Presentation on Novozymes

Locimap Conference
Sille Bendix Larsen
2/28/2014
2
2/28/2014
NOVOZYMES PRESENTATION
Content of presentation
•
•
•
•
Introduction to Novozymes’ waste water treatment plant in
Kalundborg
From energy consumer to energy producer
Is it that easy?
More energy projects
CONTENT
3
28/02/2014
NOVOZYMES PRESENTATION
Environmental Operations on Site Ka
Environmental Operations Kalundborg
Wastewater and biomass treatment
Overview
Waste Water treatment
Facts
Waste water
9.500 m3/d ~ 3.5 m3/year
Treatment
Organic mat.
Nitrogen
Phosphorus
Organic material, Nitrogen, Phosphorus
152 ton/d -> CO2 & H2O
6 ton/d -> Atmospheric nitrogen
Chemical precipitation
COD Efficiency
98 % – the rest is treated at Municipal
waste water treatment plant
Biomass
NovoGro®30
4400 m3/d
410 ton/d ~ 150.000 ton/year
6
28/02/2014
NOVOZYMES PRESENTATION
Wastewater treatment
1° CLARIFIER
BIOLOGICAL
TREATMENT
ANAEROBIC/
AEROBOC
2° CLARIFIER
FLOTATION/DAF
WASTE WATER NZ
WASTE WATER NN
WATER
REUSE
KALUNDBORG
MUNICIPAL
WWTP
WAS
BIOMASS TO
INACTIVATION/DECANTERS
REJECT
WASTEWATER
SURPLUS
BIOMASS
RESIDUAL COD
TREATEED WITH
OZONE
200 mg/L to 75 mg/L
NOVO
ZYMES
PRESE
NTATI
ON
7
28/02/2014
NOVOZYMES PRESENTATION
Biomass treatment
INACTIVATION
DECANTERS
LAND APPLICATION
BIOMASS FROM
WASTE WATER
TREATMENT PLANT
BIOMASS
WASTE WATER
SOLIDS
STABILIZED
WITH LIME:
NOVOGRO30
BIOMASS FROM
PRODUCTION TO BE
INACTIVATED
STEAM: 90ºC – 1 HOUR
OR
CAUSTIC (pH > 11)
NOVO
ZYMES
PRESE
NTATI
ON
WASTEWATER
TREATMENT
PLANT
NovoGro30
150.000 t/year
Storage on farm land
Spreading by NZ
9
28/02/2014
NOVOZYMES PRESENTATION
Biogas at Novozymes Kalundborg
• Reactor capacity
≈ 55 ton COD/d
• CO2 reduction
≈ 20.000 ton/y
• Safety of operation
and expansion
possibility in focus
10
28-02-2014
NOVOZYMES PRESENTATION
Process and energy mass balance
Energi
Biomasse
Aerob proces
Renseanlæg
(MWh)
Før
Electricity
-17.500
+9.000
-6.500
-5.500
Damp
Fjernvarme
Total
Varme
N2/CO2
Biomass
Anaerob proces
Energi
+25.500
-24.000
29.000
Biomasse
Aerob proces
Varme
N2/CO2
Biogas
Efter
= energy
Corresponding to 7
Wind mills at
Horns Rev II
28/02/
2014
11
NOVOZYMES PRESENTATION
The process: UASB reactor
Upflow Anaerobic Sludge Blanket
Komplekst organisk
materiale
Hydrolytiske og
fermenterende bakterier
PAT
Mellemprodukter
(fx. alkoholer og carboxylsyrer)
Acetogene
bakterier
Acetat
CO2 + H2
IC-reaktor
Acetoclastiske
Hydrogenotrofe
Metandannende bakterier
CH4 + CO2
28/02/
2014
12
NOVOZYMES PRESENTATION
Technology
28/02/
2014
13
NOVOZYMES PRESENTATION
Is it that easy?
Nm3/h
1000
\\PIDK\CC$080NFT01
0,89
Nm³/h
900
800
Nm3/h
1000
\\PIDK\CC$080NFT01
301,13
Nm³/h
700
• 40% of flow from ”Brown city”
900
600
• New biomass inoculated Dec 2013
800
500
700
• No wastewater from ”Brown city”
400
600
300
• Production first started week 3-4 due to low
NN production load.
500
200
400
100
14-11-2013 09:31:34
Biogas flow
300
5,64 days
20-11-2013 00:47:20
200
100
18-11-2013 07:24:20
Biogas flow
6,27 days
24-11-2013 13:50:02
14
 Lab-scale: Inhibition tests (Raw materials)
Nutrient solution (anoxic): Outlet from biogas reactor
Potential toxic compound (dilutions)
Acetate (adjust pH)
Biomass
Run 1:
7 d, 35C
1. Release pressure
2. Acetate
Pressure (hPa)
1.
2.
3.
4.
400
350
300
250
200
150
100
50
Run 2:
3 d, 35C
0
0,00
0,50
1,00
1,50
Days
2,00
2,50
15
28/02/2014
NOVOZYMES PRESENTATION
Biomass – on site ‘liquid’ solution
biogas
BIOMASS FROM
WASTE WATER
TREATMENT PLANT
ANAROBIC
DIGESTION
Biomass: 1.5 mill m3/year
Reactor volume estimate:
100.000 m3
BIOMASS FROM
PRODUCTION
NOVO
ZYMES
PRESE
NTATI
ON
CONCENTRATION
OF BIOMASS
WASTE WATER
High on nitrogen
(1000 tons N/year)
READY TO SELL
PRODUCTS
SOLIDS
STABILIZED
WITH LIME:
NOVOGRO30
WASTEWATER
TREATMENT PLANT
Expansion for nitrogen
removal estimated at
2 bioreactors (~100
mill DKr)
Or an Anammox
16
28/02/2014
NOVOZYMES PRESENTATION
Biomass – off side ‘solid’ solution
BIOMASS FROM
PRODUCTION
DEWATERING
ANAEROBIC
DIGESTION
BIOMASS FROM
WASTE WATER
TREATMENT PLANT
DIGESTED MIX
OF MANURE AND
NOVOGRO FOR
LAND
APPLICATION
Dewatered
biomass
MANURE
Volume: 150.000 m3/year + Manure.
Land requirement for sustainable P
management: 8000 ha/year – 40.000
ha/5 years.
NOVO
ZYMES
PRESE
NTATI
ON
3 months application window for
liquid slurries.
17
28/02/2014
NOVOZYMES PRESENTATION
Liquid solution
LIQUID
SOLUTION
BENEFITS
BIOGAS VALUE ?
REDUCED COST FOR NZ GMO
INACTIVATION PROCES
6 MILL DKR/YEAR
CHALLENGES
ADDITIONAL NITROGEN REMOVAL
CAPACITY NEEDED ~ 100 MDKR
BIOGAS REACTOR VOLUME:
100.000 M3
DEWATERING AND STORAGE OF
DIGESTED SLUDGE.
NOVO
ZYMES
PRESE
NTATI
ON
WHERE DO
WE GO FROM
HERE?
18
28/02/2014
NOVOZYMES PRESENTATION
Off side ‘solid’ solution
SOLID
SOLUTION
BENEFITS
BIOGAS VALUE ?
REDUCED LIME CONSUMPTION
11 MILL DKR/YEAR
CHALLENGES
HECTARES NEEDED FOR
SUSTAINABLE P MANAGEMENT
8.000 HECTARE/YEAR
40.000 HECTARE/5 YEAR
LONG TRANSPORTATION OF
DIGESTED SLURRY
NZ/NN PRODUCTION SERURITY
NOVO
ZYMES
PRESE
NTATI
ON
WHERE DO
WE GO FROM
HERE?
19
2/28/2014
Questions?
Questions
NOVOZYMES PRESENTATION
CONTACT:
SBXL@NOVOZYMES.
COM