SuDS Case Studies from the Construction Industry

SuDs Management
at Glenconway
Windfarm
SuDS
Introduction to
Gael Force Renewables
SuDs
• Gael Force Renewables Ltd was
formed in 2011 by McLaughlin &
Harvey Ltd and William & Henry
Alexander (Civil Engineering) Ltd to
target onshore Wind Farm
opportunities in GB & ROI.
SuDs
Gael Force Renewables – What We Do:
•
150 years of Civil Engineering Experience
•
Gael Force offer full Design and Build Services
•
Early client and designer involvement so that innovative, safe, buildable solutions are developed.
•
At Gael Force we implement lessons learnt to ensure our teams constantly progress, develop and
refine skills, methodologies and work sequences
•
Full time on site Environmental Professionals
SuDs
Project - Balmurrie Fell Wind Farm,
Stranraer, South West Scotland.
(7 x 1.3 MW Siemens WTG)
SuDs
Project – Glenconway Windfarm,
Limavady, Northern Ireland
(20 x 2.3MW WTG)
SuDs
Design to Construction
SuDS
Settlement Ponds
SuDS
Silt Fencing
SuDS
Clean water cut off drains
SuDS
Swales & check dams
SuDS
Breakouts
SuDS
Settlement Areas
SuDS
Monitoring Effectiveness
• Water Quality testing (internal & external)
• External inspections by Designers
• Internal weekly inspections by
Environmental Representative
• SEARS (Safety Environmental Awareness
Reporting Scheme). Positive and Negative
issues raised by everyone on site.
SuDS
SuDS
Water Quality Testing
• External water quality testing was carried
out every two weeks at 5 locations for Phase
1 and 8 locations for Phase 1 & 2
• Testing covered 21 chemical parameters and
biological (macro invertebrate) monitoring
• Internal samples took place daily for phase 1
and weekly for phase 2. Parameters
included turbidity, dissolved oxygen, pH,
temp & EC.
SuDS
Environmental Awareness
• Water Quality results are displayed on
site
• Correlation between turbidity and
rainfall is also presented on graphs.
SuDS
Toolbox Talks
• Every Tuesday
morning
• Covers key issues
such as waste,
energy, water
pollution
• All site staff
shared the
responsibility
SuDS
Environmental Awareness
SuDS
Environmental Coaching
Environmental
Sessions to date:SuDS (McCloys)
Peat Stability /
Peat Slides (BLP)
Archaeology
(Gahan & Long)
Flora and Fauna
(Blackstaff)
SuDS
SuDS
Conclusion
• SuDS design must account for inclement weather
conditions
• SuDS design must be site specific
• SuDS features must be installed prior to works
starting
• Very beneficial to have an on site environmental
representative
• Water Quality monitoring is important during
construction – even visual inspection of water
courses
• Maintenance of SuDs Features is critical
SuDS
Construction-Phase Temporary SuDS: A75 Case Study
Richard Collins BSc MSc AIEMA
Construction Context
•
•
•
3.67km carriageway realignment and upgrade:
include earthworks, drainage and culverts, utility
works, surfacing & underpass construction
Existing drainage mitigation inadequate
Filter drains & 4 balancing ponds with reed beds
Key Environmental Aim
‘Protecting the Pow Water tributaries during
construction’
Challenges & Uncertainties
•
Geology & soils

Earthworks intensive

EIA stated ‘potentially increased sedimentation’

True nature of soils
Fine Clays
•
Spatial constraints
 Limited opportunity for temporary SuDS
locations
•
Temporal Constraints

Not scheduled in programme of works

Resources to complete with immediate effect

Costs
Usual Suspects






Exposed soils: ensuring capping/seeding is
completed ASAP
Stockpiles: limiting, stabilising
Washing & washout facilities
Haul roads: wheel wash operative (spatial
constraints)
Dewatering: sumps, releasing at suitable times
Inclement weather: be prepared
Water Management Strategy

Liaise with local SEPA representative

Alum sulphate required: minimal dosing policy

Tiered, impermeable treatment zones

Maintenance plan: Daily checks

pH (6-8) & turbidity (<10ntu) testing

Controlled release
Tangible Results
Permanent Pond Installation
• Isolated pond
• Limited opportunity for
treatment
• Use of existing vegetation
• Lined sediment forebay
• Aquatic bench in
permanent pool;
ecology, amenity &
safety
Native Species Planting
Pond Edge Mix
Yellow Flag Iris
Water Avens

Meadowsweet
Benefits of bio-retention and enhanced biodiversity
Learning Points
Detailed pre-construction review of EIA
Robust planning, management & maintenance
required
Micro-managed retention & release
Maximise use of sub-catchments in design
Thank you