14-06-2014 - Regional Office Chandigarh

Telephone No. : (017212638061
Fax No.
: (017212638135
\fW~~
~-;jo 24-25,
~~
~-31~, ~ 160030
qllTcHUI ~ q;:r ~
GOVERNMENT OF INDIA
vll:T J i:RlJlrn
MINISTRY OF ENVIRONMENT AND FORESTS'll:i (! O;\ll(.",n
F. No. 5-127/2008-RO (NZ)!
Northern Regional Office,
Bays No. 24 & 25, Sector 31·A,
I
Dakshin Marg, Chandigarh·160 030
II
Slf S3
Dated: 16.06.2014
m-r1{ ,
The Director(Business Development & Projects)
Mis Omaxe Ltd.
7, Local Shopping Center
Kalkaii, New Delhi-11 0019
Sub: Construction of Residential Group Housing Project named as
"Om axe Greens" at village-Jharmari, Dera Bassi, Punjab by MIs
Omaxe Ltd~.-site inspection regarding.
Ref. MoEF, New Delhi's letter No.21-408/2007-IA.11I dt. 08.05.2008.
\3q':!ffi ~ 1{ \3c>clllCld qR'41\J1<f1 CI>I 'frritmur fu;:ricp 14th June, 2014 CB!
fcl:>m 4fflT I ~ f.tfrmur cI> ~ CPft -Q-m-uIT am qR'41\J1<f1 3IfuCflIR'41 -a- q:qf cI>
mG 3ialElMI~ &ill"([Cl1 ;f!;r-CflActI4d 't:Gf ~ 'fcIRrr 1FII ~ f3R:pI 3INCI>I ~
Ft~3iT 1R CflI~cn~ cI> ~ Cf®" 1FII ~ I
3IJlRt ~ ~ 1m ~ 't:Gf cI>.~ CPft
=Cbln.",~q...d-I~ fWt 3Ifa- ~ ~ "CflB qft cpu ~ I
~3iT 1R CbF2cn~ ~
"
.-/
(~epIR)
A~~ICfl("(!R)
Tel. No. (0172)-2638994
EMail:[email protected]
Copy to :
The Director(S), Monitoring Cell, Ministry of Environment and
Forests, Paryavaran Bhawan, CGO Complex, Lodhi Road, New
Delhi 110 003 for information and necessary action please. '
~:
Telephone No. : (0172) 2638061
Fax No.
: (0172) 2638135
~Q~
~ -;10 24 - 25 1
~-31"Q1 ~ 160030
~mcnR
qmcHUI~CR~
GOVERNMENT OF INDIA
,
~ MINISTRY OF ENVIRONMENT AND FORESTS
F. No. 5-127/2008-RO (NZ)
iJlt:; ~
r,RlII'i4l
'w; e, i!!~I[.ri4l
I
II
Northern Regional Office,
Bays No. 24 &25, Sector 31-A,
Dakshin Marg, Chandigarh·160 030
Dated: 16.06.2014
To
The Director(Business Development & Projects)
MIs Omaxe Ltd.
7, Local Shopping Center
Kalkaji, New Delhi-110019
Sub: Construction of Residential Group Housing Project named as
"Omaxe Greens" at village-.Jharmari, Dera Bassi, Punjab by MIs
Omaxe Ltd.-site inspection regarding.
Ref. MoEF, New Delhi's letter No.21-408/2007-IA.l1I dt. 08.05.2008.
Sir,
On the basis of site inspection of above cited project on 14th June, 2014, point
wise discussion with project executing authorities and subsequent information submitted
so far, a comprehensive monitoring report is being submitted to Ministry for further
necessary action and following comments and observations are forwarded to you for
necessary action at your end. Accordingly, information and 'action taken report' on
the following points may be submitted to this office urgently:­
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Inform the completion schedule of remaining towers.
Inform the number of families occupied the flats.
Submit the information about the funds spent on medicines and medical help
to the workers during construction phase till date.
'"
Inform tentative schedule of installing the Solar system for common lighting.
Inform the schedule for cleaning the Rainwater harvesting measures. It is
noticed that the rainwater harvesting pits are not being cleaned regularly.
You have committed to provide dual plumbing line in remaining 4 Towers to
use treated water from STP for toilet flushing. It may be complied sincerely and
the compliance report should be submitted to this office immediately.
Adequacy report of STP through an authorized agency immediately.
Latest physical and financial progress about CSR activities may be
informed.
Uploading of six monthly progress report and monitoring reports on the'web
site of the Company may be ensured.
Ambient Air Quality, Soil quality, ground water quality and Noise levels near
DG sets should be monitored by some approved lab and the results should be
submitted to this office from time to time.
Submit information about green belt development in the following proforma
with six monthly proqress report:­
S.No
Year
Area
Exp.
No.
of Species of
covered
plants
incurred
plants
planted
(in Rs.)
planted
Submit action taken report in respect of Energy Conservation Measures actually
being adopted in the residential colony.
Inform the strategy to be adopted about the collection and disposal of solid
waste from the residential colony during operation of the buildinq.
--2­
14.
15.
16.
17.
18.
The Energy audit report in respect of Housing Complex
through an
authorized a enc .
You have to adopt in vessel bio-composting for the garbage and kitchen
waste to be generated from the residential colony. For this purpose the
installation of Organic Waste Converter may be harnessed. Action proposed
.
to be taken in this re ard ma be informed.
Submit details about the funds kept in the budget for implementation of
Environment Management Plans and uptodate expenditure on different items
of EMP.
Submit the copies of following NOC's/approvals:­
• Valid 'Consent to Operate' under Air & Water Acts.
•. NOC from NHAI for access from National Highway to your project.
Submission of six monthly progress report in hard and soft copies may be
ensured as the same will be displayed on MoEF's Web site. Next six monthly
pro ress re ort is due in 1st week of December, 2014.
An 'Action Taken"Report' and clarifications, if any, may be sUbmitted.
Yours faithfully,
(Surendra Kumar)
Director(S)
Tel. No. (0172)-2638994
E:
Mall:sk5~1(@yahoo.com
Enc!. as above:
Copy to :
The Director(S), Monitoring Cell, Ministry of Environment and Forests,
Paryavaran Shawan, . CGO Complex, Lodhi Road, New Delhi--110003 for
information and necessary action please.
"
~\~~~~
(Surendra Kumar)
Director(S) .
~:
Telephone No. : (0172) 2638061
Fax No.
: (0172) 2638135
~~~
~<io 24-25,
'm"{Cl "ffiCl)R'
QllTCl{OI ~ CFf ~
GOVERNMENT OF INDIA
MINISTRY OF ENVIRONMENT AND FORESTS
vlGl
J Grl~lrll
I
'll:1 l! WII:Ti.fl II
F. No. 5-127/2008-RO (NZ)
~-31 ~, ~ 160030
Northern Regional Office,
Bays No. 24 &25, Sector 31·A,
Dakshin Marg, Chandigarh·160 030
Dated: 16.06.2014
-wrr1I
The Director(S), Monitoring Cell
q4iq~oI '(!Ci q;:r 4:;:rlcl4
q4iq~oI ~,
c>ffift m:,
-at."3ft.m.
CflIAI~CR"l
~ ~ I
Sub: Construction of Residential Group Housing Project named as
"Omaxe Greens" at village-Jharmari, Dera Bassi, Punjab by MIs
Omaxe Ltd.-site inspection regarding.
Ref. MoEF, New Delhi's letter No.21-408/2007-IA.11I dt. 08.05.2008.
~ ~ 1I \3WlRoCld qR4131O"fI '<t>I ~lffUI ~ 14th June, 2014 eN
~ 1FIT I ~ ~lffUI $ ~ ~ !T1ffUl! am qR4131O"fI 3IfuCflIR41 'R ~ $
qJG 3lal('1'81Il$fr &RT furR
1J{ 3fRim mrr
~ tBr ~ ~ ~
f,1 3IIlffi
f4:> 3lIq{?4ClJ CflI~('n~ CIRCb ~ CbI4icl4 eN ~. '4~ &RI
1J{ CflI~qI~ 'R 3lCPIff qm;f
eprr CD? I
3FJWr t
mt
FRw'r
mt
mt
~'o\~\\1\
(~epIR)
Ae{?ICfl(m)
Tel. No. (0172)-2638994
EMail:[email protected]
~:
Telephone No. : (0172) 2638061
Fax No.
: (0172) 2638135
~ahfm~
~-;io 24-25,
emm tRCf)R
~-311?, ~ 160030
qlllq{OI ~ CR ~
GOVERNMENT OF INDIA
MINISTRY OF ENVIRONMENT AND FORESTS
ijll:i ~
q(,T
d"ll/ll'!1 I
? l~11(,1J)
II
Northern Regional Office,
Bays No. 24 & 25, Sector 31-A,
Dakshin Marg, Chandlgarh-160 030
F. No. 5-127/2008-RO (NZ)
Dated: 16.06.2014
To
The Director(S), Monitoring Cell
Ministry of Environment and Forests
Paryavaran Bhawan, CGO Complex
Lodhi Road, New Delhi--110 003
Sub: Construction of Residential Group Housing Project named as
"Omaxe Greens" at village-Jharmari, Dera Bassi, Punjab by MIs
Omaxe Ltd.-site inspection regarding.
Ref. MoEF, New Delhi's letter No.21-408/2007-IA.1II dt. 08.05.2008.
Sir,
Please find enclosed herewith site inspection report of above cited project
which was inspected by the undersigned on 14th June, 2014. The salient features of
the non-compliance status of the environmental conditions is given below:­
The cleaning schedule of rainwater harvesting pits is yet to be submitted.
Energy Audit is yet to be carried out.
Latest physical and financial progress about CSR activities is yet to be
informed.
Uploading of six monthly progress report and monitoring reports on the web
4.
site of the Company is yet to be ensured.
.
.
Recommendations for action keeping In view the nature and extent of violation In
reference to Ministry's D.O. letter No.J-11014/267/2007-IA.II dated 25.06.2007.
1.
2.
3.
S.No.
1.
2.
3.
4.
Nature and extent of violation
No violation detected
Minor violations (not serious in
nature) detected.
Further course of action recommended
---­
implementation
As
regards
of
environmental safeguards laid down in
EC letter, only minor violations which
are not serious in nature have been
detected. Hence, a non-compliance
letter/suggestive letter is being written
to rectifylimprove them and submit 'An
action taken report'
Si!=)nificant violations detected.
NA
NA
Serious violations detected.
This is for your Information and necessary action please.
Yours faithfully,
~
(Surendra Kumar)
Director(S)
Tel. No. (0172)-2638994
EMail:[email protected]
Encls. : As above
Ministry of Environment & Forests
Northern Regional Office
Chandigarh
DATA SHEET
1.
Project Type:
2.
Name of the Project:
3.
4.
5.
6.
Construction Project
(Group Housing project named as "Omaxe
Greens")
Residential Group Housing Project by Mis
Omaxe Ltd.
No. 21-408/2007-1A.11I dated 8 1n May, 2008
Clearance letter (s)1 O.M No.
& dates:
Location:
a) District (s)
SA S Nagar
Punjab
b) State (s)
c) Latitudes/lonqitudes
75° 58' 76" East / 29° 49' 30" North
Address for correspondence:
Director(Business
Shri
Daleep
Maudgal,
a) Address of Concerned Project Development & Projects)
Chief Engineer
(with Pin Code/ MIs Omaxe Construction Ltd.,
Tel No./Telex/Fax No.1 E-Mail 7 Local Shopping Center, New Delhi-11 0019
address)
Tel. No. 011-41893100,41896680-85
41896776
FAX: 011-41896653,41896655,41896799
Cell No. 09818099256
Shri A.K.Srivastava, PI-9815503092
Shri Deepak Bhardwaj, Dy. Manager
Salient features:
The project involves the construction of a
a) of the project
residential colony on a plot area of 62,120.99 sq.
meters. The total built up area proposed is
sq.
meters(will
have
660
97,456.96
units/apartments-3 BR-450, 2 BR-150 and EWS­
60). Total water requirement proposed is 526 KLD
(Fresh water requirement will be 297 KLD and
treated waste water 861 KLD). The capacity of
STP proposed is 400 KLD. Treated waste water to
be used for flushing of toilets - 148 KLD,
horticulture -81 KLD and balance 171 KLD will be
used for irrigation of surrounding fields. Total
Solid
waste
generation
will
be
1320
(biodegradable-660 kg/day, non-biodegradable ­
396 kg/day and inert waste -264 kg/day).Total
power requirement is 4750 'rQN. Total parking
spaces proposed are for 1291 (basement-472,
covered parking -558 and open-261). Total cost of
the project is Rs. 71.165 crores.
~ HorticUlture activities initiated.
b) of the environmental
~
Rain water harvesting measures are taken.
management plans
~ Fire fighting facilities will be installed as per
existing norms.
~ Adequate car parking facilities are incorporated
in the project site to take care of traffic problem.
~ STP is installed.
--2-­
7.
Break up of the project area:
q
Break up of project affected
population
Financial details:
a) Project cost as originally
planned and subsequent
revised estimates and the year
of price reference.
b) Allocations made for
environmental management
plans with item wise and year
wise break up.
c) Benefit cost ratio/lnternal
Rate of Return and the year of
assessment.
d) Whether (c) includes the
cost of environmental
management as shown in b)
above.
e) Actual expenditure incurred
on the project so far.
t) Actual expenditure incurred
on the environmental
management plans so far:
Plot area
Built up area
Not applicable.
I
Not submitted
Yet to be submitted
Rs. 75.00 crore approx.
RS.10.00 lacs
11.
The status of clear felling in
non-forest areas
Status of construction:
a) Date of commencement June, 2008
(actual and/or planned)
14.
IRs. 71.165 crore
Sufficient funds have been provided for the
implementation
of
the
Environment
Management Plans.
Forest land requirement:
13.
62120.99 sq. meters
97,456.96 sq. meters
o::=J Original project cost:
10.
12.
-­
Approval from the I\JRO, MoEF,Chd. has been
obtained for the approach road to the project.
N.A.
b) Date of completion (actual 31.01.2013(Tentative).
and/or planned)
More than 85% of work has been completed
Reasons for the delay if the I\J.A.
project is yet to start:
Dates of site visits
a. Date of previous site visit:
21.06.2012
b. Date of present site visit:
14.06.2014
Participants
(A)
From MIs Omaxe Ltd.
1. Shri Oeepak Bhardwaj, Oy. Manager
(8)
From NRO,MoEF, Chandigarh
1. Shri Surendra Kumar, Oirector(S)
--3­
PART-II
STATUS OF COMPLIANCE
&
PART-III
DETAILED MONITORING REPORT
The project involves the construction of a residential colony on a plot area of
62,120.99 sq. meters. The total built up area proposed is 97,456.96 sq. meters(will have
660 units/apartments-3 BR-450, 2 BR-150 and EWS-60). Total water requirement
proposed is 526 KLD (Fresh water requirement will be 297 KLD and treated waste
water 861 KLD). The capacity of STP proposed is 400 KLD. Treated waste water to be
used for flushing of toilets -148 KLD, horticulture -81 KLD and balance 171 KLD will be
used for irrigation of surrounding fields. Total Solid waste generation will be 1320
(biodegradable-660 kg/day, non-biodegradable -396 kg/day and inert waste -264
kg/day).Total power requ(rement is 4750 KW. Total parking spaces proposed are for
1291 (basement-472, covered parking -558 and open-261). Total cost of the project is
RS.71.165 crores. The construction work was started at the project site in June, 2008.
There are in total 9 towers out of which the work at 5 towers have been occupied. At
other towers, the work is running in different stages. More than 85% of construction
work has been completed. The completion schedule is December, 2014.
The compliance of different conditions is given below:­
(A)
Specific Conditions:
1. Construction Phase
"Consent to Establish" shall be obtained from
PSPCB under Air & Water Acts and a copy shall be
submitted to the Ministry before start of any
construction work at site.
(i)
Being complied
The 'Consent to Establish'/NOC under Air & Water Acts was obtained by the project
proponent in time. The Consent to Operate under Air & Water Acts has been
obtained for the Towers which have been occupied but a copy of the same is yet
to be submitted.
(ii)
All
required
sanitary and hygienic measures
should be in place before starting construction
activities and to be maintained throughout the
construction phase.
Being complied
About 230 number of workers are engaged at work. It is gathered that the contractor
has been made responsible to provide all sanitary and hygienic conditions to the
workers during construction phase. Following measures have been taken by the
contractor for implementation of the condition:­
~
To provide adequate number of toilets (at least one for every 50 labourers) with
proper septic tank, vent pipe connector and soak pit for the construction
labourers separate for male and females.
--4­
~
~
'y
(iii)
To ensure proper disposal of sewage so that sanitary conditions are maintained.
To ensure regular cleaning of toilet and soak pits.
To ensure proper water sprinkler system on the construction sites to suppress
dust during handling of excavated soil.
A First Aid Room will be provided in the project Being complied
both during construction and operation of the
proiect.
The First Aid facilities have been provided at the construction site during construction
phase to take care of minor medical treatments. The PA has been asked to intimate the
expenditure done on providing medicines to the workers.
(iv)
Adequate drinking water and sanitary facilities
should be provided for construction workers at the
site. The safe disposal of waste water and solid
wastes generated during the construction phase
should be ensured.
Being complied
Around 230 workers have been employed by the contractor during construction phase.
It is confirmed that the construction site has adequate drinking and sanitary facilities for
the workers. Moreover, the contractor has made foolproof arrangement for disposal of
waste water and solid waste generated during the construction phase.
(v)
Provision should be made for the supply of Being complied
kerosene or cooking gas I pressure cooker to the
laborers durinQ construction phase.
It is gathered that only 230 no. of workers are engaged for the project. During active
construction phase the kerosene and LPG is being supplied by the contractor to the
workers on payment basis. However, the health, safety, sanitation and drinking water
facility for the workers is being ensured by the contractor as well as project authorities
during construction period.
(vi)
All the laborers to be engaged for construction
work should be screened for health and adequately
treated before the issue of work permits.
Being complied
It is informed that the contractor has provided necessary medical facilities to the
workers and First Aid Boxes are provided at the construction sites.
For disinfection of waste water, use ultra violet
radiation, not chlorination.
Being complied
One STP of 250 kid is functional. Ultra violet radiation is being used for disinfection of
the treated water. However, the compliance of this condition will be monitored by this
office from time to time.
--5­
(viii)
All the topsoil excavated during construction
activities
be
stored
in
should
for
use
horticulturellandscape development within the
proiect site.
Not applicable
No excavation has been started so far as there is stilt in the towers.
(ix)
Disposal of muck including excavated material
during construction phase should not create any
adverse effects on the neighboring communities
and disposed off taking the necessary precautions
for aeneral safetv and health aspects.
Being complied
It is confirmed that all the practical possible precautions are being followed in the whole
construction work to ensure that there is no nuisance to neighboring communities during
the disposal of muck including excavation mat!=rials.
(x)
Use of diesel generator sets during construction
phase should be enclosed type and should
conform to E(P)A Rules prescribed for air and
noise emission standards.
Being complied
It is observed that 2 DG set of 250 kva capacity have been provided with acoustic
enclosures at site for power back up.
I (xi)
I Diesel should be stored in underground tanks:
I Not applicable
At the moment, the diesel storage is hardly 900- 1000 litre at any moment. Hence, the
large storage of diesel are not required.
(xii)
Vehicles hired for bringing construction material to
the site should be in good condition and should
conform to applicable air and noise emission
standards and should be operated only during
non-peak hours.
Being complied
All the trucks are checked for their 'Pollution under Check' Certificates before entering
into project construction area. The PA has submitted the copies of few of the PUC's for
our record.
Ambient noise levels should conform to residential
standards both during day and night.
Being complied
The contractor has been instructed to keep all the construction activities in controlled
manner to keep the ambient noise levels within residential standards during day and
night time. It is also confirmed that there is no complaint from any person in
surroundings about high noise levels during construction period.
--6-­
(xiv)
Fly ash should be used as building material in the
construction as per the provisions of Fly Ash
Notification of September! 1999 and amended as
on August, 2003 (The above condition is applicable
only if the project is within 100 km of Thermal
Power Station).
Being complied
As the Ready Mixed Concrete is being used during construction, the fly ash from 22 to
25% is being used in the ready mixed concrete as per design mix.
Ready mixed concrete must be used in building
construction.
Being complied
As the Ready Mixed Concrete is being used during construction, the fly ash from 22 to
25% is being used in the ready mixed concrete as per design mix.
Storm water control and its re-use as per CGWS
and SIS standards for various a lications.
Being complied
It is assured by the PA that storm water will be stored and then reused as per CGWB
and BIS standards.
(xvii)
Water demand during construction should be
reduced by use of pre-mixed concrete, curing
a~ents and other best practices referred.
Being complied
This condition has been duly complied by the project proponent by reducing the
demand of the water by using the pre-mixed concrete, curing agents and other best
practices.
(xviii)
Permission to draw ground water shall be obtained
to
from
the
competent
Authority
prior
construction/operation of the project.
Being complied
It is confirmed by PA that there one bore well in the project site. The permission from
CGWA has been obtained by the PA for operation of the bore well.
(xix)
Separation of grey and black water should be done Being complied
by the use of dual plumbing line for separation of
grey and black water.
The project authorities have confirmed that the dual plumbing line is being provided in
only 4 towers which are will be completed very soon.
(xx)
Fixtures for showers! toilet flushing and drinking Being complied
should be of low flow either by use of aerators or
pressure reducing devices or sensor based
control.
As this is a Group Housing Project, there is not much scope of complying this condition.
--7-­
(xxi)
Use of glass may be reduced by upto 40% to
reduce the electricity consumption and load on
airconditioning.
If necessary, use high quality
double glass with special reflective coating in
windows.
Not applicable
­
As this is a Group Housing Project, there is not much scope of complying this condition.
(xxii)
Roof should meet prescriptive requirement as per
Energy Conservation Building Code by using
appropriate thermal insulation material to fulfill
requirement.
Being complied
The roofs meet prescriptive requirement as per Energy Conservation Building Code by
using appropriate thermal insulation material to fulfill requirement.
(xxiii)
Opaque wall should meet prescriptive requirement
as per Energy Conservation Building Code which
is proposed to be mandatory for all airconditioned
for non­
spaces while
it is aspirational
airconditioned spaces by use of appropriate
thermal insulation material to fulfill reauirement.
Not applicable
As this is a Group Housing Project, there is not much scope of complying this condition.
(xxiv)
The approval of competent authority shall be
obtained for structural safety of the buildings due
fire
fighting
to
earthquake,
adeguacy
of
equipments etc. as per National Building Code
includina orotection measures from liahtenina etc.
Being complied
It is informed by PA that this condition has been duly complied.
I (xxv) I Regular supervision of the environmental safeguards.
I Being complied
This condition is being complied by the project authorities.
(xxvi)
Legal action against the project proponent if the
construction work is started without ensuring the
environmental clearance.
No legal action is
required
The construction work at the project site was started only after ensuring the
environment clearance from the competent authority.
(2) Operational Phase·
(i)
The installation of STP should be certified by an
independent expert and a report in this regard
should be submitted to the Ministry before the
project is commissioned for operation.
Being complied
--8-­
The installation of Sewerage Treatment Plant having 250 KLD capacity extendable to
500 KLD has been completed. The PA has provided the UV system also with the STP
to disinfect the treated water.
(i i)
Rain water harvesting for roof run- off and surface
run- off, as plan submitted should be implemented.
Before recharging the surface run off, pre­
treatment must be done to remove suspended
matter, oil and !:Trease.
Being complied
Rainwater harvesting measures have been taken as per condition imposed by the
MoEF by providing 10 recharge pits with desilting chambers. The PA has been asked to
prepare the cleaning schedule for the Rainwater harvesting structures.
(iii)
The solid waste generated should be properly
collected and segregated before disposal to the
City Municipal Facility.
Being complied
It is informed that the practice of segregating bio-degradable and non biodegradable
waste is adopted and then the waste is disposed off by the project authorities by giving
to Municipal Committee's approved/designated places. However, the PA has been
asked to install the Organic Waste Converter for using the biodegradable material into
bio-compost.
(iv)
Any hazardous waste including bio-medical waste
should be disposed of as per applicable Rules &
norms with necessarv approvals of the PSPCB:
Assured to comply
As 3 DG sets of 250 kva each will be established for power back up and the waste
oilllubricant will be generated during their maintenance, the PA has been asked to
comply following measures in respect of disposal of waste oil/used oil which is
categorized as hazardous waste:­
>>>(v)
The lubricant/waste oil from DG sets should be collected in separate containers
with marking of "Hazardous waste" and the same may be disposed off by selling
to registered recyclers only.
A register will be maintained by respective companies to keep a record of
quantity of lubricant/waste oil generated by DG sets.
The project authorities will submit return in Form-4 and Form-13 to the PSPCB
every year with the copies to this office.
The green belt design along the periphery of the
plot shall achieve attenuation factor conforming to
the day and night noise standards prescribed for
residential land use. The open spaces inside the
plot should be suitably landscaped and covered
with veaetation of indiaenous variety.
Being complied
--9­
The green belt development has been started. About 2400 trees and 1500 shrubs have
been planted so far. About 23.5% of total plot area has been covered under plantation.
The PA has been asked to submit the details of plants planted with every six monthly
progress report in the following proforma:­
Year
(vi)
Area
covered
No. of plants
lanted
Incremental pollution loads on the ambient air Being complied
quality, noise and water quality should be
periodically monitored after commissioning of the
proiect.
The ambient air quality, ground water quality, stack emission, effluent at inlet and outlet
and noise level have been monitored by an approved lab namely Eco Pro Engineers
Pvt. Ltd., Ghaziabad in May, 2014 indicating all the results within permissible
limits. The project authorities have been asked to get the monitoring done on six
monthly basis and submit the reports to this office with six monthly progress reports.
(vii)
Application of solar energy should be incorporated
for illumination of common areas, lighting for
gardens and street lighting in addition to provision
for solar water heatinCl.
Not complied
It is confirmed that there is no provision of solar lights in the project so far.
(viii)
Traffic congestion near the entry and exit points
from the roads adjoining the proposed project site
must be avoided. Parking should be fully
internalized and no public space should be utilized.
Being complied
It is confirmed that separate entry and exit provisions and one way vehicular movement
has been made in the Residential colony. Thus the Parking will be fully internalized and
no public space will be utilized.
(ix)
A Report on the energy conservation measures
conforming to energy conservation norms finalized
by Bureau of Energy Efficiency should be prepared
incorporating details about building materials &
technology, R & U Factors etc. and submit to the
Ministry in 3 months time.
Being complied
Energy conservation measures conforming to energy conservation norms incorporating
details about building materials & technology and R & U factors etc. have been taken in
the design of the residential colony. It is informed that CFL lights are being used in
toilets and common areas. Detailed Energy Conservation Plan to be adopted by PA in
this project is yet to be submitted. The PA has been asked to get the Energy audit done
in respect of the energy conservation measures in the building in due course of time.
--10-­
'8) General Conditions:
(i)
The environmental safeguards contained in the Assured to comply
EIA Report should be implemented in letter and
soirit.
Although separate report has not been submitted by the project authorities about the
implementation status of environmental safegLJards contained in the EIA Report, the
PA has assured to comply most of the environmental safeguards satisfactorily.
submission
of six
monthly
progress
Being complied
The project has been monitored on 14.06.2014 and regular submission of six monthly
progress report is being ensured. The PA has been asked to submit six monthly
progress report in 1st week of December and 1st week of June every year in soft and
hard copies both as the report will be displayed on Web site of the Ministry of
Environment & Forests in pursuance of the provisions of new EIA Notification no.
1533(E) dated 14th September, 2006.
(iii)
Approvals from Chief Controller of Explosives, Fire
Department, Civil Aviation Department, Forest
(Conservation) Act, 1980 & Wildlife (Protection)
Act 1972 etc. should be obtained.
Being complied
It is informed that the clearances/NOC's from Fire Safety Department and Municipal
Council have already been obtained. The approval from Civil Aviation Department is not
necessary. The NOC's from Ministry of Environment & Forests under the Forest
(Conservation) Act, 1980 for the passage to the Residential Colony and 'Consent to
Operate' from PSPCB under Air & Water Acts have been obtained as more than 75%
families have started to reside in the completed 5 towers.
Copy of environmental clearance
advertised in two local newspapers.
should
be
Being complied
The environmental clearance has been advertised, in local news papers. Newspapers
cuttings are placed in the file.
(10)
Under the provisions of EPA, 1986, legal action Complied
shall be initiated against the project proponent if it
was found that the construction of the project had
started without obtaining environmental clearance.
The construction of the project has been started only after getting the environmental
clearance. Hence, no legal action is to be initiated against the project authorities.
(11 )
Environmental clearance is subject to final order of Assured to comply
the Hon'ble Supreme Court of India in the matter of
Goa Foundation Vs. Union of India in Writ Petition
(Civil) No.460 of 2004 as may be applicable to this
project.
--11-­
The PA has promised to follow the verdict of Hon'ble Supreme Court of India in the
matter of Goa Foundation Vs. Union of India in Writ Petition (Civil) No.460 of 2004 as
may be applicable to this project in due course of time.
~
(Surendra Kumar)
Direetor(S)
Ene!. as above: