Anchor Running Procedure for Stanislav Yudin Project Name : Loggs Platform Installation Project No.: 17.012 Prepared by SHL.17.012/PC/001 Rev. 0 : R. van Kranen Page 1 of 22 Preface Since this procedure will be Chapter 4 of the Offshore Installation Manual Volume 2, the different paragraphs of this procedure are numbered with number four (4). This preface and the Table of Contents will not be part of the procedure included in the Offshore Installation Manual - Volume 2 but will only be part of this document if the procedure is submitted for approval / information as a stand-alone document. SHL.17.012/PC/001 Rev. 0 Page 2 of 22 Table of Contents 4.1 4.1.1 4.1.2 4.1.3 4.1.4 4.1.5 Marine Procedures Introduction Compliance Equipment Personnel Responsibilities 4.2.1 4.2.2 Anchor Plans and Catenaries Anchor Plans Catenary Curves 4.3.1 4.3.2 Clearances and Restrictions Clearances Restrictions 4.4.1 4.4.2 4.4.3 4.4.4 4.4.5 4.4.6 4.4.7 4.4.8 Anchor Handling Procedures General Approach Anchor Running Mid-line buoy installation Anchor Positioning Test moorings Anchor retrieval Proposed Anchor Positions 4.2 4.3 4.4 4.5 Anchor Handling Records 4.6 Environmental Conditions 4.7 Contingencies General Anchor drag Mooring line failure Deteriorating weather Anchor recovery Missing buoy HLV Loss of Motive Power AHT Loss of Motive Power 4.7.1 4.7.2 4.7.3 4.7.4 4.7.5 4.7.6 4.7.7 4.7.8 4.8 SHL.17.012/PC/001 Drawings / Charts / Reports Rev. 0 Page 3 of 22 4.1 MARINE PROCEDURES 4.1.1 Introduction This procedure describes equipment, line of command and details of the method of deploying anchors of the HLV "Stanislav Yudin" at Loggs Riser Platform location. 4.1.2 Compliance The following procedures are in compliance with the Offshore Marine and Anchoring Procedures as laid down in Client's document No. CUK-L-IY-80XC00-002. Where required, changes may be implemented in mutual agreement between SHL and Client. They will apply to all vessels required, to approach or operate near installations during anchoring preparations of the HLV "Stanislav Yudin". 4.1.3 Equipment The standard vessel spread will consist of the HLV "Stanislav Yudin" and two (2) Anchor Handling Vessels. Both Anchor Handling Vessels will be of the open-sterned type, capable of decking the anchors. Only the lead AHV will lay anchors that cross or are placed adjacent to existing pipelines. The Anchor Handling Vessel(s) will be typical North Sea Class AHT. Since final commitments concerning hiring AHT are not yet in place, the particulars of the Anchor Handling Vessel(s) will be included in due course. Mobilization of the vessel spread will be described in section 3 of this document (Offshore Installation Manual - Volume 2). Prior to mobilization, the vessel(s) will undergo a suitability survey. This survey will be witnessed by the Client's Warranty Surveyor and will include a visual inspection of the vessel and examination of the validity of the certificates as laid down in Contract document LRP-C-02 / Exhibit "B" / part I / 6.8. SHL.17.012/PC/001 Rev. 0 Page 4 of 22 The HLV will be equipped with the appropriate surface positioning system for precise positioning of the anchors. This positioning system will comprise of: - One (1) DGPS receiver onboard the HLV and the lead AHV One (1) Laser positioning system onboard the HLV One (1) Laser positioning system spare One (1) Gyro Compass Information about the anchor spread is summarized in section 4.8 of this document. 4.1.4 Personnel The following critical personnel / parties will be involved during the anchoring operations: Seaway Heavy Lifting HLV Captain HLV 1st Officer HLV Captain's Advisor AHT Captain (Ass.) Superintendent Rigger Foreman with riggers Crane Operator Positioning Subcontractor Conoco Client's Marine Representative Loggs O.I.M. 4.1.5 Responsibilities The chain of Command and Communications for this operation will be as shown on the organization and communication chart included in section 4.8 SHL.17.012/PC/001 Rev. 0 Page 5 of 22 Responsibilities of the key personnel are as follows : Conoco Loggs O.I.M. Is responsible for all marine activities within the Loggs 500 metre zone. Anchor running and retrieval will not commence without prior approval of the O.I.M. Client's Marine Rep. Will witness the anchor handling operations and give approval where necessary. He will liaise with the HLV Captain and will keep the Loggs O.I.M. informed of all anchor handling operations. Will obtain approval to commence the anchoring operations from the Loggs O.I.M. Seaway Heavy Lifting HLV Captain Is responsible for all marine activities associated with tug movements and anchor laying within a one mile radius of the HLV. Will liaise directly with the Client Marine Representative. HLV 1st Officer Will assist the HLV Captain in anchor laying operations. Reports to the HLV Captain. HLV Captain Advisor Will assist/advise the HLV Captain during vessel operations in general and during anchor-handling operations in specific. (Ass.) Superintendent Responsible for all deck activities on board the HLV. Reports to the HLV Captain. Crane Operator Will transfer the pennants from the HLV to the anchor handling tug. Reports to the (Ass.) Superintendent. AHT Captain Responsible for running of anchors under the direction of the HLV Captain. Positioning Supervisor Responsible for setting up and operating all positioning equipment including DGPS and the HLV Laser Positioning System. Will report to the HLV Captain. SHL.17.012/PC/001 Rev. 0 Page 6 of 22 SHL.17.012/PC/001 Rev. 0 Page 7 of 22 4.2 ANCHOR PLANS AND CATENARIES 4.2.1 Anchor Plans (Patterns) Anchor Plans for the installation of the Loggs Riser Platform Jacket / Topside and Bridge are included in section 4.8 of this document. Since there will be a different set-up for both the Jacket / Topside installation and Bridge installation, there will be two separate anchor plans. 4.2.2 Catenary Curves Catenary curves for the appropriate water depth (20.5 M.) and covering the full range of working tensions ( 0-120 tonnes) are included in section 4.8 of this document. Normal operating tension range Maximum tension for pre-tension - 20/40 tonnes - 80 tonnes For mid-line buoy installation, "Segment 1" represents the distance from the anchor to the buoy and "Segment 2" represents the distance from the buoy to the HLV. SHL.17.012/PC/001 Rev. 0 Page 8 of 22 4.3 CLEARANCES AND RESTRICTIONS 4.3.1 Clearances This paragraph describes the clearances which will be observed by the HLV "Stanislav Yudin" at Loggs Riser Platform location. The following clearances apply : 4.3.2 (a) The initial setting up and tensioning of anchors will take place not less then 200 meters from any structure. Similarly the vesselwill be hauled off the same position for anchor recovery. (b) Mooring wires will at no time be run in such a way that they will ever come within 10 meters of the structure, unless it is deemed absolutely necessary and prior agreement is given by the Client's Marine Representative and the Loggs O.I.M. (c) No anchor will be placed closer than 200 m. from an installation. (d) Where a pipeline lies between the HLV and its anchor, the drag distance to the pipeline will not be less than 400 m. with a minimum direct distance between the pipeline and anchor of 200 m. (e) When mooring wires are crossing over a pipeline, the anchor pattern will be such that a minimum vertical clearance of the mooring above the pipeline of 10 m. can be maintained at lowest working tension (20 tonnes). If required this minimum vertical clearance will be maintained using chaser vessels and/or midline buoys. Restrictions This section describes the restrictions which will be observed by the HLV "Stanislav Yudin" at Loggs Riser Platform location. SHL.17.012/PC/001 Rev. 0 Page 9 of 22 4.3.2.1 Anchor running (a) No anchor will be passed from one vessel to another over or within the direct vicinity of any subsea installation or pipeline. (b) When an anchor is run over a pipeline, the anchor will be decked on an open-sterned anchor handling vessel, and secured with a second (preventer) wire of the same diameter as the main pennant. (c) The project specific catenaries will be used to determine minimum allowable wire tensions. (d) Anchor running at the working location will not start until the following conditions have been met : - - The Client representative is on board the vessel to monitor the anchoring. All surveyors and their equipment are ready. Weather forecasts for the next 72 hours have been seen by all concerned and a favorable weather window for the next 12 hours is forecasted (Beaufort 6 and decreasing). Permission to start has been agreed with by the Client. 4.3.2.2 Anchor Positioning (a) No anchor will be lowered unless the positioning surveyor confirms that its position will be within the intended target area. (b) If any undue delay occurs after confirmation that the position is acceptable, then the anchor will not be lowered, and the operation suspended until further instructions are received. (c) Once the anchor has been lowered the moment that it reaches the seabed will be reported to the positioning surveyor so that a check fix can be taken. During tensioning of the wires, lengths and tensions will constantly be monitored, until the vessel confirms that the anchor is set. The surveyor will then confirm and log the anchor position, and this record will be made available to the Client immediately on request and for a period of up to one year after completion of work. (d) No anchor will be moved or raised without prior agreement of the Client's Marine Representative, except in case of an emergency, but still to the SHL.17.012/PC/001 Rev. 0 Page 10 of 22 agreed Conoco procedures. SHL.17.012/PC/001 Rev. 0 Page 11 of 22 4.3.2.3 Anchor Line Tension Under normal operating conditions, the tension on any anchor line shall not exceed 33% of the minimum breaking load of the anchor line (MBL of the anchor wire is 238 mT). 4.3.2.4 Marker Buoys (a) Any buoy which can present a hazard to small vessels will, as far as possible, be designed and constructed of material which will minimize damage in the event of collisions. (b) Buoys will have the name or signal letters of the vessel to which they are attached at least 0.5 mtr. high painted in a color contrasting to the body of the buoy. SHL.17.012/PC/001 Rev. 0 Page 12 of 22 4.4 ANCHOR HANDLING PROCEDURES 4.4.1 General The Scope of Work in relation to anchoring procedures for the HLV "Stanislav Yudin" at Loggs Riser Platform location can be divided into two (2) phases : 1. 2. Installation of Jacket / Topside Installation of Bridge This section describes details of the method of deploying anchors. It should be emphasized that the anchor running sequence will be dependent upon tide, current, wave and wind direction and shall be decided by the HLV Captain at the time of anchor running. In case of pipelines, anchors will be run as much as possible with the HLV positioned between final anchor position and pipeline. This may involve repositioning of the vessel during the anchoring operation. 4.4.2 Approach When the HLV and attending tug(s) are approaching the installation site the Client Marine Control shall be informed and all vessel movements shall be notified to the Client Marine Representative. When on location the HLV shall manoeuvre into the required anchor running position using its own propulsion system, however in the event that prevailing weather and loss of power on the HLV could drift the vessel onto the Loggs Structures, a tug will be connected to the bow of the HLV. Recommended anchor running position is the "stand-off" position as indicated on the project specific anchor plans. The location of the HLV during the approach to the installation site shall be monitored using the on board DGPS navigation system. SHL.17.012/PC/001 Rev. 0 Page 13 of 22 The required platform centre line co-ordinates are : Latitude Longitude UTM-Zone Central Meridian Eastings Northings 4.4.3 53o-23'-27.1" N 002o-00'-15.4" E 31 3o East 433737.30 E 5916329.97 N Anchor Running The following sequence can be considered as normal running practice : (1) The pennant wire will be handed over to the anchor handling tug. (2) While paying out anchor wire from the HLV, spool the pennant wire onto the anchor handling winch, until the anchor reaches the AHT stern roller. (3) Run the anchor into position (4) Lower the anchor to the seabed by paying out the pennant wire (5) Attach the pennant buoy to the pennant wire and deploy the buoy. In case an anchor is run over a pipeline the anchor will be secured on the anchor handling tug as follows: (1) The pennant wire will be handed over to the anchor handling tug and spooled onto the anchor handling winch. (2) The anchor will be decked and secured with a second (preventer) wire of the same diameter as the main pennant. (3) After the anchor is run into position, release the preventer wire, gently lower the anchor over the stern roller by paying out the pennant wire and deploy anchor and buoy. SHL.17.012/PC/001 Rev. 0 Page 14 of 22 4.4.4 Mid-line Buoy Installation In the event that specified vertical clearance above a pipeline cannot be obtained by tensioning, anchor wire lifting buoys, i.e. midline buoys, will be attached to the anchor wire. Outlined below are two (2) methods of running anchors using mid-line buoys. These procedures may be altered due to weather conditions and shall be decided on board by the HLV Captain. Prior to commencement of work, the final mid-line buoy installation procedure will be agreed between all parties concerned. Option A (1) The anchor will be decked on board the AHT and disconnected from its anchor wire. (2) The anchor wire will be spooled on a AHT winch for a distance equal to the distance between the anchor (in position) and the position of the midline buoy. Mid-line buoy is now attached to the anchor wire on board the AHT. (3) (4) AHT proceeds to mid-line buoy position while anchor wire is paid out from the HLV. (5) Deploy mid-line buoy and proceed to anchor location point by paying out anchor wire from the AHT. (6) Attach anchor to anchor wire and deploy anchor and pennant buoy. SHL.17.012/PC/001 Rev. 0 Page 15 of 22 Option B 4.4.5 (1) Anchor will be decked and secured with a second (preventer) wire of the same diameter as the main pennant. (2) When the tug has steamed a distance equal to the distance between the anchor (in position) and the cross point anchor line / pipeline she will stop and maintain her position. (3) The anchor line will then be pulled onto the deck of the HLV and the mid-line buoy shall be connected to the anchor line. (4) After this the anchor line and buoy will be lowered into the water. (5) The tug will then pick-up tension to clear the anchor wire from the seabed. (6) When the tug is in final position, deploy anchor and pennant buoy. Anchor Positioning The anchors will be positioned at the location indicated on the relevant anchor plan. The anchor handling tug positioning will be monitored using DGPS and a Laser system. The ships radar system will function as back-up. Before permission is given to lower an anchor, the position of the anchor handling tug relative to the HLV will be checked and marked on the anchor plan. The tension will be released in the anchor line and the anchor lowered to the seabed. The "as installed" position of each anchor will be shown by a large surface pennant buoy. Anchor handling tug(s) will remain on station until successful pre-tension has taken place. SHL.17.012/PC/001 Rev. 0 Page 16 of 22 4.4.6 Test Moorings When all anchors have been laid, the anchor will be proof loaded (test load) at 80 tonnes for a 15 minute period to ensure the anchors have adequate holding capacity. If an anchor does not hold it will be recovered by the AHT and redeployed. 4.4.7 Anchor Retrieval The anchor retrieval sequence will be dependent on wave and wind directions and will be decided by the HLV Captain at the time of demobilization. Retrieval of anchors will be monitored by the survey / positioning system and/or vessel radar system. Anchors will only be recovered to the HLV when they are secured close against the stern of the anchor handling tug. When recovering an anchor, the anchor handling tug shall not move from its position above the anchor, until the anchor has been lifted to the surface. The anchors will be retrieved to the same method as detailed in the anchor running methods in 4.4.3 and 4.4.5 During anchor retrieving anchor line tensions will be checked and verified with the limitations stated in section 4.3.2.1 and 4.3.2.2 Prior to departing from location, the Captain of the installation vessel shall obtain clearance from the Client Marine Control and state departure time and destination. SHL.17.012/PC/001 Rev. 0 Page 17 of 22 4.4.8 Proposed Anchor Positions Information about the proposed anchor positions is summarized in Table 4.2 below. For the anchor patterns, reference is made to section 4.8 of this document. Anchor Positions Jacket/Topside Installation Anchor Positions Bridge Installation Anchor number Eastings Northing s Eastings Northings 1 (S1) 2 (S2) 3 (S3) 4 (S4) 5 (P4) 6 (P3) 7 (P2) 8 (P1) 433140 433643 434644 434536 434016 433285 432635 432698 5917366 5917413 5916753 5916056 5915475 5915548 5916427 5916931 433440 433643 434644 434016 433285 432635 432698 5917437 5917413 5916753 5915475 5915548 5916427 5916931 Table 4.2 - Proposed Anchor Positions SHL.17.012/PC/001 Rev. 0 Page 18 of 22 4.5 ANCHOR HANDLING RECORDS The positioning of the anchors will be monitored as follows: a) A positioning Subcontractor will be used to operate the DGPS system. The anchor positions will be recorded of co-ordinated positions and a plot plan, or calculated co-ordinates from bearings and distances from either the HLV or an adjacent platform using the DGPS system. b) The positioning may be monitored from the HLV radar and subsequently plotted on the anchor pattern drawing. The final position of the anchors will be recorded on the anchor running report (see section 4.8) This report, when signed by the Captain, together with any printouts or plans necessary, shall be submitted to the Client Marine Representative. The Client Marine Representative shall return the reports to the Field Engineer for enclosure within the "As-Built" documentation package. In addition, all anchor line tensions during anchor running and when in position, together with the anchor positions shall be recorded in the vessels log. All information shall be kept on file for further reference. SHL.17.012/PC/001 Rev. 0 Page 19 of 22 4.6 ENVIRONMENTAL CONDITIONS Based on the available information, the following environmental conditions can be expected during the anchor operations of the HLV "Stanislav Yudin" at the Loggs Riser Platform location: Maximum current Speed / Direction 3 knots (1.6 M/S)/ NW-SE Average wind Speed / Direction 14 knots (7.2 M/S)/013E Average waves Height / Direction 1.28 M / 195E Significant Waves Height / Period 2.10 M / 5 sec. Water depth 20.5 M from LAT Table 4.3 - Environmental summary During anchor running the only weather restriction that applies is the motion of the anchor handling tug(s) and their ability to maintain position during the handling and placing of anchors. A 12 hour fair weather forecast (Beaufort 6 and decreasing) is recommended before anchor running commences and visibility should be maintained between the HLV and anchor handling tug(s). SHL.17.012/PC/001 Rev. 0 Page 20 of 22 4.7 CONTINGENCIES 4.7.1 General The contingency procedures as described in this section, should be read in conjunction with the relevant sections of these anchor handling procedures. All decisions and activities will be agreed with the Loggs O.I.M. prior to any action taking place, unless remedial action is required to safeguard the platform complex and/or vessel spread. If remedial action is required, the Loggs O.I.M. will be notified as soon as possible. 4.7.2 Anchor Drag Whenever an anchor drags or is dropped accidentally in a prohibited zone, the anchor cable will be slackened and no further remedial action taken without the prior consultation with the Client Marine Representative except that at the same time preparation should be made to lift the anchor. If slackening does not eliminate risk of the anchor dragging then the cable should be slipped or cut and the position of the bitter end accurately recorded. If practicable the end should be buoyed for recovery. 4.7.3 Mooring Line Failure In the event of a mooring line failure, the HLV Captain shall adjust the tension on remaining anchors to maintain the vessel safely in position, until remedial action to retrieve and re-attach the anchor can be taken. The Client Marine Representative will be advised accordingly. The anchor shall be re-deployed in accordance with section 4.4 4.7.4 Deteriorating Weather In the event of deteriorating weather conditions the HLV Captain and Superintendent shall agree their intended course of action and advise the Client Marine Representative. He will in turn inform and discuss the course of action with the Loggs O.I.M. SHL.17.012/PC/001 Rev. 0 Page 21 of 22 4.7.5. Anchor Recovery If for any reason anchors are not recovered before the onset of severe weather the attendant or available vessel or vessels should be made fast to windward and utilized to ease the strain on the weather moorings. When any vessel requires to recover the anchors in bad weather her own ability or that of the designated towing vessel or vessels to hold the moored vessel to windward or uptide should be tested prior to commencing recovery. In the event that there is insufficient power or time available, then depending on circumstances, slipping of moorings may be the most appropriate action to safeguard existing structures or pipelines. 4.7.6 Missing Buoy In the event of a buoy being lost, the Client Marine Representative will be advised immediately. In case of a missing buoy, other than small plastic buoys, the relevant Coast Guard authority will be informed immediately, giving the following details: (a) (b) (c) (d) Size, color and marking of the buoy Time buoy was last sighted Probable speed and direction in which buoy is drifting Action being taken to locate and recover In view of the potential hazard to shipping, a seabed search to ascertain whether the buoy has sunk and a vessel search of the area shall be performed. The results shall be communicated to the relevant Coast Guard authority. SHL.17.012/PC/001 Rev. 0 Page 22 of 22 4.7.7 HLV Loss of Motive Power Reference is made to the "Marine Risk Assessment Report" prepared by Offshore Marine Contractors b.v. In the event of a black-out during anchoring operations, the course of action will depend on the stage in which the anchoring operation has progressed. * In case failure occurs when entering the 500 m Safety Zone, tow HLV to a safe area outside the 500 m Zone. * If, due to prevailing weather and a insufficient number of anchors positioned, the HLV could drift onto the Loggs Structures, the HLV willbe moved to a safe area outside the 500 m. zone. If there is no danger of drifting towards the Loggs Structures, anchoring operations will be continued. * when HLV is completely anchored, connect tug if required. 4.7.8 AHT Loss of Motive Power Reference is made to the "Marine Risk Assessment Report" prepared by Offshore Marine Contractors b.v. In the event of a black-out during anchoring operations, the course of action will depend on the stage in which the anchoring operation has progressed. * In case failure occurs when entering the 500 m Safety Zone, maintain position with other tug and suspend anchoring operations. * In case failure occurs when running anchors, use HLV propulsion system and lower anchor in a safe area. If there is a change that the AHT will drift onto the Loggs Structures, connect the second tug and tow to a safe area. 4.8 DRAWINGS / CHARTS / REPORTS - Organization and communication chart Summary of Mooring Equipment Anchor plans Catenary curves Anchor running report SHL.17.012/PC/001 Rev. 0 Page 23 of 22 SHL.17.012/PC/001 Rev. 0 Page 24 of 22 Qty Qty Spare Description 8 1 Mooring Anchor - 10 tonnes Delta Flipper 8 Mooring winch - Electrical Variable Speed - Max. pull = 1800 kN (= 180 tonnes) - Max breaking load = 2590 kN (= 259 tonnes) 8 Mooring wires - Length - Diameter - Construction - MBL - Weight = 2100 m = 61 mm. = 6 * 36 WS + IWRC = 238 tonnes = 15.5 Kg/m (10.4 lb/ft) 8 Pennant wires - Length - Diameter - Construction - MBL - Weight = variable to depth = 61 mm. = 6 * 36 WS + IWRC = 238 tonnes = 15.5 Kg/m (10.4 lb/ft) Pennant buoys - Brand - Type - Material = "Dynoplast A.S - Scanmarin" = Modular - 3 module floats = Polyethylene skin and polyurethane core = 6 tonnes 4 min. 2 or equiv. - Buoyancy - Brand - Type - Material 4 - Buoyancy 4 Mid-line buoys - Brand - Type - Material - Buoyancy 8 Fairleads - Height = "Floatex" = Modular - 3 module floats 18/60 = External rationally moulded crosslinked polyethylene and filled with ridged expanded polyurethane. Central structure of the buoy is hot galvanised = 6 tonnes = "Floatex" = Modular - 6 module floats 18/120 = External rationally moulded crosslinked polyethylene and filled with ridged expanded polyurethane. Central structure of the buoy is hot galvanised = 12 tonnes = 6.1 m above water level at mean operating draft Summary of Mooring Equipment SHL.17.012/PC/001 Rev. 0 Page 25 of 22
© Copyright 2024 ExpyDoc