HALLIBURTON HES Field Camp El Reno Maintenance Building

May 20, 2014
HALLIBURTON
HES Field Camp El Reno
Maintenance Building
Revision-3 Narrative
Note: Please refer to revised drawings with clouds and delta ‘3’ for revision items which
incorporate changes and updates prompted by vendor comments.
ARCHITECTURAL
Sheet A-0.0
1.) Revised sheet index matrix for Revision 3.
Sheet A-1.2
1.)
2.)
3.)
4.)
Jib crane #3 relocated.
Service trench relocated.
Revised walls per furniture size.
Added partition type CC.
Sheet A-1.3
1.)
2.)
3.)
4.)
Revised walls per furniture size.
Added partition type CC.
Relocated millwork and door #1404B per furniture size.
Added partition type CC.
Sheet A-1.4
1.) Revised walls per furniture size.
2.) Relocated stair #6.
3.) Added partition type CC.
Sheet A-1.5
1.)
2.)
3.)
4.)
5.)
6.)
Revised walls per furniture size and PEMB channel.
Revised wall types callouts.
Revised Key Note #3 to be Mezzanine Channel.
Relocated door #2605
Revised millwork at WPS Kiosks 2515
Added partition type CC.
Sheet A-1.6
1.) Revised grids at Office 1109, Office 1110, and Sperry Office 1112.
Sheet A-1.7
1.) Revised grids at Office 1503.
Sheet A-1.8
1.) Revised grids at Cubicles 1604.
Sheet A-1.9
1.) Revised lights to be center of Test Cells along gridline 7
Sheet A-1.10
1.) Revised ceiling material at Stair 2010.
Sheet A-1.11
1.) Revised grids at Kiosks 2606, Men Lockers 2613, Women Lockers 2614, and IT
2615.
Sheet A-3.1
1.) Removed liner panel at building sections.
Sheet A-4.3
1.) Added liner panel to mezzanine wall at section 7.
Sheet A-7.1
1.)
2.)
3.)
4.)
Jib crane #3 relocated.
Service trench relocated.
Revised furniture layout at Sperry Office 1112.
Added GG to Furniture Legend
Sheet A-7.2
1.) Revised furniture layout at Warehouse Office 1404
2.) Added GG to Furniture Legend.
Sheet A-7.3
1.) Revised furniture size at cubicles 1604.
2.) Added GG to Furniture Legend.
Sheet A-7.4
1.) Revised furniture size at Kiosks 2111 and conference 2511
2.) Revised furniture layout at Kiosks 2606, Men Lockers 2613, and Women Lockers
2614.
3.) Added GG to Furniture Legend.
MECHANICAL
1.) Diffusers relocation due to minor changes on the RCP, affected sheets are:
MB-M1.2, MB-M1.3, MB-M1.4, MB-M1.6 & MB-M1.7
PLUMBING
Sheet P-1.2 and P1.5
1.) Relocated hub drain serving the service trench.
Sheet P-1.3, P3.2, and P4.4
1.) Relocated break room sink.
ELECTRICAL
Sheet E-1.0
2.) Added an equipment note.
Sheet E-1.2
5.) Adjusted data drops, printer receptacle to reflect architectural changes.
Sheet E-1.3
1.) Added additional communication conduit and communication pedestal.
2.) Added note 18 and 19.
Sheet E-1.4
1.) Deleted communication conduit.
2.) Added note 20
Sheet E-1.6
1.) Moved panels H11A and H12A against the wall.
2.) Adjusted data drops and power outlets to reflect architectural changes.
Sheet E-2.2
1.) Adjusted Light fixtures.
2.) Added a switch for test lights.
3.) Added a note 3.
Sheet E-2.3
1.) Adjusted light fixtures and switches.
2.) Added a test light.
3.) Added a note 3.
Sheet E-2.5
1.) Shifted light above test cell.
Sheet E2.6
1.) Adjusted light fixtures.
2.) Added an exit sign.
Sheet E-5.0
1.) Deleted a 100Amp Breaker to Sperry storage.
2.) Increase breaker size for panel H11A
3.) Increase the size of H11A panel.
Sheet E-5.3
1.) Revised circuits.
2.) Added a new circuit for test lights.
Sheet E-6.3
1.) Added a circuit for Test lights.
Sheet E-6.6
1.) Revised lighting fixture schedule.
3.)
End of narrative