Capital Improvement Projects - Bexar County

PUBLIC WORKS DEPARTMENT
Project:
Benton City Road
Drainage Structure / Low Water Crossing
Precinct: 1
Location / Limits:
Benton City Rd between Von
Ormy Rd and Jackel Rd, Elm
Creek..
Scope:
Structure replacement will provide
for an improved conveyance of
storm water runoff while having
no adverse impact to the existing
100-years level of Water Surface
Elevation
Status: Complete
Additional Information:
Consultant: HDR Engineering
Bid Opening: Feb. 14, 2014
Contractor: D Plata Construction LLC
Construction Start : 2 Q 2014
Construction Cost: $ 356,906.24
Construction End Date: 4 Q 2014
Joint Bid: None
With Flood Control Component
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project:
Big Country Phase V
Precinct: 1
Location / Limits:
Blue Mesa, Fort Wayne, Black
River, Hatchet Pass, Jarbo
Pass, Cache Path, Yurba Trail,
Two Wells, Fish Springs, Olney
Springs, Potter Valley, Muddy
Peak, Crescent Peak and Mud
Lake.
Scope:
The main purpose of the project is
to reconstruct 14 residential streets
with curb & gutter section, 4-foot
sidewalk including ADA complaint
ramps and driveway approaches.
SAWS joint bid with Bexar County
to replace existing service service
lines within the project.
Status: Construction
Additional Information:
Consultants: LNV / In TEC
Bid Opening: May 3, 2013
Contractor: Olmos Equipment, Inc.
Construction Start : 3 Q 2013
Roadway Construction Cost: $ 5,729,172.71 Construction End Date: 2 Q 2015
Joint Bid : SAWS
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: FM 1957 Potranco Rd
Precinct: 1
Location / Limits:
Loop 1604 to just west of
SH 211
Scope:
Construction will provide for
enhanced connection between
two western relief routes of SH
211 and Loop 1604.
The
proposed
improvements
will
expand the existing two-lane rural
roadway section to an urban
roadway section consisting of two
11-foot lanes, and two 14-foot
shared use lanes, continuous left
turn lane or 14-foot raised center
median within an 80’ ROW
(Minimum).
Status: Final Design , Utility
Relocation / Adjustments
Additional Information:
Consultants: Pape-Dawson / Jacobs
Advertise Date: 1 Q 2015
Contractor: TBD
Construction Start Date: 2 Q 2015
Construction Cost: $ 34,226,011
Construction End Date: 3 Q 2018
Joint Bid: CPS , SAWS
Pass Thru Project (TX DOT)
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: FM 471 Culebra Rd
Precinct: 1 & 2
Location / Limits:
From FM 1560 to Old FM 471.
Scope:
The construction will complete the
capacity gap that currently exists on
FM 471 from FM 1560 to Old FM
471. The proposed improvements
will widen Culebra Road from its
existing two-lane configuration to a
four-lane divided roadway with
anticipated bicycle and pedestrian
amenities.
Status: Final Design
Additional Information:
Consultants: CP&Y / Atkins
Advertise Date: 2 Q 2015
Contractor: TBD
Construction Start Date: 2 Q 2015
Construction Cost: $ 14,719,463
Construction End Date: 4 Q 2016
Joint Bid: SAWS, CPS Gas.
Pass Thru Project (TX DOT)
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: Fischer Rd Phase I
Precinct: 1
Location / Limits:
From Quintana Rd to IH 35 S
Scope:
Project will expand the existing twolane rural roadway section to an
urban roadway section consisting of
two 16-foot travel lanes in each
direction with 6 ft. shoulders, curbs
and sidewalks within an 86’ ROW
(typical).
-
2,100 L.F.
No in flood plain.
One culvert (pipe).
Medio Creek Watershed.
Status: Preliminary.
Additional Information:
Consultants: Garzabury LLC
Advertise Date: TBD
Contractor: TBD
Construction Start Date: TBD
Construction Cost: $ 1,890,000
Construction End Date: TBD
Joint Bid: TBD
Economic Development Project
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project:
Macdona Streets Reconstruction
Precinct: 1
Location / Limits:
Macdona
Subdivision
in
Southwest
Bexar
County,
including next streets:
Commerce St,
Rockport St,
Main St and 3, 4, 5, 6 & 7th St.
,
Scope:
Reconstruction of 24’ rural
roadway
section
and
reestablishing positive drainage
(9 streets).
Status: Complete
Additional Information:
Consultants: CP & Y / Prof Serv. Ind.
Bid Opening: January 10, 2014
Contractor: Tropical Contracting Inc.
Construction Start: 3 Q 2014
Construction Cost: $ 2,464,000.00
Construction End Date: 1 Q 2015
Joint Bid: None
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project:
Precinct:
Old FM 471 & Talley Rd
1
Location / Limits:
Old FM 471 starting and ending
on FM 471 (Culebra Rd) and
Talley Rd from FM 471 (Culebra
Rd) to Old Talley Rd. (South
End).
Scope:
Roadway expansion from 2 lanes
to 3 lanes with curbs, sidewalks
and drainage improvements due
to new schools and development
in the area.
Status: Preliminary
Additional Information:
Consultant: Dannenbaum
Advertise Date:
Contractor: TBD
Construction Start Date:
Construction Cost: $ 10,000,000
Construction End Date: TBD
Joint Bid: TBD
January 30, 2015
TBD
TBD
PUBLIC WORKS DEPARTMENT
Project:
Roft Rd
Precinct: 1
Location / Limits:
From Culebra Rd to Rockwall
Mill Rd. (5,100 L.F.)
Scope:
This project will expand the
existing two-lane rural roadway
section to a mixed rural/urban
roadway section with curb &
sidewalks on the east side of the
roadway
and
drainage
improvements.
Status: Intermediate Design
Additional Information:
Consultant: ARCADIS
Advertise Date: 3 Q 2016
Contractor: TBD
Construction Start Date: 4 Q 2016
Construction Cost: $ 3,100,000
Construction End Date: 4 Q 2017
Joint Bid: TBD
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: SH 211
Precinct: 1
Location / Limits:
From FM 1957 (Potranco Rd) to
FM 471 (Culebra Rd)
Scope:
The
proposed
project
would
construct a new two-lane roadway
connecting the existing sections of
SH 211 from FM 471 (Culebra
Road) to FM 1957 (Potranco Road).
The purpose of the proposed project
is to improve connectivity and
mobility, and provide residents a
through alternative between FM
1957 and FM 471. The total length
of the project is 7.6 miles.
Status: Alternatives Analysis /
Environmental.
Additional Information:
Consultant: Pape-Dawson
Advertise Date: 3 Q 2015
Contractor: TBD
Construction Start Date: 4 Q 2015
Construction Cost: $ 18,100,000
Construction End Date: 3 Q 2017
Joint Bid: N/A
Pass Thru Project (TX DOT)
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: Talley Rd – FM 957
(Potranco Rd) to Wiseman Blvd.
Precinct: 1
Location / Limits:
From FM 1957 (Potranco Rd)
to Wiseman Blvd.
Scope:
Roadway expansion from 2 to 4
lanes with curbs, sidewalks, bike
lanes, turn lanes and drainage
improvements.
Some
ROW
acquisition will be required.
Status: Preliminary.
Additional Information:
Consultant: CP & Y
Advertise Date:
Contractor: TBD
Construction Start Date:
Construction Cost: $ 12,500,000
Construction End Date: TBD
Joint Bid: TBD
January 30, 2015
TBD
TBD
PUBLIC WORKS DEPARTMENT
Project:
West Military Bridge Ext
Precinct: 1
Location / Limits:
West Military Bridge Extension
Scope:
Project consist of construction of
mirror image of existing 32 ft. X
400 ft. bridge parallel over Medio
Creek stripping to accommodate
bike lanes and travel lane each
direction and 5 foot sidewalk.
The
project
included
the
adjustment
/
relocate
/
replacement of CPS gas within
the project limits.
 Status: Complete.
Additional Information:
Consultants: SEA / HJV Assoc / Arias
Bid Opening: Aug 6, 2012
Contractor: Relmco
Construction Start: 3 Q 2012
Construction Cost: $ 1,589,168
Construction End Date: 2 Q 2014
Joint Bid: CPS.
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project:
Watson Rd Phase I
Precinct: 1
Location / Limits:
From Somerset Road to SWISD
Scope:
Watson Rd is currently a 2 lane
roadway
and
will
be
reconstructed to include 4-12’
travel
lanes,
drainage
improvements and pedestrian
amenities.
Status: Planning.
Additional Information:
Consultants: TBD
Bid Opening: TBD
Contractor: TBD
Construction Start: TBD
Construction Cost: $ 6,800,000
Construction End Date: TBD
Joint Bid: TBD
MPO Project
January 30, 2015
PUBLIC WORKS DEPARTMENT
Project: WT Montgomery Road Phase I
Precinct: 1
Location / Limits:
IH 90 West to Lucas Creek
bridge.
Scope:
The main purpose of the project
is to provide much needed
drainage improvements and road
reconstruction
to
the
WT
Montgomery Road.
Status: Final Design
Additional Information:
Consultant:
IDC, Inc.
Advertise Date: 2 Q 2015
Contractor: TBD
Construction Start Date: 2 Q 2015
Construction Cost: $ 5,671,000
Construction End Date: 4 Q 2016
Joint Bid: TBD
January 30, 2015