Halton Regional Police Service New Headquarters Design Project Trust & Respect Integrity Accountability Excellence Teamwork Presentation to Police Services Board November 27, 2014 Progress Through Participation Justice Background / Status • September 2013 – Board authorized HRPS Staff to determine Regional ability to fund the construction of a new HRPS Headquarters. – • • Based on Stantec Architecture Feasibility Study In 2014 – April – Rebanks Pepper Littlewood Architects Inc. (RPLA) retained as Prime Consultant – April – Facilities Plan Update presented to PSB – October – 10-Year Capital Forecast approved by PSB (including New HQ and 1 District) Today’s meeting – Present current design findings for HQ – Present Total Project Cost based on Class B (+/- 10%) construction cost estimate – Solicit approval to proceed to Regional Council (January 2015) 2 New HQ Building Overview • Planning horizon = 25 years • To accommodate all HQ Administrative units and select operational units • Consolidate all evidence control functions (supporting best practices in evidence management) • Centralize training (supporting more efficient training deployment) • Appropriate upgrades to technical spaces for speciality units, such as : • Forensic Labs • Evidence storage • Training rooms and ammunition storage • Supports 20 & 30 Division facilities for long term growth • Project Site has been revised to include lands to the South 3 Contribution to the Long Term Facilities Plan Are we still generating the same benefits as we expected? YES Accelerates phasing of Central Services Facility (CSF) Extends planning horizon for HQ (from 10 years to 25 years) Operational and space use efficiencies in combined HQ / CSF Geographic centralized site location Relocates bureaus from 20 & 30 Division which provides space proportionate to growth envisioned in 2011 BPE Maintains proximity of HQ with regional services Safety Village remains in existing location Funding efficiencies from land donation and funding approach Able to satisfy parking needs (public and secure) Evidence control functions into single site (custody, audit) Eliminates challenge of finding suitable site for CSF 4 Massing Model – Feasibility Study 5 Site Plan - Feasibility Study 6 Site Plan - Design Project 7 Building Orientation 8 New HQ Design 9 New HQ Design 10 New HQ Design 11 Building Size – Feasibility vs. Current Design Program Area Feasibility Current Study Design Comments Usable area above grade Administration Command / Chief's Staff / HRPSB 12,009 13,303 Operations RID / FIS / ESU / Traffic 19,729 27,700 Increased garage spaces Support Services CPS / SS / IT / CS / HR & Training / Range 79,824 57,447 CPS restructured; smaller spaces Common Areas Public Lobby/Community & Media Room Staff Amenities Shared Meeting rooms / unfinished space Washrooms, stairs, service rooms corridor 5,340 16,664 2,310 28,274 5,942 21,776 3,070 31,300 164,150 160,538 25,350 28,709 2,300 4,349 27,650 33,058 191,800 193,596 17,900 36,804 209,700 230,400 Subtotal Usable area below grade Vehicle parking Workshops/ Storage Fleet / IT / RID Subtotal Total Usable Area Building Ancillary Mechanical/Electrical Total Building Gross Floor Area (sq ft) 12 Building Size – Feasibility vs. Current Design Program Area Feasibility Current Study Design Comments Usable area above grade Administration Command / Chief's Staff / HRPSB 12,009 13,303 Operations RID / FIS / ESU / Traffic 19,729 27,700 Increased garage spaces Support Services CPS / SS / IT / CS / HR & Training / Range 79,824 57,447 CPS restructured; smaller spaces Common Areas Public Lobby/Community & Media Room Staff Amenities Shared Meeting rooms / unfinished space Washrooms, stairs, service rooms corridor 5,340 16,664 2,310 28,274 5,942 21,776 3,070 31,300 164,150 160,538 25,350 28,709 2,300 4,349 27,650 33,058 191,800 193,596 17,900 36,804 209,700 230,400 Subtotal Usable area below grade Vehicle parking Workshops/ Storage Fleet / IT / RID Subtotal Total Usable Area Building Ancillary Mechanical/Electrical Total Building Gross Floor Area (sq ft) Consistent with Feasibility Study 13 Building Size – Feasibility vs. Current Design Program Area Feasibility Current Study Design Comments Usable area above grade Administration Command / Chief's Staff / HRPSB 12,009 13,303 Operations RID / FIS / ESU / Traffic 19,729 27,700 Increased garage spaces Support Services CPS / SS / IT / CS / HR & Training / Range 79,824 57,447 CPS restructured; smaller spaces Common Areas Public Lobby/Community & Media Room Staff Amenities Shared Meeting rooms / unfinished space Washrooms, stairs, service rooms corridor 5,340 16,664 2,310 28,274 5,942 21,776 3,070 31,300 164,150 160,538 25,350 28,709 2,300 4,349 27,650 33,058 191,800 193,596 17,900 36,804 209,700 230,400 Subtotal Usable area below grade Vehicle parking Workshops/ Storage Fleet / IT / RID Subtotal Total Usable Area Building Ancillary Mechanical/Electrical Total Building Gross Floor Area (sq ft) Feasibility Study underestimated Ancillary 14 Cost Estimate – Feasibility vs. Current Feasibility Study Construction Funding Model Class B Median Class B 3% Low 51.3 56.1 52.8 51.2 Contingency and Cash Allowances 3.8 incl. above 3.4 3.3 Furniture, Fixtures and Equipment 1.6 1.5 1.6 1.6 IT Infrastructure 5.0 5.0 4.5 4.5 Professional Fees 5.1 3.0 3.1 3.1 Soft Costs 0.1 1.7 1.7 1.7 incl. above incl. above 1.3 1.3 - - 0.6 0.6 66.9 67.3 69.0 67.3 Land - acquired by Region - 1.8 1.8 1.8 Land - transfer from Region (non-cash) - 7.3 7.3 7.3 66.9 76.4 78.1 76.4 Difference versus Feasibility - excluding Land (2.2) (0.4) Difference versus Funding - excluding Land (1.7) 0.0 Overall Project Contingency Project Management Fee (Region) Subtotal Total Project Cost 15 Cost Estimate – Discussion • Cost consulting estimate of construction is to reflect the expected median bid amount from a competitive tender result. Minimum of four tender submissions. • Lowest acceptable bid is dependant on market conditions at the time of tender. • Currently the market looks favourable for a spring 2015 tender, with few large construction projects anticipated for early next year. • A construction tender spread between 5% to 8% would be considered normal given market conditions. • Project Steering Committee and Consulting Team believe it is a reasonable risk to expect a low bid of at least 3% below median. 16 Project Time Line • 60% Construction Documents and Class B cost estimate Nov 14, 2014 • HRPSB Presentation of Design and Funding Proposal Nov 27, 2014 • Prequalify General Contractors Dec – Jan 2015 • 90% Construction Documents and Class A cost estimate Jan 8, 2015 • Administration and Finance Committee Presentation Jan14, 2015 • Region Council Budget Approval Presentation Jan 28, 2015 • Request for Tender (prequalified GC’s) Feb thru April 2015 • Award General Contractor (lowest compliant bid) Mid April 2015 • Earliest Projected Construction Start May 2015 • Estimated Construction Duration 24 Months 17 Recommendation – Feasibility Study (Sept 2013) “That the Halton Regional Police Service Board receive the Stantec information as presented and authorize staff to move forward to determine Regional ability to fund the construction of a new HRPS Headquarters located on adjacent Halton Region Centre property to enable more effective and efficient delivery of policing services; and further, …” November 27, 2014 18 Recommendation – Design Project (Nov 2014) “That the Halton Regional Police Service Board receive the project information as presented and authorize staff to move forward to Regional Council for funding approval to construct a new HRPS Headquarters located on adjacent Halton Region Centre property to enable more effective and efficient delivery of policing services.” November 27, 2014 19 Questions?
© Copyright 2024 ExpyDoc