< Reference > January 27, 2014 Tokyo Electric Power Company Fukushima Daiichi NPS: Progress Status of Construction of Seaside Water Impermeable Wall 1. Progress status of seaside water impermeable wall (as of Jan. 26) Leakage preventing rubber plate Steel pipe sheet pile ① In Construction Zone No. 1 (inside the port), - Installation of steel pipe sheet piles: 395 piles completed (out of a total of 404) - Application of treatment to joints: 293 joints completed (out of a total of 404) ② In Construction Zone No. 2 (outside the port), - Installation of steel pipe sheet piles: 139 piles completed (out of a total of 191) 東 波 除 堤 East breakwater embankment Joint part Filling of mortar (treatment applied to a joint) Illustration of treatment that is applied to a joint Mooring post Construction Zone No. 2 (outside the port) Construction Zone No. 1 (inside the port) #4スクリーン・ポンプ室 #4取水電源ケーブルダクト #4取水電源ケーブル管路 置き換え路盤材40-0 電気室 栽培漁業センター #4海水配管トンネル Legend: Installation of steel pipe sheet piles completed Application of treatment to joints completed #4海水配管ダクト(SW系) スロープ5% 路盤材40-0 敷き鉄板 #4循環水管基礎 #4復水 貯蔵タンク #4逆洗弁室 #4共通配管ダクト Reclamation completed #4薬品タンク連絡ダクト 1 2. Sequence of reclamation inside the port The subject area was divided into blocks, and underwater concrete installation and reclamation has been started from the northernmost block and is currently underway. 東 波 除 堤 Inside the port, - Underwater concrete: Approx. 900m3 completed (out of a total of approx. 3,300m3) (as of Jan. 26) - Reclamation material (rubble stones): Approx. 2,500m3 completed (out of a total of approx. 41,000m3) (as of Jan. 26) B C D E F G A #4スクリーン・ポンプ室 #4取水電源ケーブルダクト #4取水電源ケーブル管路 置き換え路盤材40-0 電気室 栽培漁業センター #4海水配管トンネル The construction is currently being conducted in the Blocks A and B area. #4海水配管ダクト(SW系) スロープ5% 路盤材40-0 敷き鉄板 Reclamation of this part is to be conducted after the installation of 9 steel pipe sheet piles, which has been interrupted for now. #4循環水管基礎 #4復水 貯蔵タンク #4逆洗弁室 #4共通配管ダクト #4薬品タンク連絡ダクト 2 3. Scheduled reduction of the number of seawater monitoring points following reclamation work The number of seawater monitoring points will be sequentially reduced in accordance with the progress of the reclamation work for the seaside water impermeable wall. A monitoring point will be added in a location near the center of the open conduit of the Units 1-4 intake channel in the north-south direction. To be retained in place To be retained as a monitoring point To be used from around May Until the completion of steel pipe cofferdam To be installed in late Feb. Until mid or late May Until early or mid Apr. Outside: To be used from late Feb. Outside: Until early Mar. Inside: Until mid or late Jun. Outside: Until Jan. 31 Inside: Until mid or late Mar. Until mid or late Feb. To be removed on Jan. 31 To be removed in early Feb. To be removed in late Feb. Outside: Until early Feb. Inside: Until late Apr. or early May To be removed in early Mar. Until the completion of steel pipe cofferdam Inside and outside: Until the completion of steel pipe cofferdam To be removed after the completion of steel pipe cofferdam * The schedule is subject to change depending on the progress status of the work. Silt fences to be removed or newly installed Measurement points for seawater monitoring to be excluded or added Outside: Outside the silt fence Inside: Inside the silt fence Measurement points for gamma, gross-beta, and H3 densities. Measurement points only for gamma densities 3
© Copyright 2024 ExpyDoc