Agricultural Need for Sustainable Willow Effluent Recycling Irrigation schemes: Bridgend, Ballinacarrick, Churchtown Co. Donegal Con McLaughlin Donegal County Council Senior Engineer Acknowledgements • Colleagues in Donegal County Council with key inputs o Hugh Doherty (M&E design) o Patrick Doherty (Construction Supervision) o Joanne Holmes, (Planning /design etc) o Michelle McDaid (Project claims) o David Robb (Lifford Landfill Project) • Prof Alistair McCracken, AFBI • Donal Doyle, RPS Consulting Engineers • Aila Carty, Vesi Environmental Limited, Cork it enough to change change your game?it self or isIs your goal to the game GAME CHANGERS! ANSWER Project sites in County Donegal • 14 ha SRC willow plantation irrigated with effluent at Bridgend wastewater treatment plant • Lysimeters on cap at Ballinacarrick Landfill • Combined technologies in Churchtown Landfill Restoration o Bioremediation with src willows plus o Integrated Constructed Wetlands (ICW) Lands identified are in close proximity to Bridgend Wastewater Treatment Works Bridgend WWTW Field 2, Field 1, Low pressure pumping of effluent to willow plantations Field 3 to Derry Irrigation layout by Laqua showing rising main & 25no zones at Bridgend Irrigation zones at Bridgend 25 zones each with a valve wired back to an irrigation controller These jobs bring their own challenges! Irrigation system at Bridgend Wastewater Treatment (emerging src willows in background) Laterals through buffer area into willows (Holes 9m centres) Header pipe (for one zone) Rising main (pumped from the Bridgend works) Bridgend Treatment plant Before and After the ANSWER Project Irish Water have progressed a screen which will further enhance the works Friday Saturday Sunday 5pm 11am 5am, Pumps on All data trended and available online, this example showing inlet flow, irrigation flow and no flow to river Data capture during commissioning • 1st July – 8th October – Total inlet flow – Total irrigated Flow – Overflow to River 11,300m3 9,363m3 [83%] 1,937m3 [17%] • These figures will be improved on, we established (8th Oct) one set point in the controls which was causing an overflow Ballinacarrick landfill General arrangement of trial plots (lysimeter's) Lysimeters at Ballinacarrick Landfill The Ballintra Landfill site 12 no lysimeter's Willows in lysimeters at Ballintra (Ballinacarrick Landfill) Willows in lysimeters at Ballintra The Lifford Landfill site .. works managed by David Robb, DCC Restoration works financed by q Department of Environment, Community & Local Government q The ANSWER Project River Finn Churchtown Landfill, Lifford– situated between N15 Road and River Finn Haul road Stripping topsoil River Finn View from the air shortly after the work started in May 2014 The ‘Master Plan’ at Lifford, with . . . • willows irrigated in the core • ‘ICW’ ponds either side (flow split 60 : 40 based on area) • ‘ICW’ A floor area 6,547m2 (62%) • ‘ICW’ B floor area 4,018m2 (38%) 62% Total ‘ICW’ floor area 10,565m2 (2.6 acres) 38% Indication of Proposed Boreholes / Site monitoring Ground water Piezometers Gas Leachate extraction Leachate collection design Pumping Stations 1, 2 & 3 Capturing leachate from toe drains which is returned to head of works for treatment (Willows and / or ICW’s) PS1 Pumping Stations 4 Leachate Extraction from waste body also to head of works for treatment (Willows and / or ICW’s) PS3 PS2 Constructing toe drain and shaping side slopes Importing clay / forming the Cap Proposed Emission Limit Values Extensive site! clay cap works ongoing Stone drain through topsoil to capture any run of following heavy rains or leachate not absorbed by the willows Imported material (to October) Type Vol (t) No of loads Subsoil 57,000 2,850 Clay cap (500mm) 93,457 4,673 Topsoil (450mm) 19,500 975 Drainage stone 3,079 140 TOTALS 173,036 8,638 Enhanced design – receiving cell incorporated in pond 1A Receiving Cell under construction within Pond 1A Pond 1A Ponds 4a & 5a under construction Progress at end of August with willows emerging and ‘ICWs’ under construction Construction at 19th September Ponds flooded for planting Access Road around site Embankments top-soiled Control philosophy (north half only shown) Online analyser (composite sampler ) (with ‘a’ or ‘b’) a) Compliant – routed to storm drains Any run off b) Non compliant – to head of from willows site for further treatment to central drains Option at head of works to send to either ICW and/or willow depending on hydraulic loading Some early words of encouragement .. ‘It is therefore important that this type of sustainable technology is actively encouraged in today’s environmentally aware and financially constrained climate’ Mr. John McMillen, Chief Executive, NIEA speaking enthusiastically about the potential of using SRC willow at the ANSWER Project launch In the same vein, I wish to acknowledge the support we received from the EPA’s Office of Environmental Enforcement, Dr Mick Henry, Senior Inspector Mr John Gibbons, Inspector Lifford Landfill - 3rd October 2014 Thank You
© Copyright 2024 ExpyDoc