1604/P1/2014/KSBCDC 19/06/2014 KERALA STATE BACKWARD CLASSES DEVELOPMENT CORPORATION REVIEW ON SCHEME IMPLEMENTATION - May 2014 The overall target for Scheme Implementation for the year 2014-15 is fixed at ` 260 crores. The cumulative target of May 2014 (2/12 the of total Target), and Cumulative achievement are given below: Target and achievement under NBCFDC Schemes Target up to May 2014 District TL Micro Achievement up to May 2014 MSY Total TL Micro MSY Total % 166.70 192.72 0.00 0.00 0.00 0.00 0.00 65.53 64.5 58.64 0.00 0.00 58.64 63.97 85.67 56.15 0.00 0.00 56.15 65.54 5.00 20.67 0.00 0.00 0.00 0.00 0.00 2.5 7.33 104.00 102 22.5 0.00 124.5 119.71 80.67 0.00 6.33 87 34.30 6.00 0.00 40.30 46.32 EKM 107.50 2.5 8.33 118.33 67.41 0.00 0.00 67.41 56.97 TSR 86.17 0.00 6.00 92.17 43.36 0.00 0.00 43.36 47.04 CHK 21.50 4.16 0.00 25.67 0.00 0.00 0.00 0.00 0.00 PKD 86.17 2.16 5.00 93.33 48.50 0.00 0.00 48.50 51.94 PTB 21.50 0 4.17 25.66 21.19 0.00 0.00 21.19 82.58 MPM 76.67 2.5 5.83 85.00 46.52 0.00 0.00 46.52 54.73 WDR 23.33 4.16 0.00 27.5 32.70 0.00 0.00 32.70 118.91 TRR 16.67 0.00 4.17 20.83 8.6 0.00 0.00 8.6 41.29 KKD 107.50 5 8.50 121.00 130.16 0.00 0.00 130.16 107.57 WYD 67.17 1.67 5.33 74.17 58.44 0.00 0.00 58.44 78.79 KNR 94.33 1.67 8.17 104.17 129.88 0.00 0.00 129.88 125.68 KGD 80.83 2.16 6.33 89.33 66.70 0.00 0.00 66.70 74.67 TOT 1342.35 37.98 105.15 1486.33 1048.88 128.50 0.00 TVM 80.67 0.00 5.83 86.5 66.70 100.00 0.00 VKL 26.83 2.00 2.50 32.17 0.00 0.00 KLM 94.17 0.00 7.33 101.5 65.53 PTA 80.00 5 6.67 91.67 ALP 80.83 2.5 2.33 HPD 15.67 0.00 KTM 94.17 IDK 1177.38 79.21 Target and Achievement under NMDFC schemes Achievement up to May 2014 Target up to May 2014 District Term Loan Micro . Total Term Loan NM Micro Total % TVM 47.67 5.83 53.50 14.95 0.00 14.95 27.94 VKL 16.17 0.00 16.17 0.00 0.00 0.00 0.00 KLM 56.00 10.00 66.00 57.74 0.00 57.74 87.48 PTA 47.83 0.00 47.83 16.35 0.00 16.35 34.18 ALP 46.00 5.00 51.00 8.39 0.00 8.39 16.45 HPD 10.00 0.00 10.00 0.00 0.00 0.00 0.00 KTM 56.00 5.33 61.33 8.53 29.50 38.03 62.00 IDK 47.83 8.5 56.33 32.10 19.00 51.10 90.72 EKM 63.83 6.16 70.00 18.68 0.00 18.68 26.69 TSR 51.00 6.16 57.17 23.55 0.00 23.55 41.19 CHK 12.83 0.00 12.83 0.00 0.00 0.00 0.00 PKD 51.17 5.83 57.00 6.20 0.00 6.20 10.88 PTB 12.83 0.00 12.83 1.3.00 0.00 1.30 10.13 MPM 43.00 7.17 50.17 19.40 0.00 19.40 38.67 WDR 17.67 0.00 17.67 6.2 0.00 6.20 35.09 TRR 8.50 4.16 12.67 0.00 0.00 0.00 0.00 KKD 63.67 5.83 69.59 5.9 0.00 5.90 8.48 WYD 39.83 0.00 39.83 38.11 0.00 38.11 95.68 KNR 56.00 5.00 61.00 3.75 0.00 3.75 6.15 KGD 47.83 4.66 52.50 6.57 0.00 6.57 12.51 TOT 795.63 79.63 875.33 267.72 48.50 316.22 36.13 Target and Achievement under KSBCDC Own fund Schemes Achievement up to May 2014 Target up to May 2014 SG SS OTH Total SG SS OTH % Total SG % SS % OTH % Total % TVM 43.67 12.5 51.67 107.83 4.50 1.85 92.45 98.8 10.30 14.8 178.9 91.63 VKL 14.67 4.17 18.33 37.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 KLM 45.00 25.00 60.83 130.83 26.00 32.15 115.58 173.7 57.78 128.6 190.0 0 132.8 PTA 29.17 28.33 43.33 100.83 4.50 16.07 112.74 133.3 15.43 56.72 260.2 132.2 ALP 21.67 16.67 50.00 88.33 28.30 .70.00 89.17 118.2 130.59 4.20 178.3 133.8 HPD 8.33 5.00 16.67 30.00 0.00 0.00 0.00 0.00 0.0 0.00 0.00 0.00 KTM 29.17 25.00 63.83 118.00 9.62 45.49 90.22 145.3 32.98 181.96 143.3 123.1 IDK 23.33 19.17 63.33 105.83 10.60 21.00 44.10 75.7 45.44 109.55 64.64 71.53 EKM 33.33 26.67 81.67 141.67 33.79 44.85 85.73 164.4 101.38 168.17 105 116 TSR 26.67 20.00 66.33 113 0.00 8.20 48.73 56.93 0.00 41.00 73.47 150.3 8 CHK 5.00 6.67 16.67 28.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 PKD 23.33 18.33 74.00 115.67 1.50 6.00 95.22 102.7 6.43 32.73 128.7 88.79 PTB 6.67 5.33 17.33 29.33 0.00 0.00 10.58 10.58 0.00 0.00 61.05 36.07 MPM 23.33 25.00 58.83 107.17 38.30 76.13 82.07 196.5 164.17 304.52 139.5 183.4 WDR 8.33 13.33 13.83 35.50 14.00 65.15 52.00 131.2 168.07 488.75 376 369.6 TRR 5.00 10.00 16.67 31.67 7.5 10.33 14.98 32.81 150 103.3 89.86 103.6 KKD 33.33 26.67 83.33 143.33 27.00 4.00 101.18 132.2 81.01 14.99 121.4 92.23 WYD 16.67 22.00 43.33 82.00 6.00 10.20 94.75 111.0 35.99 46.36 218.7 135.4 KNR 20.00 20.00 82.33 122.33 42.40 50.20 145.50 238.1 212 251 176.7 194.6 KGD 13.33 13.33 76.17 102.83 22.45 12.00 115.78 150.2 168.41 90.02 152 146.1 TOT 430.00 343.17 998.48 1771.67 276.46 404.32 1390.77 2072 64.29 117.82 139.3 117 Agency wise Achievements –At a glance Target Achievement District Total NB NM OWN Total NB NM % OWN TVM 86.5 53.50 107.83 247.83 166.70 14.95 98.8 280.5 113.2 VKL 32.17 16.17 37.17 85.51 0.00 0.00 0.00 0.00 0.00 KLM 101.5 66.00 130.83 298.33 65.53 57.74 173.7 297.00 99.55 PTA 91.67 47.83 100.83 240.33 58.64 16.35 133.3 208.3 86.67 ALP 85.67 51.00 88.33 225.00 56.15 8.39 118.2 182.7 81.2 HPD 20.67 10.00 30.00 60.67 0.00 0.00 0.00 0.00 0.00 KTM 104.00 61.33 118.00 283.33 124.5 38.03 145.3 307.8 108.6 IDK 87.00 56.33 105.83 249.16 40.30 51.10 75.7 167.1 67.07 EKM 118.33 70.00 141.67 330.00 67.41 18.68 164.4 250.5 75.91 TSR 92.17 57.17 113.00 262.34 43.36 23.55 56.93 123.8 47.19 CHK 25.67 12.83 28.33 66.83 0.00 0.00 0.00 0.00 0.00 PKD 93.33 57.00 115.67 266.00 48.50 6.20 102.7 187.4 70.45 PTB 25.66 12.83 29.33 87.82 21.19 1.30 10.58 33.07 37.66 MPM 85.00 50.17 107.17 242.34 46.52 19.40 196.5 262.4 108.33 WDR 27.5 17.67 35.50 80.67 32.70 6.20 131.2 170.1 210.9 TRR 20.83 12.67 31.67 65.17 8.6 0.00 32.81 41.41 63.54 KKD 121.00 69.59 143.33 333.92 130.16 5.90 132.2 268.3 80.35 WAD 74.17 39.83 82.00 196.00 58.44 38.11 111 207.6 105.9 KNR 104.17 61.00 122.33 287.5 129.88 3.75 238.1 371.7 129.3 KGD 89.33 52.50 102.83 244.66 66.70 6.57 150.2 233.5 95.44 1486.33 875.33 1771.67 4133.33 1177.38 316.22 2072 3565.15 86.27 TOTAL 1. The Cumulative utilization up to May 2014 is Rs. 3565.15 Lakhs, which is 86.27 % of the target. 2. The achievement under NBCFDC, NMDFC and Own fund schemes is 79.21, 36.13 and 117 % respectively. The shortage under NMDFC scheme is to due to non-receipt of fund from NMDFC during the current quarter. 3. Thiruvananthapuram, Kottayam, Malappuram, Wandoor, Wayanad, and recorded more than 100% achievement during the month. 4. Chelakkara, Thrissur and Pattambi recorded below 50% of the target. 5. In the case of Swastha graha scheme Alappuzha, Ernakulam, Malappuram, Wandoor, Thiroor and Kasaragod recorded disbursement in excess of target. These offices are directed to limit disbursement within the target. 6. In the case of Suvarnasree scheme, Kollam, Kottayam, Idukki, Ernakulam , Malappuram, Thiroor and Wandoor offices are directed to control disbursement within the target. 7. The disbursement under Nitaqat Returnee scheme may be expedited so as to complete the implementation before 30th June 2014 as decided by the Board of Directors of the Corporation. 8. All District/Sub District Managers are directed to report details of pending applications of High value/Foreign Education Loan above ` 5 lakhs to this office for scheduling RLPSC meeting. Managing Director
© Copyright 2024 ExpyDoc