Moray Offshore Renewables Limited

Moray Offshore Renewables Limited
MORL Speed Update
Aberdeen, January 2014
Moray Offshore Renewables Limited
MORL’s first projects are in the EDA – Telford, Stevenson and MacColl
Key Project Characteristics
• Submitted for consent for 1500 MW in August 2012 (consent expected Q1 2014)
• First project will be around 500 MW in p j
2018 (CAPEX ~£1.8 billion)
• WTGs to be between 5‐8 MW capacity
Key Challenges to FID
• CfD availability and UK Government capacity definition
• Consents‐maintain the advantage as an early mover
• Grid (delivery timescales)
• WTG selection (shortlist February 2014)
• Route to Market (PPA)
<<MORL Engineering Activities 30‐01‐2013>>
2
MORL Programme
Key Workstreams to maintain FID in Q4 2015 and First Generation in 2018
Q4
2013
Q1
2014
Consent Determination
Q2
2014
Q3
2014
Q4
2014
Q1
2015
Q2
2015
Remuneration Certainty
Q3
2015
Stage Gate 3
FID
Final Economic Model
Bank Engagement/ Insurance/ Economic Model
Management Contractor
Pre‐FEED
25‐50 Geotech
Boreholes
WTG Shortlist – 4/5 Turbines Q2
2016
Q3
2016
Q4
2016
FEED
Balance of Geotech
Contract Award – based on lead time drivers:
Offshore AC SS: up to 32mo.
WTGs: up to 36mo.
SS/GBS: up to 25mo.
Critical Path
WTG Selection
WTG Shortlist – 2/3 Turbines
Turbines Scoping
Q1
2016
Project Process
Engineering Evolution WTG Procurement
Grid
Offshore Metmast
Offshore Metmast
Stage Gate 2
WF Layout
Q4
2015
Commercial Negotiations & initial fabrication
g
Offshore Studies
Final Land Acquisition
AC St d
AC Study
C bl R t S
Cable Route Survey
OMM Installation
1 Year Data
2 Years Data
OMM Design, Fab. & Transp.
<<MORL Engineering Activities 30‐01‐2013>>
3
MORL Key 2014 Milestones
Critical path items to maintain FID date and increase the probability of successful award of a CfD
The following actions have been prioritised for MORL (and, where applicable, in conjunction with ICOL) in the period January 2014 to April 2014:
conjunction with ICOL) in the period January 2014 to April 2014:
• Secure offshore consents for MORL eastern development area (Q1 2014)
• WTG shortlist: reduce shortlist to 2 manufacturers (by 14 February 2014)
WTG shortlist: reduce shortlist to 2 manufacturers (by 14 February 2014)
• Final layout/capacity definition for first MORL project (February 2014)
• Detailed geotechnical investigation (to commence May 2014)
• Install offshore met mast (June 2014)
• Substructure selection (June 2014)
WTG selection (July 2014)
• WTG selection (July 2014)
• Supply Chain Plan submission (July 2014)
• CfD Application (Q4 2014)
(
)
<<MORL Engineering Activities 30‐01‐2013>>
4