Application of TESLA/XFEL/ILC SRF Technology for the CW FEL

Application of TESLA/XFEL/ILC
SRF Technology for the CW FEL:
LCLS-II
Marc Ross
2014-04-14
Accelerator-IMSS-AAT Joint Seminar: LCLS-II project at SLAC
LCLS-II SRF Linac
Closely based on the European XFEL / ILC / TESLA Design
LCLS-II Linac consists of:
Component
Count
Parameters
Linac
4 cold segments
35 each 8 cavity Cryomodules (1.3
GHz)
3 each 4 cavity Cryomodules (3.9 GHz)
1.3 GHz
Cryomodule
8 cavities/
CM
13 m long. Cavities + SC Magnet
package
+ BPM
1.3 GHz 9-cell
cavity
280 each
16 MV/m; Q_0 ~ 2.7e10 (avg); 2 deg. K;
bulk niobium fine-grain sheet-metal
Cavity Auxiliary
per each
cavity
Coaxial Input Coupler; 2 each HOM
extraction coupler; lever-type tuner
Injector
1 each
1 each special cryomodule (TBD)
A-I-A Joint Seminar 140414 M. Ross
2
LCLS-II SRF Linac
•  4 GeV, 300 micro-Amp CW superconducting linac based on
TESLA / ILC / E-XFEL 1.3 GHz technology
Key topics:
•  Cavity process for high-Q0 production
•  CW cryomodule design and operations scheme for 110 W
@ 2K / CM (or better)
•  Industrial capability for 1) dressed-processed-cavity, 2)
coupler, and 3) vacuum-vessel/cold-mass production
•  Single RF-source / single-cavity
•  Jlab Cryoplant CHL-2 (12 GeV Upgrade) adapted for SLAC
A-I-A Joint Seminar 140414 M. Ross
3
LCLS-II SRF Linac
•  4 GeV ‘up to 300 micro-Amp’ CW superconducting linac
based on TESLA / ILC / E-XFEL 1.3 GHz technology
Key topics:
•  Cavity process for high-Q0 production
•  CW cryomodule design and operations scheme for 110 W
@ 2K / CM (or better)
•  Industrial capability for 1) dressed-processed-cavity, 2)
coupler, and 3) vacuum-vessel/cold-mass production
•  Single RF-source single-cavity
•  Jlab Cryoplant CHL-2 (12 GeV Upgrade) adapted for SLAC
A-I-A Joint Seminar 140414 M. Ross
4
High Q0: Fermilab-developed ‘gas-doping’ process à
Fermilab has developed a cavity processing recipe that results in high
quality factors (>3E10) at operating gradients between 10 and 20 MV/m.
This recipe is in its first phase of development and requires further
investigation to be mature enough for large project implementation.
Fermilab will lead a program in collaboration with Cornell and JLab to
bring this about.
The primary goal is to develop a reliable and industrially
compatible processing recipe to achieve an average Q0 of 2.7E10
at 16 MV/m in a practical cryomodule.
To reach this goal, the collaborating institutions will process and test
single-cell and 9-cell 1.3 GHz cavities in a successive optimization
cycle.
The deliverable is industrial capability and cost-effective
production yield.
•  To be applied to LCLS-II construction.
A-I-A Joint Seminar 140414 M. Ross
5
R&D for Optimum Q0 from Bulk Nb •  Recently discovered that surface diffusion of some foreign atomic species into Nb at high temperature seems to inhibit RF loss mechanisms that have “normally” been present. •  800°C vacuum for 3 hours is used to degas dissolved H from the niobium bulk -­‐ routine. •  ~20 mtorr nitrogen gas @ 800°C for a few minutes -­‐ new. •  Lossy nitrides on the surface are removed by light > 2 µm electropolish. •  ResulOng rf surface resistance decreases with field to unprecedented low levels (< 10 nOhm @ 2.0K, 1.3 – 1.5 GHz)= high Q0 LCLS II Cavity Processing Recipe Cavities ready for
Processing
HPR (Class 100) - 8hr
Pre-process Inspection &
Thickness Measurements
Partial Assembly(Class 10)
HPR (Class 10) - 12hr
Bulk EP (120um to 150um)
Post-process Inspection &
Thickness Measurements
1- pass HPR
Full Assembly (Class 10)
Repair Leak
Vacuum
Leak Check
(Class 10)
Fail
Pass
UHV High Temp Bake
Cavity Dressing
(helium vessel weld)
RF Tuning
HOM Notch tuning
Light EP (5-10 um)
Ship Cavity
Alcohol Rinse
A-I-A Joint Seminar 140414 M. Ross
VTA Testing
FNAL/JLab
7
A. Grassellino, SRF2013 TUIOA03
A-I-A Joint Seminar 140414 M. Ross
8
Nitrogen doping Use the temperature dependence to separate Rs components A. Grassellino, FNAL 4/11/2014 8 C. Reece
A-I-A Joint Seminar 140414 M. Ross
10
Development Work Sequence 1.  OpOmize recipe on single cell 2.  Apply to nine cells, gain staOsOcs • 
Nine cells choice: half from scratch, half reprocessed from ILC effort (want to validate full sequence including bulk removal) 3.  Study effect of cooldown on dressed and undressed caviOes in VTS 4.  (in parallel) Dress for HTS, study Q in HTS 5.  (in parallel) – study of cooldown effect (‘Thermal-­‐cycling’) on residual in CM2 Anna Grassellino, Fermilab TD
High Q0 Studies schedule:
1.  Use single-cell cavities to optimize and define protocol
2.  Apply to nine-cell cavities for vertical test
3.  and for horizontal (cryomodule-like) cryostat test
HIGH Q0 SCHEDULE
2014-­‐01-­‐20
M. Ross, SLAC
15 tests completed September 1, 2014
Y
M
D
Num. Tests
2014
J
J
13 27
Fermilab
1. N-­‐treatment N-­‐treatment pprocess rocess optimization optimization with with single-­‐cell s ingle-­‐cell cavities cavities 8
2. 9-­‐cell cavity treatments and vertical tests
8
3. Dress Dress 99 c
cell ell ccavities avities ffor or HHTS TS ccomplete
omplete
4. HTS HTS tests tests (Fermilab)
(at Fermilab) complete
3
5. Final FY 2014 report submitted
Jlab
Num. Tests / Cavities
1. Begin N-­‐treatment s ingle cpell rocess cavity optimization fab
with s ingle-­‐cell cavities 6 ◊
2. Cavity s et complete
3. Single Dress c9
ell cell parametric cavities sftudy
or HTS complete
18
4. Production HTS tests (p
at rotocol Fermilab) ready complete
for application to 9-­‐cells
5. Nine cell production processing 6
6. Final report submitted
Cornell
Num. Tests 1. Single N-­‐treatment cell tests p-­‐rocess initial optimization with s ingle-­‐cell cavities 10
2. Single cell tests -­‐ final
8
3. Nine Dress cell 9-­‐ cinitial ell cavities process
for HTS complete
4
4. Nine HTS cell tests -­‐ s econdary (at Fermilab) process
complete
2
5. HTC Tests (Cornell)
3
6. Final report submitted
A-I-A Joint Seminar 140414 M. Ross
F
10
F
24
M
10
M
24
A
07
1
2
A
21
3
M
05
M
19
J
02
3
4
6
J
16
J
30
8
◊
J
14
J
28
A
11
A
25
S
08
5
6
7
8
◊
◊
2
1
S
22
O
06
O
20
3
◊
N
03
N
17
◊
◊
3
6
9
12
15
18
◊
◊
1
2
3
4
5
6
◊
◊
2
4
6
8
10
◊
3
2
5
8
◊
4
2
1
2
3
◊
13
LCLS-II nine-cell cavity test:
Showing effect on high Q0 vs Eacc from gas-doping
A-I-A Joint Seminar 140414 M. Ross
14
TB9ACC015 – N2 doped plus 8 microns EP
test after FF tuned and with SC NbTi flanges
TB9ACC015
5.00E+10
4.50E+10
T=2K
4.00E+10
3.50E+10
Q
3.00E+10
2.50E+10
LCLS-II spec
TB9ACC015
2.00E+10
1.50E+10
1.00E+10
5.00E+09
0.00E+00
0.00
2.00
4.00
6.00
8.00 10.00 12.00 14.00 16.00 18.00
E [MV/m]
•  First nine cell proof of principle Q > 4e10 at 2K, 16 MV/m
•  Optimal amount of EP post bake yet to be found (gradient optimization) – quench at
17 MV/m, some MP x-rays, cavity will receive 5 more microns EP
LCLS-II Single 4.5 K Cold-box Cryoplant Scheme
Size limited by
transport logistics
Very close to:
Jlab – CHL2, SNS and
FRIB plant designs
A-I-A Joint Seminar 140414 M. Ross
16
Jlab CEBAF 12 GeV
Upgrade 4.5 K coldbox (Linde) ‘CHL 2’
17
Cost
Optimization:
•  Assumes tunnel
is ‘free’
•  Includes 10 yr
operations
LCLS-II is at costoptimum for given
cryoplant scheme
. Cost (arbitrary units) . LCLS-II is below 2 x 4.5 K Cryoplant cold-box threshold:
Construc5on plus 10 Year Opera5ng Cost -­‐ 2.00 K CM + RF + Controls Cryo Plant, Transfer Lines and Facility -­‐ 2.00 K 10 Yr Linac and Cryo AC -­‐ 2.00 K 450 400 LCLS-II
350 300 250 200 150 100 50 0 8 10 12 14 Eacc (MV/m) 16 18 20 2 cold-box
threshold
Model of relative LCLS-II linac cost as a function of operating
gradient, at 2 K.
A-I-A Joint Seminar 140414 M. Ross
18
LCLS-II SRF Linac
•  4 GeV ‘up to 300 micro-Amp’ CW superconducting linac
based on TESLA / ILC / E-XFEL 1.3 GHz technology
Key topics:
•  Preserving high-Q0 in a cryomodule: HTS
•  CW cryomodule design and operations scheme for 110 W
@ 2K / CM (or better)
•  Industrial capability for 1) dressed-processed-cavity, 2)
coupler, and 3) vacuum-vessel/cold-mass production
•  Single RF-source single-cavity
•  Jlab Cryoplant CHL-2 (12 GeV Upgrade) adapted for SLAC
A-I-A Joint Seminar 140414 M. Ross
19
Horizontal Test: HTS
•  Cool-down
dynamics (Tc)
•  Magnetic field
shielding
•  Coupler heating
•  Cryogenic controls
•  HOM feedthrough
•  Fermilab (HTS) /
Cornell (HTC)
A-I-A Joint Seminar 140414 M. Ross
21
Development Work Sequence 1.  OpOmize recipe on single cell 2.  Apply to nine cells, gain staOsOcs • 
Nine cells choice: half from scratch, half reprocessed from ILC effort (want to validate full sequence including bulk removal) 3.  Study effect of cooldown on dressed and undressed caviOes in VTS 4.  (in parallel) Dress for HTS, study Q in HTS 5.  (in parallel) – study of cooldown effect (‘Thermal-­‐cycling’) on residual in CM2 Anna Grassellino, Fermilab TD
Cool-down dynamics near Tc
Dependence of the residual surface resistance of
superconducting RF cavities on the cooling
dynamics around Tc A. Romanenko,∗ A. Grassellino,† O. Melnychuk, and D. A. Sergatskov
Fermi National Accelerator Laboratory, Batavia, IL 60510, USA (Dated: March 11, 2014) We report a strong effect of the cooling dynamics through Tc on the amount of trapped
external magnetic flux in superconducting niobium cavities. The effect is similar for
fine grain and single crystal niobium and all surface treatments including
electropolishing with and without 120◦ C baking and nitrogen doping. Direct magnetic
field measurements on the cavity walls show that the effect stems from changes in the
flux trapping efficiency: slow cooling leads to almost complete flux trapping and
higher residual resistance while fast cooling leads to the much more efficient flux
expulsion and lower residual resistance. Slow cooling: <0.3K/min
Fast cooling: 1.8-2.4K/
min
Understanding why: magnetic probe positioning - examples!
mG H=5mG Fluxgate magneto
meters FIG. 4. Picture of the nine cell cavity with two fluxgate magnetometer probes mounted on the equator of the second cell.
3
flux from being expelled, leading to almost complete flux
trapping, while a fast cooldown through Tc helps pushing
efficiently the flux out of the superconductor.
Also in this case, the RF performance correlated with
the previous findings, as shown in Fig. 5: fast cooldown
lead at 2 K and medium fields to Q0 ⇠ 1.5 ⇥ 1010 , and
slow to Q0 ⇠ 1.2 ⇥ 1010 . It is interesting to observe that
compared to the nitrogen baked cavity the e↵ect on the
residual resistance is smaller in the 120 C bake case. An
interpretation for this could be that for the same amount
of trapped flux, this trapped flux reflects di↵erently on
losses depending on the cavity surface treatment. This
is plausible since the low field residual resistance due to
trapped flux depends on the radius of the vortex cores
(⇡coherence length ⇠) with ⇠ strongly a↵ected by the surface mean free path. It has been measured that the mean
free path at the surface of a 120 C baked cavity is as low
as 2 nm versus about 40 nm for nitrogen doped cavities5,6 . However, the trapped flux surface resistance part
which depends linearly on the rf field is indeed present in
both cases, and appears to deteriorate the medium field
performance of the 120 C baked cavity by about 4-5 n⌦.
In the third experiment, we studied the performance of
a single cell nitrogen doped cavity with the results shown
in Fig. 7. Similar to the 9-cell nitrogen doped cavity,
Field enhancement due to Meissner effect – ambient flux expulsion What did magnetic probes reveal?!
•  Similar magneOc field at transiOon between fast/slow •  No addiOonal field generated during fast cooling •  SystemaOc strong difference in flux expulsion efficiency between slow and fast cooling EP+120C, Fine grain a)
4
EP, fine grain N doped, Fine grain b)
c)
FIG. 6. Characteristic magnetic field expulsion data for: a) 9-cell EP+120 C baking; b) nitrogen doped 1-cell; c) EP 1-cell. A
strong systematic di↵erence in the field expulsion at di↵erent cooling rates is observed for all surface treatments.
DESY XFEL CM ‘High Duty Factor’ Tests à XM-3
Proof of Principle: Very high Q0 demonstrated in practical
cryomodule
•  Jacek Sekutowicz: XM-3 in CMTB; September 2013
•  7 large grain; 1 fine grain cavities with improved HOM
antennas
LCLS-II DESY AccSeminar 140114
27
What are the technical and “practical” limits for DF ?
1st limit: Heat load at 2K for each cryomodule should not
exceed ca. 20 W
2nd limit: Heating of the HOM couplers must not cause
quenching of the cavity
3th limit: An upgrade of the cryogenic plant should be
“doable”
4th limit: New RF-sources will be added to klystrons used
for the sp operation
Jacek Sekutowicz; 05.11.2013
28
2. cw and lp operaOon; 3 experiments c. Dynamic heat load for Large Grain Cryomodule Comparison of cryomodules: cw operaOon at Eacc = 5.7 MV/m PXFEL3_1 PXFEL2_3 XM-­‐3 XM-­‐3 8 FG 8 FG 7 LG 7 LG # of caviOes with new HOM output 3 2 8 8 T [K] 2 2 2 1.8 Measured DHL [W] 19.5* 18.7 11.5 5.1 1.69 1.63 1 0.44 Type of Nb Ra5o: M-­‐DHL / (M-­‐DHL of XM-­‐3 at 2 K) *scaled to 8 caviOes One must note here that we have not tested yet standard XFEL-­‐type CM housing 8 FG caviOes, all equipped with new HOM output lines. LCLS-­‐II DESY AccSeminar 140114 29 LCLS-II SRF Linac
•  4 GeV ‘up to 300 micro-Amp’ CW superconducting linac
based on TESLA / ILC / E-XFEL 1.3 GHz technology
Key topics:
•  Cavity process for high-Q0 production
•  CW cryomodule design and operations scheme for 110 W
@ 2K / CM (or better)
•  Industrial capability for 1) dressed-processed-cavity, 2)
coupler, and 3) vacuum-vessel/cold-mass production
•  Single RF-source single-cavity
•  Jlab Cryoplant CHL-2 (12 GeV Upgrade) adapted for SLAC
A-I-A Joint Seminar 140414 M. Ross
30
Cavity Specifications (1)
RF frequency
1300
MHz
2
K
~16
MV/m
2.7×1010
-
1.038
M
1036 (998)
Ω (Ω/m)
Geometry constant (G)
270
Ω
HOM damped Q value (monopole and dipole)
≤107
-
8
-
0.5
mm
5
kW
6.3
kW
10
W
Operating temperature
Average operating gradient
Average Q0
Cavity length (L)
R/Q (r/Q)
Number of cavities per CM
Cavity alignment requirements (RMS)
RF beam power per cavity (@300 µA load)
RF power needed per cavity
Cavity
dynamic
load
A-I-A
Joint Seminar
140414
M. Ross
31
Cavity Specifications (2)
Cavity Control Specifications
Qext
4×107
-
Coarse (slow) tuner range
± 245
kHz
~1
kHz
≤1.5
Hz/(MV/m)2
Peak detune (with piezo tuner control)
10
Hz
Required amplitude stability per cavity
0.01
%
Required phase stability per cavity
0.01
deg
Fine (fast) tuner range
Lorentz detuning (k)
A-I-A Joint Seminar 140414 M. Ross
32
Linac cryogenic heat loads
for Q0 = 2.7 x 1010
Cryomodule Heat
Loads
40 K
5K
2.0 K
Predicted static heat
per cryomodule (W)
100
12
6
Predicted dynamic
heat per powered
cryomodule (W)
88
10
85
Predicted total linac
heat (kW)
9.4
0.9
3.1
Note: these heat loads are best estimates, no uncertainty margins added here.
For helium vessel and cryomodule thermal design, a 50% margin for heat load is taken.
We also design cryomodule so as fully to retain a 1.8 K option (lower vapor densities).
A-I-A Joint Seminar 140414 M. Ross
33
1.3 GHz cryomodule
modifications for LCLS-II
•  We start with the TESLA Type 3+, XFEL, and Type 4 designs
•  Modifications for high heat loads
Larger chimney pipe from helium vessel to 2-phase pipe
Larger 2-phase pipe (4 inch OD)
•  Closed-ended 2-phase pipe
Separate 2 K liquid levels in each cryomodule
2 K JT valve on each cryomodule
•  End lever tuner and helium vessel design for minimal df/dP
•  Two cool-down ports in each helium vessel for uniform cooldown of bimetal joints
•  No 5 K thermal shield
But retain 5 K intercepts on input coupler
•  Input coupler design for 7 kW CW plus some margin
A-I-A Joint Seminar 140414 M. Ross
34
LCLS-II cryomodule schematic
A-I-A Joint Seminar 140414 M. Ross
35
LCLS-II Preproduction Cryomodule
1.3 GHz, modified for CW operation
Total length ~12.2 m Nearly the final LCLS-II cryomodule design
A-I-A Joint Seminar 140414 M. Ross
36
LCLS-II Preproduction Cryomodule
8 cavities (End Tuner) + 1 Splittable Quad (V. Kashikhin), 6 Current Leads ~50A
-80K shield (CM3)
-4K intercepts
-Global magnetic shield not shown
-JT Valve
A-I-A Joint Seminar 140414 M. Ross
-Splittable Quad
-BPM
-Gate Valve
37
LCLS-II CM Cavity String & He Gas Return Pipe at
Magnet End
5 K forward pipe
BPM
Warm-up / Cool-down line
and connections to the cavity
A-I-A Joint Seminar 140414 M. Ross
Gate Valve
Splittable Quad
with Needle bearings Supports
(6 Current Leads ~50A)
38
1.3 GHz cryomodule
modifications for LCLS-II
We start with the TESLA Type 3+, XFEL, and Type 4 designs
Modifications for high heat loads
•  Larger chimney pipe from helium vessel to 2-phase pipe
•  Larger 2-phase pipe (4 inch OD)
Closed-ended 2-phase pipe
•  Separate 2 K liquid levels in each cryomodule
•  2 K JT valve on each cryomodule
End lever tuner and helium vessel design for minimal df/dP
Two cool-down ports in each helium vessel for uniform cool-down
of bimetal joints
No 5 K thermal shield
•  But retain 5 K intercepts on input coupler
Input coupler design for 7 kW CW plus some margin
A-I-A Joint Seminar 140414 M. Ross
39
LCLS-II helium vessel and tuner
Chuck Grimm, Evgueni Borissov
A-I-A Joint Seminar 140414 M. Ross
40
1.3 GHz cryomodule
modifications for LCLS-II
We start with the TESLA Type 3+, XFEL, and Type 4 designs
Modifications for high heat loads
•  Larger chimney pipe from helium vessel to 2-phase pipe
•  Larger 2-phase pipe (4 inch OD)
Closed-ended 2-phase pipe
•  Separate 2 K liquid levels in each cryomodule
•  2 K JT valve on each cryomodule
End lever tuner and helium vessel design for minimal df/dP
Two cool-down ports in each helium vessel for uniform cool-down
of bimetal joints
No 5 K thermal shield
•  But retain 5 K intercepts on input coupler
Input coupler design for 7 kW CW plus some margin
A-I-A Joint Seminar 140414 M. Ross
41
Bringing power into the cryomodule – the coaxial
power coupler:
SLAC assembly and test (45 made for ILC-GDE studies)
September 6, 2013
A-I-A
MarcJoint
Ross,
Seminar
SLAC LCLS-II
140414 M. Ross
42
TTFIII Coupler Thermal Calculation at high
CW Power
Center conductor overheating
A-I-A Joint Seminar
140414 M. Ross
43
A-I-A Joint Seminar 140414 M. Ross
44
Modified FPC Antenna For LCLS-­‐II Tip cut 8.5 mm, d = 46.5 mm, Qext Nominal = 4e7 Qext Max = 6e7 d Antenna edge rounded by 3 mm A-I-A Joint Seminar
140414 M. Ross
45
TTF3 Coupler Warm Section
SecOon to be removed and re-­‐plated A-I-A Joint Seminar 140414 M. Ross
Center conductor
bellows à subject to
overheating
46
HOM extraction
•  LCLS-II Low current: HOM extraction requirements
relaxed
A-I-A Joint Seminar 140414 M. Ross
47
A-­‐I-­‐A Joint Seminar 140414 M. Ross 48 D. KosOn, J. Sekutowicz Antenna ModificaOons for E-­‐XFEL “The feedthroughs are made of high conducOvity materials, pure niobium, molybdenum and sapphire. They will be connected thermally to the 2-­‐phase tube with copper braids for be}er heat transfer to the 2 K environment.” A-­‐I-­‐A Joint Seminar 140414 M. Ross 49 D. KosOn, J. Sekutowicz FNAL HOM Quench Study A-I-A Joint Seminar 140414 M. Ross
LCLS-II SRF Linac
•  4 GeV ‘up to 300 micro-Amp’ CW superconducting linac
based on TESLA / ILC / E-XFEL 1.3 GHz technology
Key topics:
•  Cavity process for high-Q0 production
•  CW cryomodule design and operations scheme for 110 W
@ 2K / CM (or better)
•  Industrial capability for 1) dressed-processed-cavity, 2)
coupler, and 3) vacuum-vessel/cold-mass production
•  Single RF-source single-cavity
•  Jlab Cryoplant CHL-2 (12 GeV Upgrade) adapted for SLAC
A-I-A Joint Seminar 140414 M. Ross
51
Project Collaboration
A-I-A Joint Seminar 140414 M. Ross
• 
• 
• 
• 
• 
50% of cryomodules: 1.3 GHz
Cryomodules: 3.9 GHz
Cryomodule engineering/design
Helium distribution
Processing for high Q (FNAL-invented gas doping)
• 
• 
• 
50% of cryomodules: 1.3 GHz
Cryoplant selection/design
Processing for high Q (gas doping)
• 
Undulators
• 
e- gun & associated injector systems
• 
Undulator Vacuum Chamber
• 
• 
Also supports FNAL w/ SCRF cleaning facility
Undulator R&D: vertical polarization
• 
• 
• 
R&D planning, prototype support
processing for high-Q (high Q gas doping)
e- gun option
52
Cryomodule Collaboration
Fermilab is leading the cryomodule design effort
•  Extensive experience with TESLA-style cryomodule design
and assembly
Jefferson Lab and Cornell are partners in design review,
costing, and production
•  Jefferson Lab sharing half the 1.3 GHz production
-  Recent 12 GeV upgrade production experience
Argonne Lab is also participating in cryostat design
•  Beginning with system flow analyses and pipe size
verification
A-I-A Joint Seminar 140414 M. Ross
53
Cryomodule Collaboration
Fermilab is leading the cryomodule design effort
•  Extensive experience with TESLA-style cryomodule design
and assembly
Jefferson Lab and Cornell are partners in design review,
costing, and production
•  Jefferson Lab sharing half the 1.3 GHz production
-  Recent 12 GeV upgrade production experience
Argonne Lab is also participating in cryostat design
•  Beginning with system flow analyses and pipe size
verification
A-I-A Joint Seminar 140414 M. Ross
54
Fermilab Cryomodule: CM2 à testing underway now
A-I-A Joint Seminar 140414 M. Ross
55
Cavity Transmi}ed power Gradient = 31.5 MV/m Fermilab
CM2
First wholly
US-built ILCstyle CM
Uses high
gradient
cavities
Cavity Forward power Cavity Reflected power CM-­‐2 Cavity 1 achieves 31.5 MV/m (AdministraOve limit) 1 Hz, 1.3 ms pulse width 20 December 2013
Capabilities and Infrastructure: FNAL/ANL Cavity
Processing
Electropolishing
Ultrasonic degreasing
•  Dressed cavity prep for CM or
HT ass’y
•  Re-processing
A-I-A Joint Seminar 140414 M. Ross
High-pressure rinse
Ass’y & Leak check
57
Capabilities and Infrastructure: FNAL CM assembly
Class 100
Class 10
Cavity String Assembly
Clean Room
Cavity String Assembly
Cryomodule Transport
Final Assembly
A-I-A Joint Seminar 140414 M. Ross
Cold Mass Assembly
Final Assembly
58
Capabilities and Infrastructure: FNAL 1.3 GHz CM Ass’y
WS2:7d (7)
WS1: 9d (6)
WS3: 5d (10)
WS4:5d (10)
A-I-A Joint Seminar 140414 M. Ross
WS0: 5d (2)
WS5: 10d (8)
WS6: 4d (4)
Total = 45 days
Workstation: duration (#people)
59
Capabilities and Infrastructure: FNAL CM Test
~100M investment 2006-2012
A-I-A Joint Seminar 140414 M. Ross
60
Cryomodule Test Facility (CMTF)
Cryoplant (blue)
Distribution box (silver)
Cryomodule Test Stand (CMTS)
H- beam test cave
A-I-A Joint Seminar 140414 M. Ross
61
Capabilities and infrastructure: FNAL CM test facility
Existing infrastructure for one cryomodule test stand (CMTS)
•  Project to provide RF source/distribution, and cryo distribution
in cave
Cryoplant (blue)
Distribution box (silver)
H- beam test cave
A-I-A Joint Seminar 140414 M. Ross
62
Cryomodule Collaboration
Fermilab is leading the cryomodule design effort
•  Extensive experience with TESLA-style cryomodule design
and assembly
Jefferson Lab and Cornell are partners in design review,
costing, and production
•  Jefferson Lab sharing half the 1.3 GHz production
-  Recent 12 GeV upgrade production experience
Argonne Lab is also participating in cryostat design
•  Beginning with system flow analyses and pipe size
verification
A-I-A Joint Seminar 140414 M. Ross
63
Jlab SRF Production Facilities
Existing and required additions
•  Vertical Test Area (VTA), significant extra capacity
-  8 dewars (4 available for LCLS production, 8 cavities per week capacity)
• 
• 
Peak testing 4 cavities per week required
Routine 2 cavities per week required
-  Low level and high power RF on hand
•  Clean room for cavity string assembly, extra capacity – supported by exisitng
tooling plan
- 
- 
- 
- 
ISO 4
Dedicated drying and assembly bays
Modular wall system
Need LCLS specific cavity string assembly tooling, two sets to support production rate
•  Cryomodule assembly are, significant extra capacity
-  4 bays, two with existing rail systems, two work station per rail
-  2 rails needed for LCLS
-  Need LCLS specific cryomodule tooling, final design to be completed at Jlab to adapt exisitng
tooling to Jlab system
•  Cryomodule test facility (CMTF), pacing facility at 5 shifts per week - additional
throughput available by using more than 5 shifts per week (weekends and
multiple shifts)
-  Single shielded cave
-  2K cryogens available, high throughput investment needed
-  New feed cans for LCLS cryomodules needed
-  Borrow HP RF from the project
A-I-A Joint
Seminar
140414
M. Ross
-  New
LLRF
needed
for 1300 MHz
64
Jlab upgraded SRF Facilities: 2013
Start
2*
A-I-A Joint Seminar 140414 M. Ross
Ship
1*
*
See next page
65
Cryomodule Assembly Rails
1
2
A-I-A Joint Seminar 140414 M. Ross
66
Cryomodule Collaboration
Fermilab is leading the cryomodule design effort
•  Extensive experience with TESLA-style cryomodule design
and assembly
Jefferson Lab and Cornell are partners in design review,
costing, and production
•  Jefferson Lab sharing half the 1.3 GHz production
-  Recent 12 GeV upgrade production experience
Argonne Lab is also participating in cryostat design
•  Beginning with system flow analyses and pipe size
verification
SLAC
•  installation and commissioning
A-I-A Joint Seminar 140414 M. Ross
67
SLAC: View from air:
Equipment entryway
LCLS-II Linac
A-I-A Joint Seminar 140414 M. Ross
68
SLAC Sector 10 Access Tunnel Entrance
A-I-A Joint Seminar 140414 M. Ross
69
Access Tunnel Intersection to Main Linac Tunnel
Entrance to SLAC tunnel
A-I-A Joint Seminar 140414 M. Ross
70
Cryomodules Transport into Tunnel
Beam
A-I-A Joint Seminar 140414 M. Ross
71
Existing SLAC Linac Tunnel
Remove Linac and Support Pipe; Re-use Bypass line
Linac Bypass Lines
Linac
Support Structure
A-I-A Joint Seminar 140414 M. Ross
72
‘cut-paste’ tunnel cross-section:
A-I-A Joint Seminar 140414 M. Ross
73
Summary
•  LCLS-II SRF is based on TESLA / XFEL / ILC work of 20
years
•  To be implemented by SLAC and Partners: Fermilab, Jlab
and Cornell in the next 5 years
•  High Q0 development made excellent progress in last 1
to 2 years
•  LCLS-II tries to capture these advancements
•  CW operation / Cryogenic load are cost-drivers and will
require ‘system-optimization’
•  LCLS-II can be a step toward further application of SRF
A-I-A Joint Seminar 140414 M. Ross
74
End
A-I-A Joint Seminar 140414 M. Ross
75