HARYANA VIDYUT PRASARAN NIGAM LIMITED To 1

HARYANA VIDYUT PRASARAN NIGAM LIMITED
(A Govt. of Haryana undertaking)
Regd. office: Shakti Bhawan, Sector-6, Panchkula-134109
Corporate Identity Number: U40101HR1997SGC033683
O/o Chief Engineer (Material Management),
Tel No.: 0172-2583724/2583744, Fax No.:0172-2583724/2565746
E-mail: [email protected], [email protected], [email protected]
To
1. The Superintending Engineer/TS, HVPNL, Karnal/Panchkula/Rohtak.
2. The Executive Engineer/TS, HVPNL, Rohtak/ Yamunanagar/Kurukshetra/Panipat/
Kaithal.
Memo No.Ch- 98/ITMS-144/IT&C/substation
Dated: 5.12.2014
IT Plan implementation –Substation Module implementation and Training
w.e.f 8.12.2014 at Karnal Training Center.
Subject:
As you are aware that the work of IT plan Implementation is in progress.
2.
To make the users aware about handling the application, training for 5-6 days is to be
imparted by System Integrator (SI) at Panchkula, Karnal, Hisar and Gurgaon. During the training,
the Handholding of the module alongwith exposure to working on Live Environment shall be
provided.
3.
It is to inform that the training on Substation Module at Conference Hall, o/o SE/TS Karnal,
Shakti Bhawan, Kunjpura Road Karnal will commence from 8.12.2014 (Monday) for 1st batch and
from 15.12.2014 (Monday) for 2nd batch. As per directions of Managing Director, HVPNL it was
desired that concerned SSE Incharge of the substation be also present during the training to staff.
4.
The training has been scheduled in two weeks by picking up two persons in first week and
remaining two persons in next week. The end users have been identified as per feedback
provided by concerned AEE/AE of TS and M&P Wings. The detailed training schedule for Week-1
and Week-2 is attached herewith for reference (Annexure-A and Annexure-B).
It is requested that the officers/officials mentioned in the enclosed training schedule may be
directed to report in respective Training centers at 9.15 AM on 8.12.2014 for Week -1 and on
15.12.2014 for Week-2.
SE/TS Karnal is requested to ask Sh. Piyush Xen/TS, Kurukshetra to supervise the training
programme being ‘Core User’ for substation module and his AEE/Works to assist Sh. Piyush
Xen/TS Kurukshetra for smooth running of training.
The schedule has also been uploaded on HVPN website www.hvpn.gov.in under Tab
‘IT/ERP-Training programmes’.
DA/Detailed training schedule
SE/ IT & C
For Chief Engineer/MM
HVPNL Panchkula.
CC:
1.
2.
3.
4.
The Chief Engineer/TS, HVPNL, Panchkula.
The Chief Engineer/MM, HVPNL, Panchkula.
The Vice Principal, HPTI, Pinjore.
The SPS to Managing Director, HVPNL, Panchkula for kind information of Managing
Director, Panchkula.
5. The SPS to Director (Technical/Projects) HVPNL, Panchkula for kind information of
Director (Technical/Projects), Panchkula.
6. Sh. Piyush Saini, Xen/TS, HVPNL, Kurukshetra.
7. AEE/Works of SE/TS, HVPNL Karnal.
8. Sh. Darshan Lal JE, IT Nodal officer at Karnal to ensure smooth running of training as
per schedule.
9. Sh. Pawan JE IT Nodal officer at Kaithal.
10. Sh. Dhanraj JE IT Nodal Officer at Rohtak
11. Sh. Ashutosh Triguanyat, Program Manager (Site), M/s Tech Mahindra (SI). It is
requested to supply attendance on daily basis alongwith feedback/evaluation of
participants on completion of training.
12. Sh. Satvik Shriniwaroa, Project Manager, IFS Solutions.
13. Sh. Manish Thakur, Site Project Manager, Dimension Data
14. Sh. Sandeep Dogra, Dimension Data.
Annexure-A
Training Centre
Day-1
(8.12.14)
IT Plan Implementation Substation Module Implementation Training schedule wef 8.12.2014 to 12.12.2014
Process Name
Process Name
Session-1
Whom to attend
Session-2
1. Introduction of Substation Module, IFS Basic
List given below
Equipments Master
Navigation (Launching IFS Application,Log on
Log Sheet Entry -1 (Hourly reading,
process,changing password,key shortcuts)
Battery reading)
Karnal
Whom to attend
List given below
Day-2
(9.12.14)
Log Sheet Entry.-2( Energy Meter, Bus connection &
other)
SSTN -Technical and Non Technical Log Entry Part-1
List given below
SSTN -Technical and Non Technical Log
Entry Part-2
List given below
Day-3
(10.12.14)
SSTN-Preventive Maintenance and Condiction Based
Maintenance
List given below
SSTN-Breakdown Maintenance and
Emergency Maintenance
List given below
Day-4
(11.12.14)
Technical Audit Periodical Testing
List given below
Hot line maintenance
Line Maintenance
List given below
List given below
Day-5
(12.12.14)
E mail messaging+Basic Trouble shooting of Hardware
and support mechanism
List given below
Generation of reports
List given below
Feedback+Test+Resolving shortcomings.
Participants List
Sr. No.
1
2
3
4
5
6
7
Substation
132 kV Rohtak
66 kV Lohara
66 kV Gangori
132 kV Bhore
132 kV Bodhni
132 kV Ganaur
132 kV Cheeka
1st Week
Surender SA
Sanjay Kumar JE
Raman Saini SSA(C )
Eshwar Singh SSA(C )
Balbir Singh JE
Dharambir JE
Manoj ALM
Anil SA
Vikram SA(C )
Sushil Kumar SA(C )
Mohit Lineman
Kamal Kumar SA
Satnarain GSO
Sumit Singh SA(C )
Sh. Sujan Sungh SSE
132 kV Rohtak,
Annexure-B
Training Center
IT Plan Implementation Substation Module Implementation Training schedule wef 15.12.2014 to 19.12.2014
Process Name
Process Name
Session-1
Whom to attend
Session-2
Day-1
(15.12.14)
1. Introduction of Substation Module, IFS Basic
Navigation (Launching IFS Application,Log on
process,changing password,key shortcuts)
Log Sheet Entry.-2( Energy Meter, Bus connection &
Day-2
(16.12.14) other)
SSTN -Technical and Non Technical Log Entry Part-1
SSTN-Preventive Maintenance and Condition Based
Day-3
(17.12.14) Maintenance
Day-4
(18.12.14)
Technical Audit Periodical Testing
E mail messaging+Basic Trouble shooting of Hardware
Day-5
and support mechanism
(19.12.14)
List given below
Equipments Master
Karnal
Whom to attend
List given below
Log Sheet Entry -1 (Hourly reading,
Battery reading)
List given below
List given below
SSTN -Technical and Non Technical
Log Entry Part-2
List given below
SSTN-Breakdown Maintenance and
Emergency Maintenance
List given below
List given below
Hot line maintenance
Line Maintenance
List given below
List given below
Generation of reports
Feedback+Test+Resolving
shortcomings.
List given below
Participants list
Substations
1
2
3
4
5
6
7
132 kV Rohtak
66 kV Lohara
66 kV Gangori
132 kV Bhore
132 kV Bodhni
132 kV Ganaur
132kV Cheeka
2nd Week
Sushil SA
Sinil Kumar SA(C )
Parbhash Chand JE
Bhag Singh SSA(C )
jaspal SA
Prem Lineman
Vikram Kumar SA(C )
Ram Pal SA
Vikram SA(C )
Parveen Kumar SSA(C )
Pardeep Kumar SA©
Nirmal Singh SA(C )
Navin Lineman
Harvinder Singh JE-1
Sh. Vishal Sharma
SSE 132 kV Ganaur