Rail Park Project Schedule and Task Details Kalispell Trail - FCEDA Rail Park Project Schedule Submit Categorical Exclusion Worksheet to the FRA Receive Notice of Award from the US DOT Receive TIGER VI funds from US DOT Complete Final Design and Construction Documents for Rail Park Rail Park Construction Contract Signed and All TIGER Funds Obligated Begin Construction of Rail Park Complete Construction of Rail Park Complete CHS Facility Construction and Relocate Existing Rail Users to Rail Park Complete Rail Abandonment Complete Trail Property Acquisition Complete Environmental Site Assessments and Remediation Complete Final Design and Construction Documents for Multi-Use Trail Remove Track Begin Construction of the Trail Complete Street Extension and Upgrade Pedestrian Crossings Date April 2014 October 2014 January 2015 June 2015 August 2015 August 2015 December 2016 October 2017 April 2018 May 2018 December 2018 March 2019 April 2019 May 2019 September 2021 Schedule Description Construction—FCEDA Rail Park is ready to begin construction August 2015. The NEPA process, initiated in January 2014, is being implemented to coincide with this TIGER VI application, per the guidance from the Federal Railway Administration. A Traffic Impact Analysis has been completed and KLJ Engineering is under contract to complete the engineering requirements. The Montana Department of Transportation is participating in the project by planning the needed improvements to Montclair Drive and the intersection at US Highway 2 East and has provided a Letter of Status for the project. Neighboring landowners have provided letters of support for these changes and additions. Final design approvals are anticipated in April 2015. Additionally, Flathead Drive, the private road within the Rail Park, will be widened and extended. BNSF has agreed to execute an easement to FCEDA for this road improvement when the funding for the project is secured. Preliminary engineering plans are complete and final engineering will begin within 30 days of grant funds being awarded, currently scheduled for January 2015. Project construction will be put out for bid in June 2015 with a contractor selected July 2015. The construction of the Rail Park is scheduled to begin August 2015 and will be completed in December 2016. FCEDA, project partners, and the engineering consultants have established risk mitigation protocols which ensure TIGER VI funding will be obligated by June 2016. Task 1.0: Railroad An existing rail mainline owned by BNSF Railway and operated by Mission Mountain Rail currently passes adjacent to the site of the FCEDA Rail Park. There is also an existing switch and single rail spur that extends into a portion of the neighboring BNSF Railway property immediately north, serving established rail customers Glacier Stone Supply and Klingler Wood Products. One additional rail spur is proposed adjacent to the existing mainline on BNSF Railway right-of-way and includes design and construction of 3,300 feet of rail spur along the east side of the existing mainline. Several rail spurs are proposed within the Rail Park totaling 10,950 feet of rail. These rail spurs will be utilized by CHS operations, Northwest Drywall Operations, and additional users including a trans-load facility. The total proposed length of rail for the project is 17,140 feet. Task 2.0: Roadways and Grading This task will include permitting, design, bidding, and construction for 7,000 feet of new and upgraded roadway. The planned roadway width is 32 feet with gravel base, asphalt pavement surfacing, and curb and gutter. Stormwater infrastructure will also be installed to accommodate site drainage and meet detention requirements. The budget includes widening the railroad crossing in the park as well as lights, gates, and bells at the rail crossing. Improvements outside of the facility are also proposed including improvement to and installation of a traffic signal light at the intersection of US Highway 2 and Montclair Drive to facilitate traffic to and from the site. Montana Department of Transportation (MDT) has approved the proposed changes to US Highway 2. The surrounding landowners support the addition of the signal as it will be a safety improvement and a benefit to their businesses. Task 3.0: Electrical and Gas This task includes installation of electrical and gas service to accommodate each user of the rail park facility. There is existing electrical and gas infrastructure within close proximity to the rail park but it will be required to network throughout the facility. Task 4.0: Wastewater This task includes permitting, design, bidding, and construction of wastewater facilities to service the rail park facility. Wastewater infrastructure will connect to the existing City of Kalispell sewer main located south of the rail park. A lift station will be placed at the intersection of East Oregon Lane and Montclair Drive. Gravity main will be installed throughout the rail park facility and along East Oregon Lane and drain to the lift station. The lift station will pump through a force main along East Oregon Lane to its connection with the City of Kalispell’s existing sewer main. A total of 6,025 feet of gravity sewer main and 1,940 feet of 4-inch force main are planned for installation. Task 5.0: Water Supply This task includes permitting, design, bidding, and construction of water supply infrastructure to service the rail park facility. Water infrastructure will connect to the existing City of Kalispell water main at the intersection of West Oregon Lane and 4th Avenue North. It will travel within existing ROW along Oregon Lane to its intersection with Montclair Drive, west through the center of the rail park facility to its intersection with Whitefish Stage Road, and south along Whitefish Stage Road to a point where it will connect back into City of Kalispell water system infrastructure. This would provide a looped system to maximize fire flows. Approximately 8,500 feet of 12-inch water main is planned for installation along with 17 fire hydrants Construction— Kalispell Trail will follow the construction of FCEDA Rail Park. Environmental Assessments will begin in 2017 with clean-up starting in 2018. The trail, crossing upgrades, and complete streets will be fully built by September 2021. Task 1.0 Rail Abandonment After all current rail users have had their rail use needs met to their satisfaction and relocation of their businesses to the Rail Park is complete, the City of Kalispell will work in partnership with BNSF to facilitate all necessary BNSF and Federal Rail Administration processes to abandon the approximate 2-mile long line that currently runs through the City of Kalispell. Task 2.0 Trail Property Acquisition The City of Kalispell is currently in conversation with all property owners along this approximate 2-mile route who own property over which the current active rail line traverses. BNSF owns one-half of the line in question and has indicated to the City by letter that they will enter into an agreement to transfer their ownership of the abandoned rail bed to the City once abandonment has actually occurred. The remaining length of the rail bed between 8th Ave. West and 3rd Ave. East was previously sold to 8 adjacent property owners in 1989 or there about. BNSF maintains a 25-foot easement for the existing rail in these locations. All eight owners have expressed willingness to work with the City to ensure that the trail is developed where the current rail sits. Property owners support this project both for the benefits that it brings to the community, but also because it will enhance the value of their property and enable their clients and customers an attractive additional form of access to their facility or business. The City of Kalispell has set aside Tax Increment Finance District funds to acquire properties/easements as needed. Task 3.0 Environmental Site Assessments and Remediation Because the property lies under an existing rail line that has operated for 120 years, the City of Kalispell has designated $58,000 in funds for Phase 1 and Phase 2 Site Assessments and $500,000 for Remediation. The City has operated a successful Brownfields program for the past 4 years and has the proven experience to execute Task 3.0. This work will be completed at the time of acquisition of the property or easements. Task 4.0 Multi-use Trail Design A preliminary design and feasibility study was completed in June, 2013. The City will advertise for final design, engineering and construction drawings once rail abandonment has been completed with the anticipation of going to immediate construction of the trail. The trail will be a 10-15 foot wide paved/concrete multi-use pedestrian trail. Lighting will be provided along the trail to insure safe access night and day. Three regional trailhead connections are proposed where the new trial will intersect with existing trial systems allowing the trail to connect to a 3 ½ mile trail north to the hospital, college and commercial shopping, an 8 mile trail west to Kila and a 11 mile trail south to Somers. Task 5.0 Track Removal Once the rail users have been relocated and the BNSF track has been abandoned, BNSF will salvage the existing rail and ties for either re-use or recycling depending on the quality of the materials. Task 6.0 Trail Construction The project will be competitively bid. TIF funds have been established per council action on Monday April 21, 2014 to fund construction. Task 7.0 Upgrade Pedestrian Crossings The trail will cross 6 City streets and 4 new local streets. The design will provide for the construction of safe ADA compliant crossing points. The crossing will be designed to shrink the size of the street width at the particular crossing and provide pedestrian actuated crossing signals to insure safe crossing points. Task 8.0 Complete Street Extension Once BNSF has abandoned the rail line and removed the track, the City proposes to construct at least 4 new cross streets across the abandoned rail area to improve vehicle and pedestrian access into the downtown. These 4 new crossing will augment the existing 6 crossings along this 2mile corridor previously isolated by the presence of the railroad. These streets will comply with the City complete street policy and provide sidewalks and bike lanes. This will greatly insure pedestrian access to the new trail system and further allow free movement of pedestrians through the Core Area and downtown of Kalispell previously blocked by the railroad for the past 120 years. The City has approved TIF funding for this activity per council action dated April 21, 2014.
© Copyright 2024 ExpyDoc