Timeline for the Subsidy Program for
Projects Promoting Asian Site Location in Japan (Provisional)
28th~
Oct
Nov
Jan
2013
Dec
2012
Aug
Note: Schedule is subject to change.
Announcement of Subsidy Application
Application Period(84 days)
5th~ 19th
Period for Acceptance of Application Forms
(no later than 12:00 p.m. Japan Time)
late Dec. to
early Jan.
Notification of the Screening Results
Be aware that you cannot undertake the site setup before the notification of grant determination has been issued !
Grant Application
Notification of Grant Determination
Sep
Oct
・・・・・
2014
Site Setup
End of Subsidized Project (Completion of the site)
Submission of the Subsidy Project Result
Project investigation, Determination of the Subsidy Amount
Payment of the Subsidy
Report on Regional HQ Site/R&D
Site project for 3years,
Application for approval of asset
disposal, etc.