3rd ENPCOM meeting in Extremadura
Innovation in energy managment of production activities and the
possible role of the public
Local experienses from Arvika
Presented by Thomas Malmstedt
Manager of the Arvika District Heating company and Arvika Hydropower company
Arvika in Sweden
Distance to:
Stockholm:
400 km
Oslo:
165 km
Gothenburg:
250 km
Heating plant Lycke
The company started in 1996
The main plant, Lycke, was built in 2000
It is located between two steel industries
to enable waste heat recovery
Main plant data:
Biomass, woodchips, bark
Biomass, pellets
Industrial waste
Availability, baseproduction
18 MW
6,5 MW
2,5 MW
>98%
Annual sales of heat,
110-120 GWh
CO2-reduction, yearly
ca 30 kton
(more than 90 % reduction)
Arvika District Heating System 2013, Mix of fuel
Industrial waste and
renewable fuel vs fossil
oil
Used fuel
0,5%
2,8% 1,2%
0,4%
Bark, flis, grot
4%
Rökgaskondensor
0,1%
Spillvärme, Gjuteriet
15,4%
0,2%
0,3%
2,3%
Spillvärme, Volvo
Spillvärme, Schott
Spillvärme, Smedjan
Spillvärme &
Förnyelsebart
Eldningsolja, fossil
Deponigas Mosseberg
14,7%
62,0%
Rötgas Vik
Pellets
96%
Eldningsolja 4
Eldningsolja 1
Cooperation - industrial waste heat
Nya Gjuteriet AB
Arvika Smide AB
Volvo Construction Equipment
The partnership began in 2003
-Replaced fossilfired boilers, 20 MW
-Installed equipment for district heating
-Installed equipment for recycling of waste
heat from furnaces.
-Annual sales of heat, 30-35 GWh
-Annual purchases of waste heat, 4 GWh
-CO2-reduction, yearly, 8500 ton
Local cooperation
Glava Energy Center is situated in the
community of Arvika, about twenty
kilometers south of the town. It´s goal is to
be a developing centre on a regional,
national and international level and be
open to companies and organisations,
active in the field of renewable and
efficient energy. It is also a centre of
energy for children and young people to
learn about energy.
It has grown up because of FEM, a big
transnational European project, about
energy and the interest of a local
company, and manufactures parts/panels
for solar energy.
A newly constructed solarpark is put into
operation this month
Total area 6000 m2, 1 MW/1 GWh