Element Power 3rd Floor Ben Dearg Suite Forsyth House 93 George Street EDINBURGH EH2 3ES T + 44 131 240 1237 www.elpower.com Binn Eco Park Wind Farm Community Liaison Group Meeting 10 July 2014 Minutes Present: Jeanette Thomson (JT) – Chair, Heather Kwiatkowski (HK) – Project Developer, Element Power Della Lansley (DL) – Project Director, Element Power Margaret Ponton, Glenfarg CC Bill Macpherson, Glenfarg CC Alan Muirhead, Auchtermuchty and Strathmiglo CC George Aitken, Auchtermuchty and Strathmiglo CC Cllr Henry Anderson, Almond and Earn Ward Cllr Alan Livingston, Almond and Earn Ward Apologies: Cllr Alan Jack, John Ferguson (Binn), Abernethy CC, Earn CC Chair’s Opening Remarks JT welcomed everyone to the meeting and started by explained that this year Element Power has increased its investment in Scotland by moving its UK operation to Edinburgh. It has also recruited a new and experienced team of individuals who all have a proven track record in the successful consenting and completion of the development of wind farm projects and the core skills and know-how to take projects from inception through to operation. Introductions then followed. Previous Minutes It was confirmed that the CLG had sight of previous minutes. The previous procedure for issue of meeting minutes was confirmed as informal. JT proposed a new procedure for issue and approval going forward. Draft Minutes would be issued and emailed to CLG members to amend/comment/approve within seven working days. Final, agreed minutes would then be issued to CLG members and stakeholders. This was agreed. Project Update Element Power Northern Europe Developments Limited Registered in England and Wales | Registered Office: Meridien House, 42 Upper Berkeley Street, London W1H 5QJ | Company Number: 7445420 Element Power 3rd Floor Ben Dearg Suite Forsyth House 93 George Street EDINBURGH EH2 3ES T + 44 131 240 1237 www.elpower.com The new EP team has been reviewing the design of the project, working closely with the Council’s Landscape Officer and EHO and Binn Farm Eco Park to achieve a design freeze. Since the last CLG meeting in February, the layout has changed to take account of the constraints on the site, to mitigate issues identified and to ensure that the design will produce renewable energy efficiently and at the same time be environmentally acceptable for the location in which it sits. The number of turbines has reduced from five to four and the height reduced from 125 m to 115 m. Overall installed capacity will be between 8 to 9.2 MW depending final turbine choice. Modelling is currently being undertaken on the Enercon E82 at 2.3 MW or Repower MM92 at 2.0 MW. Final selection of turbine will depend upon noise modelling at neighbouring properties. Key environmental design drivers have been landscape, noise and future plans for development at the Binn Farm Eco Park. Landscape – turbines have been moved to ensure a more coherent design from key viewpoints, as requested by the PKC landscape officer. A selection of wirelines and photomontages using the 3D model were shown to the group to demonstrate visibility. Noise - Element Power is working closely with the PKE Environmental Health Officer (EHO) and neighbours to ensure noise effects are mitigated appropriately. EP is currently meeting with property owners. Baseline surveys completed for ecology, ornithology, cultural heritage and hydrology. All information has been fed into the design process. Access – it is intended that construction traffic will come to site using the same route as Bin Eco Park from the M90 and A912 avoiding villages. EP were made aware of some of the issues faced by local people along this route and agreed to work closely with the CLG during the construction phase in order to mitigate any concerns that may arise. A Transport Management Plan will be prepared and agreed by PKC. EP confirmed that this would form part of contractor tendering process. CLG confirmed they would inform Element Power about local events to inform decisions on timing of deliveries. Cabling is to be undergrounded on site. EP to check regarding cabling from site substation at Abernethy. Following the meeting EP’s grid consultant confirmed that EP is still working with SHEPD to confirm the grid connection; however, it is almost certain that connection between our site substation and Abernethy will be entirely by underground cable. Exhibitions and Newsletter Element Power Northern Europe Developments Limited Registered in England and Wales | Registered Office: Meridien House, 42 Upper Berkeley Street, London W1H 5QJ | Company Number: 7445420 Element Power 3rd Floor Ben Dearg Suite Forsyth House 93 George Street EDINBURGH EH2 3ES T + 44 131 240 1237 www.elpower.com Element Power sought advice from CLG on exhibition venues & timings. Agreed that exhibitions in the four community council areas would be the preference (Glenfarg, Bridge of Earn, Abernethy, Gateside). JT said that exhibitions would be held at different times of the day to give everyone the opportunity to attend at least one event. Dates put forward were the 11th – 13th September. It was agreed that exhibitions will focus on the wind farm only and not the wider Binn Eco Park activities. CLG suggested Heartland Radio, Perthshire Advertiser and the Courier for advertising exhibitions. It was agreed that the newsletter would be distributed by mail to the 5,566 households identified within an 8 k radius of the site. Community Turbine MP briefed the CLG on the Glenfarg Renewable Energy Association’s interest in a community turbine. There was discussion about the Community turbine and background to the idea. JT directed the group to the CARES website for advice. John Ferguson has reiterated his commitment to provide land for a community turbine, provided that it is a joint community initiative which will benefit the four community council areas. It was confirmed that the potential project did not require input from Element Power. Discussion on structure for Community benefit JT confirmed that the community benefit package would be based on £5,000 per MW. There was a discussion about the importance of agreeing a community benefit memorandum of understanding between the four interested community councils and Element Power during the preconsent phase., It was agreed to hold a meeting in October to discuss community benefit and to invite Foundation Scotland, which administers the Lochelbank Fund. AOB JT to draft a Terms of Reference for the CLG which will include a clause confirming that attendance at CLG meetings does not imply support or otherwise for the wind farm. Terms of Reference to be discussed and agreed at the August meeting. Date of next CLG - 21 August 2014 Element Power Northern Europe Developments Limited Registered in England and Wales | Registered Office: Meridien House, 42 Upper Berkeley Street, London W1H 5QJ | Company Number: 7445420
© Copyright 2024 ExpyDoc