Pre Jobs Pre Job 9853 9769 9852 9871 9870 9869 9868 8898 9851 Start Date 2/4/15 2/2/15 2/2/15 2/1/15 2/1/15 2/1/15 2/1/15 1/30/15 1/28/15 Approx. End 2/11/15 5/31/15 3 weeks 12/31/15 12/31/15 12/31/15 12/31/15 5/30/15 2/20/15 Contractor Otis Eastern Minnesota LTD Frank Lill and Son Mid Ohio Contr Mid Ohio Contr Mid Ohio Contr Mid Ohio Contr U S Trinity Energy B Miller Excavating Gas Company Hours & Wages & Perdiem Job Description & Welding Test if Available Warehouse Location Welder Foreman Warehouse Phone Spectra Energy 6 X 10 W & J - 51.92 H - 26.76 W - 102.50 J & H - 42.50 Installation on 20 inch interconnect Waynesburg, PA Jimmy Patrick N/A Enbridge Energy 5 X 10 W & J - 51.92 H - 24.12 W - 102.50 J & H - 42.50 Donaldson & Plummer Pump Station Construction Donaldson, MN Brandon Olson N/A Kinder Morgan 6 X 10 W & J - 51.92 H - 31.73 W - 102.50 H - 42.50 1 inch - 3 inch Glycol / Station Work Lockport, NY N/A 585/953-0413 NiSource TBA W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 Emergency Call Out Work Dover, OH TBA N/A Mark West TBA W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 Emergency Call Out Work Dover, OH TBA N/A EQT TBA W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 Emergency Call Out Work Dover, OH TBA N/A Dominion TBA W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 Emergency Call Out Work Dover, OH TBA N/A Sunoco Pipeline LP 6 X 10 W & J - 40.00 H - 20.00 W - 102.50 J & H - 42.50 Compressor Station Hermleigh, TX Troy Rice 214/288-7548 H G Energy 5 x 10 W & J - 40.00 H - 20.00 W - 102.50 J & H - 42.50 8 inch & 12 inch piping / complete fabrication & tie ins Pine Grove, WV N/A N/A 2/4/2015 9:31 AM Pre Jobs 9840 9836 9838 9837 9839 9189 9835 9833 9850 9848 9841 1/28/15 1/26/15 1/26/15 1/26/15 1/26/15 1/26/15 1/26/15 1/26/15 1/26/15 1/26/15 1/26/15 3/21/15 12/31/15 12/31/15 12/31/15 12/31/15 3/15/15 3/28/15 12/31/15 2/21/15 4 weeks 12/31/15 Michels Pipeline Minnesota LTD Minnesota LTD Minnesota LTD Minnesota LTD Minnesota LTD Ace Pipeline Contractors Rental Evets Oil & Gas Northern Natural Gas 6 X 10 W & J - 51.92 H - 28.95 W - 102.50 J & H - 42.50 1,800 feet of 16 inch HDD replacement Berglund, MI Johnny Gardner 920/273-9615 none TBA W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 Shop Work Dover, OH TBA N/A Dominion TBA W & J - 51.92 H-OH-30.16 KY-22.85 W - 102.50 J & H - 42.50 emergency call out work Dover, OH TBA N/A Vectren TBA W & J - 51.92 H-OH-30.16 KY-22.85 IN-25.74 W - 102.50 J & H - 42.50 emergency call out work Dover, OH TBA N/A Columbia Gas TBA W & J - 51.92 H-OH-30.16 KY-22.85 W - 102.50 J & H - 42.50 emergency call out work Dover, OH TBA N/A Vectren 6 X 10 W & J - 51.92 H - 25.74 W - 102.50 J & H - 42.50 3,500 feet of 12 inch mainline Clarksville, IN Timothy (Scott) Kidd N/A Blue Racer 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 18,000 feet of 16 inch and 1,500 feet of 10 inch Morristown, OH Jerrett (Chad) Thomas 740/782-1043 various cities in KY, OH, IN, and MI TBA N/A Marathon Stat Oil 9768 8896 9846 1/20/15 1/15/15 1/14/15 1/14/15 3/31/15 3 months 6/15/15 blanket 6 X 10 W & J - 43.00 H - 26.00 W - 125.00 J & H - 65.00 1 inch to 10 inch piping Compressor Station Center Point, WV Jeffery Mooney 832/214-6716 1,700 feet of 6 inch steel list & lay/launcher & receiver Johnstown, PA Tim Schwendiman N/A EQT 5 X 10 W & J - 51.92 H - 26.76 W - 102.50 J & H - 42.50 none TBA W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 shop work Marietta, OH TBA 740/374-4100 Latex Constr 6 X 10 W & J - 38.70 H - 17.14 W - 92.50 J & H - 32.50 deconditioning 12 inch, 16 inch, 20 inch, 24 inch, and 36 inch lines Chamblee, GA Wayne Bates 770/455-7413 Geeding Constr Inc. 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 bolt up 2 - 20 inch operators Drumright, OK Wayne Brown 314/486-5361 88.65 miles of 36 inch mainline 1/2 36" DH 6010 bead & HP F&C 8010 G Rosenburg, TX John White N/A on going blanket Coraopolis, PA David Butterworth 724/947-2235 Minnesota LTD Quest Constr Atlanta Gas and Light 9796 TBA W & J - 51.92 H-KY-22.85 OH-30.16 IN-25.74 MI-28.95 emergency call out W - 102.50 H - 42.50 work Rockford Corp Alex Paris Const. Spectra 6 X 10 Enterprise W & J - 41.28 H - 18.28 (Rancho Pipeline) W - 102.50 J & H - 42.50 CNX 5 X 10 W & J - 51.92 H - 26.76 W - 102.50 J & H - 42.50 2/4/2015 9:31 AM Pre Jobs 9829 9828 9843 9867 9764 9761 1/14/15 1/13/15 1/12/15 1/12/15 1/12/15 1/12/15 2/14/15 5/31/15 3/1/15 3/15/15 3 to 4 weeks 3/15/15 Minnesota LTD Minnesota LTD Contractors Rental Charps Welding Geeding Constr Inc. Minnesota LTD Rice Energy 5 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 1 - 24 inch and 1 - 16 inch launcher 12" 45 250 wall & upside down 12" Branch 375 wall DH Dover, OH Aaron Shrontz 330/343-4612 Enbridge Energy 5 X 10 W & J - 51.92 H - 28.95 W - 102.50 J & H - 42.50 integrity and maintenance work in MI and WI Iron River, MI Kenneth White N/A 6 X 10 W & J - 51.92 H - 26.76 W - 102.50 H - 42.50 3 miles of 24 inch steel & 3 miles of 18 inch poly New Lay 12" 45 375 wall puddle cap & 12" Branch 375 wall 2 bead cap Bentleyville, PA James Thompson 304/962-0176 Enbridge Energy 6 X 10 W & J - 51.92 H - 24.12 W - 102.50 H - 42.50 Integrity sleeving in MN & ND 1.) 6" 45 7016 UH 7018 out 280 wall, 2.) 8" 45 500 wall, 3..) 2" 45 218 wall 6010 UH HP 7018 out, 4.) 12" Sleeve Test 375 wall, 5.) 6" Branch 7018 out Thief River Falls, MN Dale Hamnes 989/254-7117 TransCanada 6 X 10 W & J - 51.92 H - 28.74 W - 102.50 J & H - 42.50 36 inch fab in Troy shop install in Minor County, SD Troy, MO T J Luck 314/486-5361 6 X 10 W & J - 51.92 H - 24.12 W - 102.50 J & H - 42.50 Integrity work & misc call out 1.) 6" 45 250 wall 7016 bead UH 8018 out, 2.) 8" 45 500 wall 5P+ bead UH DH 8010 HP 8018 UH out, 3.) 2" 45 250 wall 5P+ bead UH DH HP 8018 out, 4.) 6" OPEN BRANCH 250 wall 7018 bead 7018 out, 5.) 12" IN SEVICE SLEEVE 500 wall 7018 out Bemidji, MN Levi Novacek N/A Rice Energy Enbridge Energy 2/4/2015 9:31 AM Pre Jobs 9775 9744 9827 9825 9823 9765 1/12/15 1/12/15 1/12/15 1/8/15 1/7/15 1/7/15 3/15/15 2/28/15 3/15/15 3/31/15 2/15/15 2 to 3 weeks Enbridge Energy 6 X 10 W & J - 51.60 H - 22.85 W - 102.50 J & H - 42.50 Integrity work & misc call out 1.) 6" 45 250 wall 7016 bead UH 8018 out, 2.) 8" 45 500 wall 5P+ bead UH DH 8010 HP 8018 UH out, 3.) 2" 45 250 wall 5P+ bead UH DH HP 8018 out, 4.) 6" OPEN BRANCH 250 wall 7018 bead 7018 out, 5.) 12" IN SEVICE SLEEVE 500 wall 7018 out Berthold, ND George Kingsland N/A Williams Field Services Co 6 X 10 W & J - 51.92 H - 26.76 W - 102.50 J & H - 42.50 2.5 miles of 24 inch 12" 45 375 wall puddle cap & 12" 375 wall branch Montrose, PA Jesse Davis 570/278-0200 Enbridge Energy 6 X 10 W & J - 51.92 H-MI 28.95 IN-36.74 W - 102.50 J & H - 42.50 34 inch deactivation oil recovery Menden, MI Steve Jackson N/A Rice Energy 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 18,000 feet 16 inch steel, 18,000 feet of 18 inch HDPE, and 1,500 feet of 8 inch Bellaire, OH Dick Swiger 678/677-96425 CBC Pipeline Mark West 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 H - 42.50 10,492 feet of 6 inch and 2,270 feet of 6 inch new lay Morristown, OH George Houston 740/942-0440 B & G PIPELINE Southwestern Energy 4 X 10 W & J - 38.70 H - 17.14 W -92.50 J & H - 32.50 bolt up on launcher & received charcoal filters Searcy, AR N/A 501/3058-3677 Minnesota LTD Rockford Corp United Piping Otis Eastern 2/4/2015 9:31 AM Pre Jobs 9743 9763 9824 9203 9822 9821 9820 1/6/15 1/6/15 1/5/15 1/5/15 1/2/15 12/29/14 12/29/14 6/19/15 2 to 3 weeks 12/30/15 1/20/15 4/15/15 3/1/15 3/1/15 Infrasource Geeding Constr Inc. Henkels & McCoy W A Rasic Price Gregory Mid Ohio Contr Mid Ohio Contr Baltimore Gas & Electric 5 X 10 W & J - 51.92 H - 24.81 W - 102.50 J & H - 42.50 16,500 feet of 12 inch steel Westminster, MD Jim Bellinghausen 707/580-8952 TransCanada 6 X 10 W & J - 51.60 H - 22.85 W - 102.50 J & H - 42.50 pig run from Cushing OK to Nederland, TX Cushing, OK N/A N/A Buckeye 5 X 10 W & J-51.92 H-OH-30.16 MI-28.95 IN-25.74 W - 102.50 H - 42.50 various anomaly digs Wakeman, OH N/A N/A Kinder Morgan 5 X 10 W & J - 52.50 H - 22.85 W - 102.50 J & H - 42.50 1200 feet of 12 inch relocation, restart Eloy, AZ Kevin Nichols 310/864-0310 Rice Energy 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 8 miles of 30 inch and 15800 feet of 24 inch 12" 45 375 wall & 12" Branch 375 wall Cambridge, OH Stan Campbell 918/605-5687 Mark West 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 9,624 feet of 20 inch new lay 12" Branch 375 wall & 12" 45 375 wall Belmont, OH Ryan Frey N/A Mark West 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 18,547 of 24 inch new lay 12" Branch 375 wall & 12" 45 375 wall Belmont, OH Mike Leasure N/A 2/4/2015 9:31 AM Pre Jobs 9795 9758 9816 9742 9739 9736 9199 9738 9195 9196 9793 9192 12/18/14 12/17/14 12/15/14 12/15/14 12/11/14 12/10/14 12/10/14 12/8/14 12/1/14 12/1/14 12/1/14 12/1/14 undetermined 2 to 3 months 3/15/15 on going 1/15/15 2/18/15 1/9/15 on going 12/31/14 1/10/15 undetermined 1/27/15 Florence Gas 5X8 W & J - 38.70 H - 17.14 W - 92.50 J & H - 32.50 10 inch pressure loop connection Florence, AL N/A 256/718-2041 Center Point Energy 5 X 10 W & J - 38.70 H - 17.14 W - 92.50 J & H - 32.50 7,600 feet of 16 inch .500 replacement Little Rock, AR Curtis Mason 501/281-4640 Blue Racer 6 X 10 W & J - 51.92 H - 26.76 W - 102.50 J & H - 42.50 24,000 feet of 16 inch new lay Morristown, OH David Mitchell 740/782-1052 N/A 4x8 W & J - 40.00 H - 20.00 W - 92.50 J & H - 32.50 shop / maintenance Arnoldsburg, WV N/A 304/655-7213 Regency Energy Partners 6 X 10 W & J - 51.92 H - 26.76 W - 102.50 J & H - 42.50 20,147 feet of 16 inch and 9,385 feet of 8 inch New Lay Linden, PA Dave Ferguson 570/865-6207 Rice Energy 6 X 10 W & J - 51.92 H - 26.76 W - 102.50 J & H - 42.50 4.2 miles of 24 inch New Lay Mt Morris, PA Andy Hunt 419/464-2461 Mid Ohio Contr Vectren 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 2,400 feet of 16 inch replacement Vandalia, OH Brian Voytko 330/243-3926 Voshell Bros Welding Eastern Shore Natural Gas 5 X 10 W & J - 51.92 H - 22.85 W - 102.50 J & H - 42.50 2 inch - 16 inch station work and misc piping upgrades Dover, DE Ken Jones 302/674-1414 Mark West 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 H - 42.50 9,100 feet of 12 inch and 7,800 feet of 20 inch Moorestown, OH Brian Boyett 740/942-0440 Buckeye 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 6,000 feet of 8 inch replacement Columbus, OH N/A 585/596-9304 City of Senatobia, MS 5X8 W & J - 38.70 H - 17.14 W - 92.50 J & H - 32.50 4 inch pipeline relocation Senatobia, MS n/a 256/718-2041 5 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 20,100 feet of 20 inch and 9,426 feet of 24 inch new lay 12" 45 375 wall & 12" Branch 375 wall Barnesville, OH Nathen Lampton 740/425-4050 T J Construction Southern Pipeline Ace Pipeline B Miller Excavating Price Gregory Precision Pipeline CBC Pipeline Otis Eastern T J Construction Pipeline Energy Group - Carl Smith Mark West 2/4/2015 9:31 AM Pre Jobs 9735 9193 9750 9190 8977 9729 9724 9747 9163 9177 8890 8891 11/28/14 11/21/14 11/17/14 11/17/14 11/12/14 11/4/14 11/3/14 11/3/14 10/21/14 10/9/14 9/23/14 9/23/14 2/27/15 2/1/15 3 months 1/24/15 12/24/14 on going 12/30/14 6 to 8 weeks 6 weeks 1/15/15 11/12/14 11/12/14 Snelson Companies Minnesota LTD Minnesota LTD Union Pipeline Wayne Holden Mid Ohio Contr Precision Pipeline Wayne Holden U S Trinity Energy Henkels & McCoy U S Trinity Energy U S Trinity Energy 6 X 10 W & J - 51.92 H - 26.18 W - 102.50 J & H - 42.50 16 miles of 10 inch new lay 12" 45 250 wall & 12" Branch 250 wall Moundsville, WV Colby Shaffer 304/843-7230 Rice Energy 6 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 3 miles of 24 inch, 3 miles of 18 inch, 4.3 miles of 24 inch, and 4.3 miles of 16 inch plastic 12" 45 375 wall & 12" Branch 250 wall Belmont, OH Jim Tyson 763/262-7000 Enbridge Energy 5 X 10 W & J - 51.92 H - 24.12 W - 102.50 J & H - 42.50 $50.00 sub pay for days worked Station Construction Clearbrook, MN Curt Quam N/A Polycorp / Mark West 5 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 14,400 feet of 12 inch new lay Jerusalem, OH Mike Fisher n/a Center Point Energy 6 X 10 W & J - 38.70 H - 17.14 W - 92.50 J & H - 32.50 anomaly digs and up grade Jackson, MS Darrell Akin 870/772-7172 EQT 5 X 10 W & J - 51.92 H - 26.76 W - 102.50 J & H - 42.50 4,000 feet of 20 inch new lay Waynesburg, PA Adam Kandle N/A Access Midstream 6 X 10 W & J - 51.92 H - 26.76 W - 102.50 J & H - 42.50 4.2 miles of 6 inch, 8 inch, & 10 inch - 500 feet of 16 inch - 2,500 feet of 20 inch 2" 45 312 wall & 6" 45 500 wall all DH 6010 & 8010 Towanda, PA N/A 570/265-2042 Center Point Energy 5 X 10 W & J - 38.70 H - 17.14 W - 92.50 J & H - 32.50 23,290 feet of 6 inch main Batesville, AR N/A N/A XTO 5 X 10 W & J - 40.00 H - 20.00 W - 92.50 J & H - 32.50 Station Modifications Ardmore, OK Steve Smith n/a TransCanada 6 X 10 W & J - 51.92 H - 25.74 W - 102.50 J & H - 42.50 install new compressor station piping Shelbyville, IN Gary Mullins 231/624-0795 Endlink 6 X 10 W & J - 40.00 H - 20.00 W - 92.50 J & H - 32.50 Compressor Station 12" BH 250 wall & 12" Branch 250 wall Big Spring, TX Jerry Tomlinson 940/240-5800 Endlink 6 X 10 W & J - 40.00 H - 20.00 W - 92.50 J & H - 32.50 Compressor Station Big Spring, TX N/A 940/489-3082 Blue Racer Midstream 2/4/2015 9:31 AM Pre Jobs 9065 9083 8964 8998 8/19/14 8/4/14 7/14/14 7/1/14 3 to 4 months 9/24/14 11/1/14 12/31/14 Minnesota LTD U S Pipeline U S Pipeline Otis Eastern 6 X 10 W & J - 51.60 H - 22.85 W - 102.50 J & H - 42.50 $50.00 sub pay for days worked integrity work and upgrade in Stations Berthold, ND Tanner Dremmel 763/262-7000 6 X 10 W & J - 51.60 H - 28.95 W - 102.50 J & H - 42.50 5.5 miles of 12 inch and 1.5 miles of 6 inch 12" BH DH & 12" Branch DH 312 wall Tilden, MI Leroy McDougal 501/230-8719 Suncor Energy 6 X 10 W & J - 51.60 H - 22.85 W - 102.50 J & H - 42.50 9.6 miles of 16 inch congested and 1.5 miles of 10 inch 12" 45 375 wall X60 & 2" 45 218 wall B 313 code Brighton, CO Scotty Jackson 281/531-6700 Sun Logistics 5 X 10 W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 anomaly digs 8 inch, 10 inch, and 12 inch Findley, OH N/A N/A Kinder Morgan Northern Natural National Fuel Gas 9012 8924 8877 8925 8911 8920 6/16/14 6/10/14 6/2/14 6/2/14 5/27/14 5/19/14 1 week on going on going on going on going 2 months 5 X 10 W & J - 38.70 H - 20.98 W - 92.50 J & H - 32.50 360 feet of 6 inch steel pipe Brookfield, OH n/a n/a Q3 Contracting 6 X 10 Northern Natural / W & J - 51.92 H - 24.12 X-Cell Energy W - 102.50 J & H - 42.50 1500 feet of 6 inch relocate and 4 miles of 12 inch hydro Eagan, MN N/A 612/499-7873 Alex Paris Const. 5 X 10 W & J - 51.92 H - 26.76 Mark west Energy W - 102.50 J & H - 42.50 4.2 miles of 12 inch new lay Washington, PA Robert Bell N/A 5X8 W & J - 38.70 H - 17.14 W - 92.50 J & H - 32.50 blanket work on stations 16 inch and under 2" 45 500 wall, 12" BH 375 wall, &12" Branch 375 wall Searcy, AR Glenn Gipson JR 501/281-4640 Enbridge Energy 6 X 10 W & J - 51.92 H - 24.12 W - 102.50 H - 42.50 18 inch - 48 inch anomaly digs in Minnesota 1.) 2" schedule 80 on 45 UH 6010 bead DH 6010 HP F&C LH 2. 12" LH sleeve on 45 , 3.) 12" L sleeve on 45, 4.) 6" saddle all LH, 5.3) 6" schedule 40 on 45 7016 bead 7018 out Grand Rapids, MN Scott Maki 218/831-8051 Center Point Energy 5 X 10 W & J - 51.60 H - 22.85 W - 102.50 J & H - 42.50 1,200 feet of 6 inch congested on first loop Batesville, AR n/a 501/729-1147 Kirila Contractors Southern Pipeline Casper Constr McCizer Pipeline Multiple Gas Companies 2/4/2015 9:31 AM Pre Jobs 8904 8796 8792 8587 8741 8704 8498 8496 8550 8454 5/7/14 4/21/14 4/12/14 3/17/14 3/17/14 3/13/14 1/27/14 1/27/14 1/6/14 10/21/13 on going on going on going on going on going on going on going 3 to 4 weeks blanket on going Tie In and Station Work on 16 inch and under 12" BH & 12" Branch 6010 DH 70+ out and 12" BH & " Branch 6010 DH 7018 LH out Berthold, ND Andrew Suermann 701/453-3700 Minnesota LTD Various 6 X 10 W & J - 51.60 H - 22.85 W - 102.50 J & H - 42.50 Wayne Holden Center Point Energy 5 X 10 W & J - 29.57 H - 12.75 W - 92.50 J & H - 32.50 call out blanket work 16 inch & under & station work Little Rock, AR N/A 870/772-7172 Hess 6 X 10 W & J - 51.60 H - 22.85 W - 102.50 J & H - 42.50 Hess gathering flex steel, poly, and steel small diameter pipe 2" 45 500 wall DH bead & HP LH cap Keene, ND Ryan Swartz 763/280-1927 Dominion East Ohio TBA W & J - 51.92 H - 30.16 W - 102.50 J & H - 42.50 various call out work in Ohio Dover, OH Jim Rini N/A 6 X 10 W & J - 51.92 H - 26.18 Antero Resources W - 102.50 J & H - 42.50 4,300 feet of 16 inch pipe new lay 12" BH 375 wall & 12" Branch 375 wall Clarksburg, WV John Starkey 304/623-7804 shop work Winfield, MO N/A N/A Minnesota LTD 5 X 10 Multiple Gas & Oil W & J - 51.92 H - 24.12 Companies W - 102.50 J & H - 42.50 emergency call out & maintenance work in MN Big Lake, MN Tom Lilyerd 763/428-4444 Minnesota LTD Hess 6 X 10 W & J - 51.60 H - 22.85 W - 102.50 J & H - 42.50 $50.00 sub pay for days worked gathering flex steel, poly, and steel small diameter 2" 45 6010 bead 7010 HP F&C Tioga, ND P D McConnaughey N/A Appellation Pre Fab various gas companies 5 X 10 H - 20.00 H - 42.50 fab shop helpers Williamsport, PA N/A 570/601-4765 Dansville, NY N/A 585/226-6244 Minnesota LTD Mid Ohio Contr Rodenburg Diversified Geeding Constr Inc. LMC Industrial various gas & Oil Companies 5 X 10 W & J - 51.92 H - 28.74 W - 102.50 H - 42.50 DTI, Williams, Nat 5 X 10 Grid, & Spectra W & J - 39.89 H - 20.00 W - 102.50 J & H - 42.50 2/4/2015 9:31 AM on going blanket Pre Jobs 8112 7095 4/1/13 10/17/11 on going on going Blue Flame Pipeline Michels / Division of Continental Fab 5 x 10 W & J - 50.27 H - 25.44 Antero Resources W - 102.50 J & H - 42.50 16.75 miles 16 inch & 20 inch pipe and 5 miles 26 inch poly pipe 12" 45 375 wall & 12" Branch Smithburg, WV Brian Fox 304/873-3029 5 X 10 W & J - 29.57 H - 14.00 W - 92.50 J & H - 32.50 pre fabrication on pipeline and station work 1.) 12" Butt DH 6010 root 8018 F&C, 2.) 12" Branch DH 6010 root 8018 F&C, 3.) 1/2 36" GMAW root & FCAW F&C, 4.) 24" GMAW root & SAW F&C Carrollton MO Nathan Owen 660/542-3868 various gas companies 2/4/2015 9:31 AM
© Copyright 2024 ExpyDoc