.)
10,30,000
744
33.0
34,56,000
111.0
Rs. 100 per ton
100.00
Rs. 500 per ton
500.00
25.8
6.4
8.2
2,00,000
2,57,500
Nearby 2 villages
Budget Rs. 10000/- per
annum
Basic salary Rs.
6000/PM
Anticipated rate of
injury : 5%
2,50,000
100,000
2,40,000
8.0
3.2
18.0
7.7
29,376
0.9
2,00,000
100,000
6.2
3.2
workers)
iv.
Environment Management
a. Maintenance of Pollution
Control Facilities
b. Dust Suppression & Pollution
Control
c. Environmental Monitoring
d. Environmental division
Total Recurring Expenditure
5,00,000
48.0
16.0
5,00,000
16.0
4,00,000
1,00,000
12.8
3.2
835.8
Say Rs. 836/-
2. ANALYSIS OF PROPOSAL
SHAIK JAMAL VALI, is proposed for annual production of 31151 Tonnes of Silica
sand and quartzite. The financial estimates reveal the rate of returns. The project is
economically viable. The estimates have also taken into consideration the occupational
health expenses, environmental protective measures, social welfare activities etc., The
Form-I and Mining Plan are submitted with this document.
SHAIK JAMAL VALI ,
S/o S.Ibrahim Saheb,
Farm House,RTP Road,
Near D.N.Palli Village
Muddanur Mandal,
Kadapa (A.P).