Muja Transformer Failure Market Impact Review – Final Update Martin Maticka Group Manager, Operations and Technology 9 October 2014 Background and Timeline Activities Since February Market Impact Summary 2 Timeline – Muja Bus Tie Transformer (BTT) Failures 2012 2014 SEP 2012 BTT1 Failed Replacement Delayed March July FEB 2014 BTT1 Replacement Delayed BTT2 Failed - BTT3 Single Contingency Dispatch of 2 Vinalco Units May April February June APR-MAY 2014 JUN 2014 Alinta Pinjarra 1 on Planned Outage Worsley Cogen on Planned Outage Worsley Cogen on Planned Outage 3 Vinalco Units Running August September October JUL 2014 AUG-SEP 2014 28 SEP 2014 Kemerton Line Commissioned 1 Vinalco Unit Running Alinta Pinjarra 1 on Planned Outage Replacement MT-BTTU Commissioned Vinalco no longer dispatched out of merit Source: Diagram by IMO 3 Background – Bus Tie Transformer (BTT) Failures at Muja To Guildford Load Area To Bunbury and Southern Terminal Load Area To Oakley and Southern Terminal To Northern Terminal To Southern Terminal Load Area To East Country Load Area Wells Terminal Boddington Narrogin South Terminal Alinta Wagerup Landwehr Terminal Wagerup To Bunbury Load Area Shotts Narrogin Collie Power Station Bluewaters Worsley Western Collieries Wagin To Bunbury Load Area Muja Terminal KEY EVENTS • BTT1 failed on 11 September 2012 • BTT1 replacement delayed • BTT2 failed on 23 February 2014 • BTT3 running as single contingency Collie Katanning Bridgetown Beenup Kojonup Manjimup Mount Barker Network Diagram Source: Diagram by IMO Albany Location Area Source: Diagram by System Management 4 Great Southern Generation – Full Summary Source: Diagram by IMO 5 Background and Timeline Activities Since February Market Impact Summary 6 Activities – Western Power 7 Activities – Western Power • Western Power considered a number of different options to improve the situation, not just those implemented [Shane Duryea, 14 May 2014] • Construction of a new transmission line between Kemerton and the existing Pinjarra-Busselton line was completed on 21 July. In the IMO view, this has significantly reduced the cost impact to market • Uprate of existing Rockingham-Waikiki transmission line completed on 24 August • Relocation of 132kV/220kV transformer from Merredin to Muja completed on 28 September 8 Network Upgrade 1: New Kemerton Transmission Line (21 July) PNJ APJ CLP WGP New Kemerton Line NGN NGS BDP KEM WCG BSI WAPL MRR WAG WOR BUH CO PIC CAP WCL MUJ WSD KAT BSN KOJ BTN MR BNP MJP MBR 330kV 220kV 132kV 132kV (new) 66kV ALB Source: Diagram by IMO 9 Network Upgrade 2: Rockingham-Waikiki Line Uprate (24 August) This was a “key enabler to allowing a major South West generator outage to proceed throughout most of September without the need to run a second Muja AB unit” [Cameron Parrotte, 30 September 2014] Source: Diagram by Western Power/IMO 10 Network Upgrade 3: Merredin Transformer (28 September) Dispatch Advisory issued at 09:12 on 28 September 2014: This Dispatch Advisory is to advise that MU-BTT2 has been put on load and stabilised. The existing Dispatch Advisories relating to the High Risk Operating State will be withdrawn and the SWIS will return to a Normal Operating State. Source: Photo Provided by Cameron Parrotte, Western Power 11 Activities – System Management 12 Challenges for System Management • System Management has to plan for credible contingencies, which do occur: – Worsley, WAPL behind-the-fence generation, Alinta Pinjarra 1 and Muja 1-4 have all tripped since 23 February – Muja to Bunbury Harbour and Picton to Marriott Road transmission lines have tripped • There is no scheduled generation south of Muja, which impedes management of load and voltage issues • Muja 1-4 start-up times varied from 24-72 hours • Initial lack of regional forecast information 13 System Management Dispatch Improvements • System Management commenced new daily regional load forecast process in July. Accuracy of forecasts was generally very good. • Detailed systems studies performed on the region allowed System Management to increase its load thresholds for dispatching Muja units • System Management were able to further increase these load thresholds following commissioning of the new Kemerton line and uprates of Rockingham-Waikiki line 14 29 Sep 27 Sep 25 Sep 389 23 Sep 412 21 Sep 458 19 Sep 17 Sep 435 15 Sep 13 Sep 11 Sep 9 Sep 7 Sep 5 Sep 3 Sep 1 Sep 30 Aug 28 Aug 26 Aug 24 Aug 22 Aug 20 Aug 18 Aug 16 Aug 14 Aug 12 Aug 10 Aug 450 8 Aug 6 Aug 4 Aug 2 Aug 31 Jul 29 Jul 27 Jul 25 Jul 23 Jul 21 Jul 19 Jul 17 Jul 15 Jul 13 Jul 11 Jul 9 Jul 7 Jul 400 5 Jul 3 Jul 1 Jul Actual Load (MW) Great Southern Regional Load vs Muja Dispatch Requirements 500 473 3 Muja Units 2 Muja Units 427 2 Muja Units 458 1 Muja Unit 412 385 350 300 250 200 150 System Managment data issue 100 50 0 1 July - 28 September 2014 - Trading days Source: Diagram by IMO 15 Impact of System Management Dispatch Improvements • Initial System Management dispatch plan (Most Likely Option): – July: two units on continuously; third cycled on/off weekly – August: two units on continuously – September: one unit on continuously; second cycled on/off weekly • System Management reacted effectively and responsively to: – Create regular and accurate load forecast profiles – Adjust dispatch thresholds following Western Power network improvements – Consider IMO’s dispatch advice on financial impacts when making dispatch decisions • Actual System Management dispatch: – July: two units on continuously; no third unit cycling – August: one unit on continuously; no second unit – September: one unit on continuously; no second unit cycling 16 Activities – IMO 17 Activities – IMO • IMO formed a dedicated specialist team, which worked with System Management to look for opportunities to reduce risks and costs to the market • IMO modelled potential options to reduce impact to market by – – – – Forming a base case of costs, modelled using SM indicative dispatch plan (Most Likely Case) Looking for cost effective alternatives to running Muja units using weekly regional forecasts Analysing accuracy of load forecasts Looking back at previous week’s forecast and analysing what actually happened • IMO provided advice to System Management based on analysis • System Management considered this advice in dispatch decision making while maintaining system security and reliability 18 “Most Likely” Scenario – SM Dispatch Requirements 100 90 80 IMO estimate 60 Muja Unit 3 50 Muja Unit 2 40 Muja Unit 1 30 20 10 30 Sep 23 Sep 16 Sep 9 Sep 2 Sep 26 Aug 19 Aug 12 Aug 5 Aug 29 Jul 22 Jul 15 Jul 8 Jul 0 1 Jul MW Target 70 Source: Cameron - Information by System Management 19 “Most Likely” Scenario – Total Additional Costs to Market Total constrained-on payments to Vinalco $25,000,000 $20,000,000 $15,000,000 Estimate @ July 2014 from 1st July onwards $8.83M $10,000,000 $7.21M $5,000,000 Price cap effective 1 July: $330/MWh $$100 $120 $140 $160 $180 $200 $220 $240 $260 $280 $300 $320 $340 Vinalco bid price Most likely - IMO estimate Most likely - SM plan Most likely forecast - IMO estimate Most likely forecast - SM plan Source: Diagram by IMO 20 Comparison of Forecast and Actual Costs Since 1 July 2014 • February to June: – Actual cost = $6.61M • July onwards estimates: – SM ‘Most Likely’ scenario – forecast cost based on forecast Balancing Prices and Vinalco bid prices at the start of July = $7.21M – SM ‘Most Likely’ scenario – cost based on actual Balancing Prices and Vinalco bid prices (impacted by repeal of carbon tax) = $4.95M 21 Dispatch Advice Estimated Costs • System Management provided GSR forecasts from the 29 July • IMO provided dispatch advice effective 29 July onwards • From 29 July to 28 September: – Estimated cost based upon SM “Most Likely” Dispatch Plan = $2.86M – Estimated cost of following IMO dispatch advice = $1.18M – Actual cost (est.) = $1.77M • Cost difference between SM “Most Likely” Dispatch Plan and Actual cost = $1.09M cost avoidance • IMO dispatch advice was based on energy requirements only. We did not have sufficient information to model voltage requirements • Further potential savings of $590k had System Management not required Vinalco for voltage support in September 22 Background and Timeline Activities Since February Market Impact Summary 23 Constrained On and Off Payments since February 2013 Month February (from 23rd) Vinalco Tesla/EnerNOC Other $208,340.10 $17,095.69 March $1,309,937.31 $642,208.05 April $1,157,141.49 $271,090.03 May $34,722.44 $632,782.33 June $3,810,422.41 July $1,944,094.46 $363,997.23 $789,159.40 $163,707.29 $848,446.39* TBC* August September (to 28th) Total $10,102,263.99 $93,674.74 $93,674.74 $378,604.73 $2,469,485.35+ * September settlement has not yet taken place. Vinalco figures are estimated. 24 Background and Timeline Activities Since February Market Impact Summary 25 Contingency Planning • System Management ensures that no single network failure leads to overload of another piece of equipment – otherwise, this could lead to a chain reaction. • Thresholds for the number of Vinalco Facilities needed are based on the amount of generation needed at Muja to prevent postcontingency overload. • This at times may make it seem that dispatch requirements are conservative when this is not the case – clearer information around this is needed 26 Energy Support • Requirement for Muja generation was initially driven by load in Great Southern region • Facilities further from region are less effective • Effectiveness can also be impacted by particular transmission lines at risk of overload • System Management calculated effectiveness factors for other facilities relative to Muja as amount of generation needed for same risk of postcontingent overload as 1MW at Muja Facility Effectiveness Factor Relative to Muja Muja 1-4 1 Tesla Picton 1 Worsley 0.9 Alinta Pinjarra 1 0.4 27 Voltage Support • Requirement for voltage support depends on both real and reactive load (inductive or capacitive) • System Management does not forecast reactive load • In security studies, System Management uses historical data with similar real load and weather as forecast • Security studies indicated that without MU-BTT2 and without Muja generation there were likely to be over-voltage postcontingent events overnight at Albany at Beenup • There could also have been under-voltage post-contingent events at particularly high evening peaks • System Management ran a Muja unit continuously to cover for the potential of these events 28 Summer 2014-15 - GSR • System Management has provided limits to run Vinalco units with the new transformer: – 412MW for first unit – 458MW+ for second unit • Based on current forecasts, System Management does not anticipate load reaching 458MW • Historical summer load not available • Great Southern Region is winter peaking • Highest load during July-September was 436MW 29 Next Steps • No longer in High Risk Operating State • System Management to dispatch the Great Southern Region as per normal operations • IMO and System Management will continue to monitor the situation in the region, however this is the last planned formal update 30 IMO Contacts Questions? Martin Maticka Group Manager, Operations and Technology [email protected] 31
© Copyright 2024 ExpyDoc